1 / 15

Remediation of the Sydney Tar Ponds Surface Cap

Remediation of the Sydney Tar Ponds Surface Cap. An Overview of a Unique Canadian Site. Nearly 100 years of steel making and coke production Tar Ponds: 81 acres 700,000 tonnes of PAH contaminated sediments 45,000 tonnes of PCB contaminated sediments Coke Ovens: 178 acres

eben
Télécharger la présentation

Remediation of the Sydney Tar Ponds Surface Cap

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Remediation of the Sydney Tar Ponds Surface Cap

  2. An Overview of a Unique Canadian Site • Nearly 100 years of steel making and coke production • Tar Ponds: 81 acres • 700,000 tonnes of PAH contaminated sediments • 45,000 tonnes of PCB contaminated sediments • Coke Ovens: 178 acres • 3,000 tonnes of PAH & VOC contaminated soil • 25,000 tonnes of coal tar in tar cell

  3. BATTERY POINT NARROWS NORTH POND FERRY STREET SOUTH POND COOLING POND COKE OVEN BROOK PRINCE STREET WASH BROOK Tar Ponds Site Aerial View

  4. Remediation of the Sydney Tar Ponds - Surface Cap

  5. Remediation of the Sydney Tar Ponds - Surface Cap Recent Capping Narrows Stage 2 3 Active S/S Remediation 2 1 Remaining S/S Remediation Excavate Sediments

  6. Important Project Components • Environmental Protection • Health and Safety • Quality Control • Traffic Management

  7. Environmental Protection Environmental Protection Plan • Site Access, Restricting Public Access and Access Roads • Product Handling and Storage of controlled products • Equipment Maintenance and Fueling • Site Generated Waste • Air Management • Erosion and Sediment Control • Decontamination • Water and Fish Management

  8. Quality Control Independent Quality Assurance Plan Independent Quality Assurance Consultants Contractor Quality Control Plan Quality Control Lead QC Testing and Inspection

  9. Health and Safety Master Health and Safety Plan (MHASP) Assignment Health and Safety Plan (AHASP) • Training • Hazard Identification/Assessment and Management • Inspections • Incident Reporting • JOSH Committees and Reps • PPE • Communication (H&S Meetings) • Emergency Response Plan • Occupation Air Monitoring • Site Control (zones, security)

  10. Project Material

  11. Vendor Notes • Trucking provided by a local supplier serving the community for over 45 years • Trucks loads will be covered, and trucks leaving the Tar Ponds site will be cleaned by automated truck wash

  12. Hauling Route - Overview

  13. Hauling Route – Frenchvale to Highway 125

  14. Hauling Route – Grand Lake Road to Site

  15. Discussion

More Related