1 / 46

CF Overview & Status

CF Overview & Status. Design Status CMGC Status Latest VE Decisions CF Total Estimated Cost Beneficial Occupancy Dates CF Organization Summary. Design Status. √ Title I - completed May 04 √ Interim services by JE between Title I/Title II – completed at the start of Title II

efrem
Télécharger la présentation

CF Overview & Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CF Overview & Status Design Status CMGC Status Latest VE Decisions CF Total Estimated Cost Beneficial Occupancy Dates CF Organization Summary

  2. Design Status • √ Title I - completed May 04 • √ Interim services by JE between Title I/Title II – completed at the start of Title II • √ Final Tunneling Memorandum and Geotechnical Investigation Report completed Jan 05 • √ Geotechnical Baseline Report (GBR) awarded April 05 to HatchMott MacDonald

  3. Design Status – cont’d • √ Title II AE Design Kickoff March 29-30 • √ 30% design review was performed in Aug-Sept 05 • Meeting was held at JE Cypress facility to review sum total of <1,000 comments from the various disciplines • 100% civil design delivered Oct 26, 05 • Road-work for North Access Road/Survey Tower Road • Open excavation at EBD/FEE/NEH

  4. Design Status – cont’d • 60% design review scheduled for Oct 28 (will likely be delayed ~ 3 weeks as a result of recent VE decisions) • 100% design review Jan 18, 05 • Progress drawings for design reviews are available at http://www-ssrl.slac.stanford.edu/lcls/cf/ • When performing design reviews… • A commitment for a timely review and response back to JE is necessary • system mgrs • citizen committees • various groups and departments, i.e. CEF, ES&H, SU

  5. Design Status – cont’d • 30% construction cost estimate delivered by JE Oct 4, 05 ($74.3M) • Title I Estimate $50.2M • DCN process was followed for all design changes to include estimated hard cost • Valued at ~$3.5M • 30% independent cost estimate delivered by WDWC Oct 7, 05 ($66.4M) • Title I Estimate $72M • Reconciliation report needs to be completed

  6. CMGC Status • Approved! • SO DOE • Chicago DOE • Washington DOE • Awarded to Turner Construction (TC) Oct 17, 05 • Phase I - $.6M • Phase II - $12M • Incentive Fee - $.55M • Safety • Schedule

  7. CM/GC Phase 1 Effort • Phase 1 – preconstruction activities to include: • Provide effective overlap period and oversight of effort during Title II • Estimates during Title II • CPM Schedule • Identify lead-time for critical items • Design coordination • Constructability reviews • Value Engineering reviews • Site investigation

  8. CM/GC Phase 1 Effort – cont’d • Develop construction bid packages • Develop list and contact potential bidders • Develop prequalification criteria • Solicit bids • Recommend award to SLAC for approval of subcontractor • Award contract to subcontractors

  9. CM/GC Phase 1 Effort – cont’d • Develop Project Management Plan (PMP) • Construction Management Plan – outlines project scope, organization, and specific approach to accomplish project • Project Safety Plan – project specific identifying job hazards, safety performance and individuals responsible for project safety • Procurement Plan – identifies systems, methods and procedures for solicitation to subcontractors • Quality Control and Assurance Plan – method of controlling time, cost and quality of various management tasks specific to the project

  10. CM/GC Phase 2 Effort • Phase 2 – CM/GC shall provide all materials, labor, and services required to construct the Project • All general conditions including field personnel, office staff, temporary offices, temporary construction, safety implementation, construction equipment, coordination of all subs, project administration, construction waste management, commissioning

  11. CMGC Status – cont’d • Held Kick-off meeting Oct 19, 05 • Delivered cost estimates from both JE and WDWC • AE Design schedule • Other data was relayed i.e. weekly Owner/Architect/Contractor (OAC) meetings, etc • Critical message • Safety First! • Cost estimate for CLOC • Construction sequencing, particularly the demolition of FFTB • Civil work • North Access Road • Open cut • Schedule of preparation of procurement packages for construction • Remaining Phase II work

