How it works the Kanban ? The definitive slideshow to understand how it works the Kanban Method

How it works the Kanban ? The definitive slideshow to understand how it works the Kanban Method Example 1 – Point of Use / Warehouse. What you need prior to start ? (therotical aspects) Why Use Kanban ? Theory of Kanban How to calculate the right number of Kanban Visit

donohues
Télécharger la présentation

How it works the Kanban ? The definitive slideshow to understand how it works the Kanban Method

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. How it works the Kanban ? The definitive slideshow to understand how it works the Kanban Method Example 1 – Point of Use / Warehouse

  2. What you need prior to start ? (therotical aspects) • Why Use Kanban ? • Theory of Kanban • How to calculate the right number of Kanban Visit www.leanlab.name

  3. What you need prior to start ? • Define the Point of Use • A place to put Kanban • The right number of Kanban • A runner/collector of Kanban

  4. Real Example • A point of use (POU) needs balls in 6 pcs / boxes • Consumption is 18 balls / day • The runner pass every day at 10:00 am • The Lead Time to recieve from warehouse = 2 days • Safety Stock fixed at 20% • This means => 8 Kanban Cards in WIP

  5. Monday 8:00 AM – Start Work Warehouse POU

  6. Monday 8:00 AM – Start Work Warehouse POU Kanban Container is Empty

  7. Monday 8:15 AM Warehouse POU

  8. Monday 8:15 AM Warehouse POU First box of balls is open for use

  9. Monday 8:17 AM Warehouse POU Kanban is located in the collection point First box of balls Is open for use

  10. Monday 9:00 AM Warehouse POU

  11. Monday 10:00 AM Warehouse POU

  12. Monday 10:00 AM Warehouse POU The collector arrives

  13. Monday 10:15 AM Warehouse POU Bring the Kanban to the Warehouse

  14. Monday 11:00 AM Warehouse POU In Process – Recieved Monday at 10.15 AM

  15. Monday 11:01 AM Warehouse POU In Process – Recieved Monday at 10.15 AM 1st box is finished

  16. Monday 11:05 AM Warehouse POU Kanban moved In Process – Recieved Monday at 10.15 AM 2nd box is opened

  17. Monday 12:00 PM Warehouse POU In Process – Recieved Monday at 10.15 AM

  18. Monday 12:00 PM Warehouse POU In Process – Recieved Monday at 10.15 AM

  19. Monday 14:00 PM Warehouse POU In Process – Recieved Monday at 10.15 AM 2nd box is finished

  20. Monday 14:00 PM Warehouse POU Kanban Moved In Process – Recieved Monday at 10.15 AM 3rd box is opened

  21. Monday 14:15 PM Warehouse POU In Process – Recieved Monday at 10.15 AM

  22. Monday 17:00 PM – End of Work Warehouse POU In Process – Recieved Monday at 10.15 AM 3rd box is finished

  23. Tueday 8:00 AM – Start Work Warehouse POU In Process – Recieved Monday at 10.15 AM

  24. Tuesday 8:15 AM Warehouse POU In Process – Recieved Monday at 10.15 AM

  25. Tuesday 9:00 AM Warehouse POU In Process – Recieved Monday at 10.15 AM

  26. Tuesday 10:00 AM Warehouse POU In Process – Recieved Monday at 10.15 AM The collector arrives

  27. Tuesday 10:15 AM Warehouse POU In Process – Recieved Monday at 10.15 AM Bring Kanban to Warehouse

  28. Tuesday 10:30 AM Warehouse POU In Process – Recieved Monday at 10.15 AM

  29. Tuesday 17:00 PM – End of Work Warehouse POU In Process – Recieved Monday at 10.15 AM

  30. Wednesday 8:00 AM – Start of Work Warehouse POU In Process – Recieved Monday at 10.15 AM

  31. Wednesday 8:15 AM Warehouse POU In Process – Recieved Monday at 10.15 AM

  32. Wednesday 8:30 AM Stick Kanban on the box Warehouse POU

  33. Wednesday 8:45 AM Warehouse POU In Process – Recieved Tuesday at 10.15 AM

  34. Wednesday 9:30 AM Warehouse POU In Process – Recieved Tuesday at 10.15 AM

  35. Wednesday 10:00 AM Warehouse POU In Process – Recieved Tuesday at 10.15 AM The collector arrives

  36. Wednesday 10:15 AM Warehouse POU In Process – Recieved Tuesday at 10.15 AM Bring Kanban to the Warehouse

  37. Wednesday 17:00 PM – End of Work Warehouse POU Empty in the POU – a warning to warehouse is given In Process – Recieved Tuesday at 10.15 AM

  38. Wednesday 17:00 PM – End of Work Warehouse POU EMPTY is always a Visual Warning In Process – Recieved Tuesday at 10.15 AM

  39. Thursday 8:00 AM – Start of Work Because of warning the material in in POU at 8:00 AM Warehouse POU

  40. Thursday 8:15 AM Warehouse POU

  41. Thursday 8:30 AM Warehouse POU

  42. Thursday 10:00 AM Warehouse POU The collector arrives

  43. Thursday 17:00 PM – End of Work Warehouse POU

  44. Friday 8:00 AM – Start of Work Warehouse POU

  45. Friday 17:00 PM – End of Work Warehouse POU Next Week the same cycle ...

  46. Some Considerations • The WIP is under control (48 balls in 8 boxes) • Is the system too risky of stock-out in the POU and why? Looking carefully at the lead time, if the collector comes at 10.00 AM, the POU start at 8.00 AM and the warehouse brings the boxes at 9.00 AM the lead time to consider is not 2 days but 2 days and 3 hours. In this case the correct lead time to use is round 2.5 days and the kanban system need is: 9 Kanban Cards rather than 8 Kanban Cards

  47. Some Considerations • At the beginning of Kanban Implemetation starts with a safe number of kanban cards and then reduced it when the system will be stable and reliable.

  48. Thank you for your attention Visit us on www.leanlab.name Info.leanlab@gmail.com