1 / 69

Floor Screeding

Floor Screeding. Lesson no 1. Learning outcomes by the end of this lesson you should be able to. Identify the bonded floor screed Describe the monolithic floor screed Recognise a Floating screed. Types of floor screed systems. Bonded. (Monolithic.) Un Bonded Floating screed.

elana
Télécharger la présentation

Floor Screeding

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Floor Screeding Lesson no 1

  2. Learning outcomesby the end of this lesson you should be able to • Identify the bonded floor screed • Describe the monolithic floor screed • Recognise a Floating screed

  3. Types of floor screed systems • Bonded. (Monolithic.) • Un Bonded • Floating screed

  4. Bonded ( monolithic) floor screed • Bonded systems tend to be the most common methods it fits better with the nature of construction and the set and leave approach of concrete. • In this method a screed is applied to a previously laid concrete base • Bonded thickness is from 25mm to 40mm

  5. Bonded floor screed

  6. Un Bonded floor screed • An unbonded floor is where no bond to the concrete base is possible owing to its condition. Minimum thickness is 50mm. • A number of different forms of floor construction are included in this type, and are often grouped on their own, e.g. laying a screed on a damp-proof sheet membrane.

  7. Un Bonded floor screed

  8. Floating floor screed • Floating screed • • An Floating screed floor is where no bond to the concrete base is possible owing to its condition. Minimum thickness is 50mm. • • A number of different forms of floor construction are included in this type, and are often grouped on their own, e.g. laying a creed on a damp-proof sheet membrane, and laying a floor on a layer of insulation

  9. Floating floor screed

  10. Task • 1. How much mixed material is needed to complete a floor screed 5.000 m long by 4.000 m wide • and 0.050 m thick? • Answer • 1 m3

  11. Task • Tools and equipment for floor screeding will generally include: • sweeping brush, trowel, float, mixer, shovel • splash brush, small tool, gauger, trowel, float • spirit level, trowel, buckets, mixer, float • levelling equipment, trowel, float, shovel buckets, mixer • Answer • 4

  12. Answer

  13. Types of materials used • Mixing is one of the most important jobs of the whole operation • The quality of the sand is important and must be sharp,gritty and clean • The mix ratio is 3 parts sand and 1 part cement

  14. Types of materials used • Some floors are laid using granite chipping • On large work , a pump mixer can be used.this will increase productivity and ensure an even mix

  15. Preparation of floors • Remove all loose particles and high points on the floor • Brush all the area to remove dust • For certain floor surfaces , a mix of cement slurry and P.V.A can be brushed into the surface • Smooth surface should be scrabbled to form a key

  16. Question Plastic sheeting below the structural floor is the: • damp proof membrane • vapour barrier • moisture trap • aid to curing the floor Answer • damp proof membrane

  17. Question • The type of cement used in floor screeds is: • Masonry Portland • Extra Portland • Rapid Portland • Ordinary Portland Answer Ordinary Portland

  18. Finishes • • Floors are generally finished with either a floated or trowelled surface. • • A wood fl oat produces a sand-faced texture. • • Trowelling gives a smooth finish which closes in the surface of a wood fl oat finish. • • Power floats, tampers and rollers can be used to assist the floor layer.

  19. Finishes • Float finish • These are laid mainly to receive mastic asphalt, asphalt tiles, bitumen, concrete tiles and other heavy finishes. • Trowel finish • These are laid mainly to receive carpet, hardboard, vinyl and cork tiles.

  20. Task make a copy of this chart

  21. Questions • What is one of the most important jobs in the whole operation • Answer • Mixing is one of the most important jobs of the whole operation • What is the mix ratio of a floor screed • Answer • The mix ratio is 3 parts sand and 1 part cement

  22. Curing • It is essential that sufficient moisture is available for the continued hydration, or setting action, between the Portland cement and water for up to seven days after laying. • This is achieved by restricting the moisture loss of evaporation from the mix by covering • the finished topping with: • Building paper. • Polythene sheets. • Damp hessian sacks.

  23. A floor scrabbling machine • How do we key a smooth floor to receive a screed • Answer • With a scrabbling machine • Basic floor • Scrabbled floor • Scrabbling machine

  24. Grinding High Spots • The screed is ground using a power operated grinding machine. • Throughout the process the surface is kept wet. • Any ground material is removed using squeegees or some modern grinders collect the material as they operate

  25. Question • How should we prepare the floor to receive a screed • Answer • Remove all loose particles and high points on the floor • Brush all the area to remove dust

  26. Floor screeding • Floor area is calculated by volume • i.e length x width x depth. • Length = 29m, x width = 30m, x depth = 0.035mm, = 30.45 m3

  27. Question • How do we key a smooth floor to receive a screed • Answer • With a scrabbling machine

  28. Monolithic floor screed • Monolithic in construction terminology means 'one body' or 'laid as one'. • That is to say when materials such as a concrete base and its screed are laid within three hours, they are deemed to be laid as one • Monolithic thickness is from 10mm to 15mm

  29. Question • Name the three types of floor screed • Answer • Bonded (Monolithic) • Un-bonded • Floating screed

  30. Floor screeding • Monolithic thickness is from 10mm to 15mm • Un-bonded thickness is 50mm • Bonded thickness is from 25mm to 40mm • Separate Minimum thickness is 40mm..

  31. Task • Now work in groups to answer questions 14-22 on pages 324 –326 of your work book

  32. Floor Screed Lesson no 2

  33. Floor screedingby the end of this lesson you should be able to • Recall why we use a datum line, and how to set out levels • Understand the term Curing • Be aware of common faults that might occur when floor screeding

  34. Recap on lesson no 1 • Name four types of floor screed Answer • Monolithic • Bonded • Un-bonded • Floating screed How do we key a smooth floor to receive a screed • Answer • With a scrabbling machine

  35. Recap on lesson no 1 • How should we prepare the floor to receive a screed • Answer • Remove all loose particles and high points on the floor • Brush all the area to remove dust

  36. Datum line • A datum line is a level line around the room • This can be drawn by using a sprit level , or a laser level, or a water level. • The height of the screed can be set from the datum line by using a builders square

  37. Water level • The green pipe is filled with water . • Then with two operatives each take an end of the water level, • By raising the end of the water level up or down they will both reach a point where both reading are the same • At this point a mark will be made on the wall, this is a datum point,from which datum lines can then be drawn

  38. Water level • Setting datum level to wall areas • Set the liquid container at a suitable height for working • Set adjustable gauge to zero at the level of liquid in container

  39. Water level • Move instrument rod 3 from station point 1 to point 2,3,4 in sequence. • Raise or lower the rod until liquid is at zero on gauge and then mark this datum point on the wall at each of the points 1 – 2 • Join up station points to obtain level datum line

  40. Water level

  41. Water level

  42. Laser level • The laser level will project a level line around the room it is located in

  43. Laser level

  44. Laser level

More Related