  12. Cost Estimates Largest variance! JE Est WDWC Est

  13. Title II JE Cost Summary by CSI Title II Est $74.4M Title I Est $50M Variance $24.1M↑

  14. Title II JE Cost Summary by CSI Site-work $4.2M (TI) vs $7.4 (TII) delta of $3.2M↑ Mechanical $8M (TI) vs $13.4M (TII) delta of $5.4M↑ Electrical $5.8M (TI) vs $12.8 (TII) delta of $7M↑

  15. Title II JE Cost Summary by Area • Areas with most significant increase: • UH $4.3M →$10.9M • NEH $6.4M →$9.6M • CUP $395K →$2.8M • XRT $3.8M →$5.7M • FEH $6M →$10.7M • CLOC $12.9M →$21.3M

  16. Title II Breakdown by Structure (with Area)

  17. Cost Estimate • Delta results in reduction in scope of various items • To date $11M worth of scope has been reduced • Total value of items continue to fall short of remaining in the box by ~$3.6M

  18. VE Scope Reductions - Tunneling

  19. T2 – shorten xrt 60’ and access tunnel 40’ • T3a – enlarge access tunnel to 19’ • T5a/b – square off transition tunnel, shift FEH 60’ to the west (T2) • T6 – cut/cover FEH (not approved) XRT/FEH Tunnel Floor Plan

  20. Architectural, Site, Finishes

  21. Architectural, Site, Finishes – cont’d

  22. A01 – Delete masonry veneer NEH – Service Yard Entrance

  23. A15 – Reduce glazing

  24. A07 – 3rd floor shell only, no interior build out CLOC Floor Plan 3rd Floor

  25. A12 – Eliminate Conf Ctr Conf Center Floor Plan Conf Center Elevation

  26. Architectural, Site, Finishes – cont’d

  27. G08 – use pan form concrete NEH Cross Section

  28. G10 – reduce size of basement level shaft NEH Floor Plan – Basement Level

  29. Architectural, Site, Finishes – cont’d

  30. S06 – replace screen wall at CUP service yard w/ 8’ mesh fence Site Plan

  31. S04 – reduce retaining walls S03 – reduce excavated bowl Site Plan - CLOC

  32. Mechanical Scope Reductions

  33. Mechanical Scope Reductions – cont’d

  34. Mechanical Scope Reductions – cont’d

  35. M13 – place baseline UH design with alt plan

  36. Mechanical Scope Reductions – cont’d

  37. Electrical Scope Reductions

  38. Electrical Scope Reductions – cont’d

  39. Summary of Scope Reductions • Tunneling - $.847M • Architectural, Structural, General - $4.484M • Mechanical - $3.782M • Electrical - $1.762M • Running Total = ~$11M • All cost reductions have been approved by Systems Managers and Project Office.

  40. BTH UNDULATOR HALL ELECTRON BEAM DUMP & FEE NEAR EXPERIMENTAL HALL AND CENTRAL LABS & OFFICE X-RAY TRANSPORT & DIAGNOSTICS TUNNEL FAR EXPERIMENTAL HALL (redesign) LCLS CF Rendering At grade in RSY Location of Pep Ring Rd Cut & Cover

  41. CF Cost Estimate – Aug 05 Total CF Cost = $80.6M

  42. Beneficial Occupancy Dates (L3 and L4) Sector 20 3/31/06 MMF 4/3/06

  43. CF Staff FY 06-08

  44. Summary • Open Issues… • Prepare for upcoming Lehman visit on Nov 17, 05 • Demonstrate readiness for CD-3 Review (7-9 February 2006) • Title II 60% design review coming shortly (?) • Geotechnical Baseline Report (GBR) in process, due in parallel with design by outside separate consultant • Independent Seismic Peer Reviewer on-board and working with JE (Forell/Elsesser Engineers, Inc.) • S20 and MMF to complete construction in the next 120 calendar days by XL Construction • Changes will delay BO date

  45. Summary – cont’d • Turner Construction (TC) to begin full steam ahead • Conduct cost estimate and major planning, conduct VE and constructability reviews, project schedule and develop bid packages • Possible advancement Phase II effort • RSY North Access Road [1] • Memo was sent SSO requesting approval to commence this activity • Open-cut of NEH area [1] ? • Utility investigation? • Title III Construction for RSY – CLOC by TC (03/06) • MEP Technical Review will be required within the next 4 weeks • Resolution to additional near future de-scope items

  46. End of presentation

More Related