An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Golden Triangle Blvd.Progress Report March 27, 2007

  2. Funding • City ……………… $7.3 Million • County…………… $7.3 Million • Federal…………… $11.0 Million $25.6 Million

  3. Current

  4. 2004 2007

  5. Proposed Urban Design Median/Left Turn Lanes Curb & Gutter Sidewalks Drainage Improvement $18.3 Million 50+ Year (permanent fix) Alternative Rural Road Barrow Ditches Federal Strings (6-8 months) 5-10 Year (Band-Aid) Re-prioritization +-

  6. Current Maintenance/Improvements • Constructing Beach St. at Alta Vista • Left Turn Lanes • Re-timing Traffic Signals • Major Surface Repair (500 tons) • Re-stripe Roadway • Drainage west of SH 377 • Keller-Hicks at Alta Vista

  7. http//www.fortworthgov.org/tpw Project Status Link

  8. $7.3M PLAN Rehabilitate Existing Roadway(Approx. Life 5 Years) Two New Lanes (Approx. Life 10 Years) Ditch Ditch Ditch

  9. $25.6M PLAN • 4-Lane Divided Arterial with Curb and Gutter • Raised Median • Underground Drainage • Traffic Signals • Left & Right Turn Lanes

  10. FEDERAL FUNDING REQUIREMENTS • Environmental Assessment • Coordination with multiple agencies • Public Involvement • TxDOT / FHWA Review and Approval Processes • 30%, 60%, 90%, 100% Reviews • Bridge Design Review in Austin • Plan Review in Austin (6 months)

  11. TIMELINE (URBAN ROADWAY)

  12. TIMELINE (RURAL ROADWAY)

  13. CONCLUSION - Councilman Espino Is 8 months worth $18.3 million?