Proposed Improvements for I-95/SR 1 Interchange to Address Unacceptable Levels of Service

The proposed modifications to the I-95/SR 1 interchange aim to tackle ten locations currently experiencing failing Levels of Service (LOS) under both existing and future conditions. Key improvements include the provision of Ramp B to enhance the merge from NB SR 1 to NB I-95, widening of I-95 NB north of SR 1 to improve freeway operations, and the separation of local and through traffic to eliminate several weaving issues. Additional measures, such as the relocation of Ramp C, are also set to streamline traffic flow and enhance safety at this critical interchange.

drew
Télécharger la présentation

Proposed Improvements for I-95/SR 1 Interchange to Address Unacceptable Levels of Service

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. N 3 2 1 4 I-95 / SR 1 Interchange Existing Locations Operating at Unacceptable LOS Failing Locations Under Existing Conditions Merge – NB SR 1 to NB I-95 (AM) 1 Freeway – I-95 NB, north of SR 1 (AM) 2 Weave – SB I-95 C-D Road (PM) 3 Weave – SB SR 1 at I-95 (PM) 4 Click for next slide

  2. N 5 3 2 1 4 7 6 I-95 / SR 1 Interchange Future Locations Operating at Unacceptable LOS Failing Locations Under Existing Conditions Merge – NB SR 1 to NB I-95 (AM) 1 Freeway – I-95 NB, north of SR 1 (AM) 2 Weave – SB I-95 C-D Road (PM) 3 Weave – SB SR 1 at I-95 (PM) 4 Additional Failing Locations Under Future Conditions Diverge – SB I-95 to SR 1 C-D Road (PM) 5 Merge – Road A to SR 1 NB (AM) 6 Weave – NB SR 1 between Mall & I-95 (AM) 7 Click for next slide

  3. N 5 3 2 1 4 7 9 10 6 I-95 / SR 1 Interchange Future Locations Operating at Unacceptable LOS Failing Locations Under Existing Conditions Merge – NB SR 1 to NB I-95 (AM) 1 Freeway – I-95 NB, north of SR 1 (AM) 2 Weave – SB I-95 C-D Road (PM) 3 Weave – SB SR 1 at I-95 (PM) 4 Additional Failing Locations Under Future Conditions 8 Diverge – SB I-95 to SR 1 C-D Road (PM) 5 Merge – Road A to SR 1 NB (AM) 6 Weave – NB SR 1 between Mall & I-95 (AM) 7 Additional LOS E Locations Under Future Conditions Weave – NB I-95 at SR 1 (AM) 8 Weave – SB SR 1 between I-95 & Mall (PM) 9 Weave – SB SR 1 between Mall & Road A (PM) 10 Click for next slide

  4. N N Ramp A 5 3 2 1 Ramp B 8 4 Ramp C 7 9 10 6 I-95 / SR 1 Interchange Proposed Improvements The proposed I-95 / SR 1 interchange modifications improve or eliminate all 10 of these locations: Merge – NB SR 1 to NB I-95 (AM) 1 Improved by provision of Ramp B Freeway – I-95 NB, north of SR 1 (AM) 2 Proposed Final Configuration Improved by I-95 widening Weave – SB I-95 C-D Road (PM) 3 Weave – SB SR 1 at I-95 (PM) 4 Eliminated through provision of Ramp A Diverge – SB I-95 to SR 1 C-D Road (PM) 5 Improved by two lane takeoff to Ramp A Merge – Road A to SR 1 NB (AM) 6 Weave – NB SR 1 between Mall & I-95 (AM) 7 Improved by separation of local & through traffic Weave – NB I-95 at SR 1 (AM) 8 Eliminated through relocation of Ramp C Weave – SB SR 1 between I-95 & Mall (PM) 9 Weave – SB SR 1 between Mall & Road A (PM) 10 Improved by separation of local & through traffic