The GRID and the Cardiff LAN upgrade

The GRID and the Cardiff LAN upgrade. Tom Wiersma INFOS 22 July 2003. The Cardiff LAN upgrade

elijah
Télécharger la présentation

The GRID and the Cardiff LAN upgrade

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The GRID and the Cardiff LAN upgrade Tom Wiersma INFOS 22 July 2003

  2. The Cardiff LAN upgrade A major joint project involving Cardiff University and the University of Wales College of Medicine to install a high speed local area network. SRIF funding targets GRID and research stakeholders and HEFCW Teaching and Learning funding ensures campus wide connectivity. GRID and Cardiff LAN

  3. GRID and Cardiff LAN • Pervasive Networks LTD Contract Holders • Foundry Hardware • 10 GE backbone moving to 40 GE • 1000 Gigabit Server Connections • 20,000 100 Mbps user outlets • “Next Generation” hardware (2004) • Up to 100 Virtual NetScreen Firewalls

  4. GRID and Cardiff LAN Modular design methodology, allowing organic growth and based on: • Core – Very High throughput switches and fibres linking major locations • Distribution – Providing high bandwidth high availability within major locations • Edge – Delivering services to customers

  5. GRID and Cardiff LAN

  6. GRID and Cardiff LAN

  7. GRID and Cardiff LAN Benefits • High bandwidth • Better Security • Better Resilience • Managed access through use of Communities

  8. GRID and Cardiff LAN Installation Timetable • CU “Core”, “Distribution” and limited “Edge” (SRIF) – Completed May 2003 • CU remaining “Distribution” and “Edge” (HEFCW T&L) – August 2003 • UWCM – By October 2003

  9. GRID and Cardiff LAN

  10. GRID and Cardiff LAN Project Stages • STAGE IEmulates existing Layer 2 network Completion September 2003 • STAGE IIMigration to Layer 3 network communitiesFoundry MG8 40GE installation Completion August 2004

  11. GRID and Cardiff LAN

  12. GRID and Cardiff LAN

  13. GRID and Cardiff LAN Issues • Engineering problems • Migration • External connectivity • Cost

  14. GRID and Cardiff LAN Short Term Actions • Resolve engineering issues • Solicit for trial GRID users • Layer 2 Migration

  15. GRID and Cardiff LAN What are we aiming for? To be able to go anywhere at anytime for any amount of safe, diverse data INSTANTLY Questions?