Report on Construct & Equip Wells (Moniter, 6400 South, 1330 East). March 9, 2011. Construct & Equip Wells. Engineer: Hansen, Allen & Luce, Inc. Contractor: Hills Construction, Inc. Contract Award Date: 2/19/2007 Original Contract Amount: $3,802,210

duard
Télécharger la présentation

March 9, 2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Report on Construct & Equip Wells (Moniter, 6400 South, 1330 East) March 9, 2011

  2. Construct & Equip Wells Engineer: Hansen, Allen & Luce, Inc. Contractor: Hills Construction, Inc. Contract Award Date: 2/19/2007 Original Contract Amount: $3,802,210 Final Contract Amount: $4,106,121

  3. Construct & Equip Wells Change Order #1: $12,147 – upsize to 14” pipe at 1330 Change Order #2: $37,818 – upsize pump & motor to 3000 gpm at 1330 well Change Order #3: $60,503 – changes in 1330 E drain line Change Order #4: $21,724 – connect 8600 S 1300 E Well to 24” line Change Order #5: $99,660 – Site work changes Change Order #6: $72,059 – Site work, chemical feed changes, electrical changes

  4. Construct & Equip Wells Moniter Drive Well Depth: 1160’ Diameter: 20” 1,000-hp Motor Equipped Flow Rate: 3,590 GPM

  5. Construct & Equip Wells 6400 South Well Depth: 832’ Diameter: 20” 400-hp Motor, VFD Equipped Flow Rate: 2,442 GPM

  6. Construct & Equip Wells 1330 East Well Depth: 1,100’ Diameter: 20” 700-hp Motor Equipped Flow Rate: 2,442 GPM

More Related