Project Management. Maintenance and Reliability. 14 Aug 2001. Introduction. What – Project Management Where – Where the success or failure of a project will have major consequences for the company

1 / 32

Télécharger la présentation

Project Management. Maintenance and Reliability

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management. Maintenance and Reliability 14 Aug 2001

  2. Introduction • What – Project Management • Where – Where the success or failure of a project will have major consequences for the company • Why – At some point every company takes on large and complicated projects – opening a new store, building a plant, developing a product

  3. Project Management • What is at stake? • Large projects, outside of normal production • Cost overruns • Late completion – penalties • Early completion – bonuses

  4.  Project Planning • Project organization • Project manager

  5. Project Planning • Planning Task • Work Breakdown Structure • Determines gross requirements for people, supplies and equipment

  6. Work Breakdown Structure • Level • 1 Project • 2 Major tasks • 3 Subtasks • 4 Activities

  7. Example • Level • 1 Open a new Retail Outlet • 2 Select Location • 2 Refurbish Location • 3 Signage • 4 Install new sign • 3 Displays • 4 Install racks • 4 Install Mannequins

  8. Project Scheduling • Sequence project activities • Allotting time

  9. Gantt Chart

  10. Project Controlling • Monitor resources, costs, quality, and budgets • Use feedback to revise project plan

  11. PERT and CPM • Program Evaluation and Review Technique • Critical Path Method • Schedule, monitor and control large projects

  12. PERT and CPM Framework • Define project • Develop relationships among activities • Draw network connecting activities • Assign time / cost estimates to each activity • Compute longest time path through network – the critical path • Use network to plan, schedule, monitor, control project

  13. Difference Between PERT and CPM • CPM – one estimate of time • PERT three estimates with probabilities

  14. Project: Obtain a college degree (B.S.) Receive diploma Register Attend class, study etc. 1 2 4 Years Activity (Arrow) Event (Node) Event (Node) PERT Symbols

  15. 2 A 1 3 B A & B can occur concurrently PERT Symbols

  16. A must be done before C & D can begin 2 D A C 1 4 3 B PERT Symbols

  17. 2 D A C 1 4 3 B E B & C must be done before E can begin PERT Symbols

  18. Activity Time Estimates • Optimistic Time (a) • Most Likely Time (m) • Pessimistic Time (b) • Beta distribution • Expected Time t = (a + 4m + b) / 6 • Variance v = [(b – a)/6]2

  19. Critical Path Analysis • ES – Earliest Start Time • LS – Latest Start Time • EF – Earliest Finish • LF – Latest Finish • S – Slack Time – LS – ES • Critical Path – Group of activities in the project that have a slack time of zero • T – total project completion time • V – total variance of activities on the critical path

  20. Project Crashing • Crashing – shorten activity time by adding resources • Can be expensive – may be less expensive than cost penalties

  21. PERT Advantages • Useful at several stages, especially scheduling and control • Not mathematically complex • Graphical display show relationships • Critical path pinpoints activities to closely monitor • Documents who is responsible for each activity • Applicable to a wide range of industries • Monitors schedules and costs

  22. PERT Limitations • Project activities clearly defined, independent, stable in their relationships • Precedence relationships must be specified in advance • Time estimates are subjective • Danger of too much emphasis on critical path

  23. Maintenance and Reliability

  24. Introduction • What – maintain capability of system while controlling costs • Where – Where results of failure can be disruptive, wasteful, and expensive in dollars and lives • Why – breakdown – idle facilities – loss of customers

  25. Definitions • Maintenance – all activities involved in keeping a system in working order • Reliability – Probability that a machine function or part will function properly for a specified period of time under stated conditions

  26. Improving Individual Components • If one component fails, entire system could fail • Reliability is the probability of not failing • Assuming the reliability of each component does not depend on the reliability of other components, • Rs = R1 x R2 x R3 x … x Rn

  27. Product Failure Rate • - FR(%) = Number Failures / Number units tested x 100% • FR(N) = Number of failures / Operating time • MTBF = 1 / FR(N)

  28. Providing Redundancy • Back up components with additional components • Rs = R1 + [R2 x (1 – R1)]

  29. Maintenance • Preventative Maintenance – Routine inspections, servicing, and keeping facilities in good repair to prevent failure • Breakdown Maintenance – Equipment fails and must be repaired

  30. Implementing Preventative Maintenance • Maintenance is costly – so when to maintain? • Infant Mortality – high initial failure rate • Once past the Infant Mortality phase, determine MTBF • Requires maintenance and breakdown record-keeping • Difficult to determine full costs of breakdown

  31. Increasing repair capabilities • Must decide where repairs are to be performed • Must decide who will perform repairs • Better to have employees perform as much as possible themselves

  32. Total Productive Maintenance – TPM • Applies TQM concepts to maintenance • Employee involvement • Excellent maintenance records • Designing machines to be reliable, easy to operate, easy to maintain • Emphasizing total cost of ownership when purchasing machines • Developing preventative maintenance plans • Training workers to operate and maintain machines