1 / 20

Background

Background. The electrification programme was started by Eskom during the late 1980’s It was further refined by the National Electrification Forum (NELF) during the early 1990’s. Access to electricity for households in RSA was approximately 30%.

edison
Télécharger la présentation

Background

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Background • The electrification programme was started by Eskom during the late 1980’s • It was further refined by the National Electrification Forum (NELF) during the early 1990’s. • Access to electricity for households in RSA was approximately 30%. • During this period the electrification programme was funded through the National Electricity Regulator (NER)

  2. Background Cont. • After 1994 and through the government’s initiative of RDP (Reconstruction and Development Programme), electrification programme was endorsed. • During 2001 the government took responsibility for funding electrification programme. • The funds are made available from the fiscas • President’s State of Nation Address (universal access in RSA by 2012)

  3. MANDATE OF INEP • To manage the electrification planning, funding and implementation process, with the aim of addressing electrification backlog so as to reach universal access by 2012. • Our Focus areas • Managing the electrification planning process • Managing the electrification funding allocation • process • Managing the electrification implementation process • Monitor the INEP in line with the Energy white paper, • the Division ofRevenue Act (DoRA, Public • Finance Management Act (PFMA),ER Act, OHS Act • etc.

  4. SITUATIONAL ANALYSIS

  5. National backlog (Households)

  6. National backlog cont.(H/H)

  7. National backlog (Schools and Clinics)

  8. Electricity value chain GENERATION Electricity is Generated by burning of fossil fuels (coal, oil, or natural gas), use of nuclear technology and hydro capability 2 TRANSMISSION SUBSTATIONS MUNICIPALITIES 1 TRANSMISSION LINES 3 TRANSMISSION (400/275 kV) High Voltage electricity is carried between Generation and required Distribution through Transmission networks (or Transmission grids) DISTRIBUTION LINES POWER STATIONS DISTRIBUTION (132/33 kV) The distribution networks collect ‘stepped down’ electricity from the transmission networks and deliver it to Redistributors /End Users DISTRIBUTION SUBSTATIONS The voltage levels of electricity are further transformed to meet Distribution requirements SERVICE CONNECTION RETICULATION HV LINE (11 & 22kV) Customer consumption is measured at the point of supply in KWh. This information is used to measure and bill consumption levels utilised/sold RETICULATION LV LINE (380/220V)

  9. Electrification Plan (Actual data)

  10. Electrification Projected Trend

  11. CHALLENGES • Challenges in the Electricity industry in South Africa • Ageing electricity infrastructure • Minimum or no investment by respective distributors (municipalities) in the operation and maintenance of the electricity infrastructure to date, hence lack of maintenance. • Increased blackouts and brownouts in the country, concern for quality and security of supply for the 2010 FIFA World cup • Limited or lack of adequate skills at local government level for operation and maintenance electricity infrastructure.

  12. Electrification outputs Project life cycle Pre-Engineering and Detailed design Household connection 80 % • Construction for backbone infrastructure • Poles • Cables MV and LV 15% 5% Start Finish

  13. Electrification outputs Project life cycle Pre-Engineering and Detailed design Household connection 80 % • Construction for backbone infrastructure • Poles • Cables MV and LV 15% 5% Start Finish

  14. Projected outputs for MTEF

  15. DoRA FRAMEWORK

  16. Comments (current) • Current framework support the projected outputs • Connections for households, schools and clinics • Building of bulk infrastructure • Assist in monitoring performance • Reallocate funding were is required (if necessary)

  17. Comments (future) • Have a schedule that allows funding of DSM and Energy Efficiency initiatives for municipalities • Framework outputs • MW shifted through the programme • Assist in monitoring performance • Process to be initiated with National Treasury

  18. INSTITUTIONAL AND LEGISLATIVE FRAMEWORK • Electricity Regulation Act (Act. No 4 of 2006) completed, will be used to: • Monitor compliance to the quality of supply regulations (to be completed by the end of October 2006. • Enforce penalties to distributors for non-compliance • Improve integration during planning process with municipal IDP. • Eskom progress report to municipalities as per DoRa requirement

  19. THANK YOU Questions….?

More Related