1 / 21

Trimble  Quantm  Haul Road Optimization

Trimble  Quantm  Haul Road Optimization. Presenters Name. Overview. The haul road problem – what are we trying to solve The Quantm Software Integrated workflows using the Trimble Tablet. Haul roads. The main consideration is optimal grade Reduce fuel consumption Reduce tire wear

doli
Télécharger la présentation

Trimble  Quantm  Haul Road Optimization

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Trimble QuantmHaul Road Optimization Presenters Name

  2. Overview • The haul road problem – what are we trying to solve • The Quantm Software • Integrated workflows using the Trimble Tablet

  3. Haul roads • The main consideration is optimal grade • Reduce fuel consumption • Reduce tire wear • Reduce machine wear • Two main consideration for haul roads • Maintenance, performing analysis on existing haul roads to maintain or improve haul road grade • Site expansion, preforming analysis to create and select new haul roads

  4. Trimble Quantm Alignment Planning System • A unique system route alignment optimization • Applied by mine and site planners • Investigates millions of alignments for: • Faster Project Planning • Reduced Capital Construction and Operating Cost • Better Environmental and Public Outcomes • Thorough Demonstration of Alternatives Analysis

  5. Trimble Quantm Alignment Planning System • Enables the simultaneous consideration of multiple factors during the alternatives analysis phase: • Environmental • Engineering • Economic/Cost • Community

  6. Trimble Quantm Desktop Applications • Planning of haul roads for mining and construction • Traditional alignment planning • Estimation and initial management of project earthworks and mass haul • Design construct value engineering • Alternative analysis during construction

  7. Trimble Quantm Desktop • Key feature – Vertical Optimization • Import CAD road design (horizontal only or 3D) • If 3D, quantity and construction cost of the alignment is calculated • Manual creation and editing horizontal alignment • Vertical optimization of existing design if 3D alignment imported • Vertical optimization and creation of vertical design for 2D or manual 2D alignment • Study are size, 10km x 10km or 20km x 20km licenses • Why buy Desktop? • Entry level solution – scalable to Premium and Service products • Manual creation of geometric alignments with quantities and costs • Vertical-only optimization, horizontal held fixed • Assists earthworks and costs by manipulating vertical of existing alignment

  8. Trimble Quantm Desktop Premium • Key features – Full Optimization • Full horizontal and vertical optimization capabilities in addition to Desktop version • Unseeded - Free to roam optimizations • Seeded - Optimize from initial alignment both horizontally and vertically • Realignment - optimize based on minimizing deviation from existing centreline • 10 x 10, or 20 x 20 km licenses • Why buy Desktop Premium? • Proven capabilities of the Quantm service on the users PC • Optimize existing concept designs vertically • Conduct full scoping, feasibility and final alignment studies, from defining corridors to detailed 3D alignments

  9. Trimble QuantmHaul Road Optimization How It Works

  10. Trimble Quantm Desktop Overview Quantm generates optimized alignments for review

  11. Study Area – Mountainous Terrain (5-8km Road) • Digital Terrain Model • Geometric Parameters • Costs • Constraints

  12. Free to Roam – 100km/h Design Speed Free to Roam Options Low Cost Corridor

  13. Comparing Haul Roads Comparing Quantm Developed existing Initial haul road Option

  14. Comparing Two Alternatives - Same Corridor Profile view

  15. Where are the Major Savings?

  16. Trimble QuantmHaul Road Optimization Haul Road Construction

  17. Infield Haul road definition Quantm Desktop SCS900 *.ttm; *.pro; *.dxf *.ttm; *.dc Alignments, *.ttm; *.pro; *.dxf *.svd; *.svl Business Center- HCE *.tag Grade Control

  18. In field Haul road workflow • Use SCS900 to collect existing Topo information and features. • Transfer TTM surface and feature data from SCS900 to Quantm Desktop (on Tablet) • Maintenance applications collect existing centreline of haul road for vertical optimization, in addition to site features. • New haul roads collect any features (streams, water features etc) • Switch to Quantm Desktop and perform optimization • Transfer resulting haul alignments back to SCS900 for stakeout

  19. Haul Road Stakeout • Detailed ground survey • Additional updates to the model • Staking out the corridor • Export alignment as PRO file • Stake out earthworksfootprint with GPS orTotal Station

  20. Construction • Haul road construction • Export alignment via TBC/TCC to a machine for construction of haul roads

  21. Thank you