NDSWG Update to ROS – May 2010. ERCOT Database Load Frequency – NDSWG continues to monitor ERCOTs progress on weekly model loads. ERCOT latest expectation is to begin weekly model loads beginning on May 10.
E N D
NDSWG Update to ROS – May 2010 ERCOT Database Load Frequency – NDSWG continues to monitor ERCOTs progress on weekly model loads. ERCOT latest expectation is to begin weekly model loads beginning on May 10. NOGRR034 – OWG approved NDSWG proposal and ERCOT is preparing a impact analysis. As an interim, OWG/NDSWG propose to lower individual point telemetry metrics to current zonal standards. NPRR146 – NDSWG reviewed and commented as requested by ROS. NDSWG would like a 15 day window prior to any database load for ICCP name changes. This item will be discussed as a separate agenda item. Both NDSWG and SSWG continue to engage ERCOT in bi-weekly TSP update calls.