1 / 10

Galt Court Water Main Replacement

Galt Court Water Main Replacement. Georgetown Village Community Woodbridge District Town Hall Meeting January 23, 2019. Service Authority Project Manager: M. Elena Herrera, P.E. Engineering Consultant: Pennoni Associates Inc. Contractor: AVES Construction. Agenda. Project Background

eleanorab
Télécharger la présentation

Galt Court Water Main Replacement

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Galt Court Water Main Replacement Georgetown Village Community Woodbridge District Town Hall Meeting January 23, 2019 Service Authority Project Manager: M. Elena Herrera, P.E. Engineering Consultant: Pennoni Associates Inc. Contractor: AVES Construction

  2. Agenda • Project Background • Purpose of Project • Project Layout and Limits of Construction • Project Schedule • Service Authority Commitments • Q&A

  3. Project Background • The existing cast iron pipe water mains are dated from 1971. • Since 2010 there have been over 10 water main breaks in Galt Court. • April 2017 - Pennoni Associates initiated design. • Summer 2018 – Service Authority replaced all water meters in Galt Court. • January 2019 – The Service Authority Board of Directors approved the construction contract with AVES Construction.

  4. Improve system hydraulics and reliability Improve customer level of service Improve safety of the community by adding a hydrant Relocate the water mains to minimize customer inconvenience Enhance system components such as meter assemblies Purpose of the Project

  5. Project Layout and Limits of Construction Limits of Construction New Water Mains and Hydrant

  6. Project Schedule • On-site construction is scheduled to begin in spring 2019 • 150 days to final completion • Dependent weather conditions • Hour of construction will be limited to weekdays from 7:00am to 5:00pm

  7. Service Authority Commitments To restore area affected by construction to original or better condition. • Includes pavement restoration of the court. To maintain road access at all times. • Emergency services, trash, mail, school buses and other services. • To communicate with HOA concerning project status. • To respond to residents’ concerns. • To notify customers about parking disruptions for daily operations. • Customers will be notified a minimum of 24 hrsin advance.

  8. Service Authority Commitments • To maintain water service. • Except for interruptions during water service reconnection. • Customers will be notified a minimum of 24 hrsin advance. No work will be performed outside of the hours of construction without prior authorization from the Service Authority. Daily clean-up by the Contractor is required. Service Authority Inspector on site daily and as necessary.

  9. Service Authority Commitments Pavement Restoration Area to be Repaved

  10. Questions and Contacts • Project e-mail address galtcourt@pwcsa.org • Project website • https://www.pwcsa.org/galt-court-water-main-replacement-project • Service Authority Project Manager M. Elena Herrera, PE Phone: (703) 335-8927 • Questions?

More Related