This communiqué provides an update on the current status of the MEM and EWR operational trials within the DCL framework, highlighting the progress of various patches and builds, specifically Patch 4 and Patch 5. It outlines the installation timelines, testing completions, and operational outcomes observed by June 13, 2013. Key topics include successful DCL operations, revisions issued, and upcoming testing schedules. Significant collaboration with airlines such as UPS, BAW, and SAS is noted, as well as plans for future functionality based on cost and schedule considerations.
E N D
Data Communications Program MEM/EWR ATCT DCL Trials DCIT24 Update To: DCIT24 Plenary From: Matt Maki Date: 06.13.2013
Agenda • Patch 4 Testing Status / MEM-EWR Installs • MEM / EWR Operational Trials Status/Results • Patch 5 / Build 7 Status • MEM Test NCP Extension: JW925-FDIO-1001 / T34501
Current DTAP Patch 4 Outlook • 6/4: Factory Acceptance Testing Completed @ Thales • 6/5: Patch 4 Installed at the WJHTC • 6/6-14: Patch 4 Testing at the WJHTC • 6/17: EWR Install • 6/18-20: EWR Pre-SAT Testing • 6/24: MEM Install (Includes UPS upgrade) • 6/25-27: MEM Pre-SAT Testing along with proposed 6/27 MGT demo - 24x7 Checkpoint
MEM Trials Current Status • Continued FDX Limited Ops (As of 6/13): • 35 to 50 DCL ops ‘shakeout’ period (20 MD-11, 15 B777 ops minimums) • 36 successful CAF DCL issued since April 17 start (28 MD-11, 8 B777) • 34 CAF, 2 UM80 Initial DCLs Issued • 5 UM79 , 3 UM80 Revisions issued • Additional ops up to 6/23 planned • MD-11 UM79 Revisions stopped after May 3 Op due to FDX FD observed en-route FMS Map ‘To Point’ Magenta Line re-draw (back to original route): • Boeing/Honeywell identified and can reproduce issue • Procedural Work around being presented to Flight Deck Working Group at Boeing/Long Beach • EWR/UPS MD-11 to try to duplicate issue • MEM 24x7 Trials Ops ‘Go’ Date pending FDX work around acceptance
EWR Trials Current Status • Continued Limited Ops (As of 6/13): • 6 successful CAF DCL issued since May 16 start (3 MD-11, 2 B777, 1 A340) • 6 CAF DCLs Issued • 2 UM79 , 1 UM80 Revisions issued • Additional ops up to 6/14 planned • Limited Trials Ops can resume 6/21 • Additional ATC DTAP support expected after 6/21 or Refresher Training • Domestic and International Participation: • UPS • BAW • SAS • FDX (pending first Revenue operation) • DLH, DLH Cargo, Swiss Air (pending initial testing)
DTAP Patch 5 and Build 7 Status • DTAP Patch 5 Requirements / Delivery Status: • EWR ATC Requirements (4 Total) • Thales cost/schedule proposal currently undergoing Gov evaluation • Dual Contact / Drop Down Remarks proposal for a summer delivery • Remaining Requirements delivery proposal moved to late Fall • Combine remaining reqs with pending Build 7 proposal/estimate • Thales to Scope Build 7 Requirements for Scope, Schedule Cost: • FAA options to select specific functionality based on schedule/cost consideration • Build Contract Acceptance and Delivery to FAA currently TBD
MEM/EWR Test NCP Status MEM Test NCPs: JW925-HNL-1004 / T34840ZME HADDS Connection (EXTENSION) NAS CCB Approved – 5/2/2013JW925-FDIO-1001 / T34501MEM DTAP FDIO/PCRCU Echo Port ConnectionNCP Issuance Date - 8/25/2012 EWR Test NCPs: JW925-HNL-1003 / T34752ZNY HADDS Connection NAS CCB Approved – 5/2/2013JW925-FDIO-1002 / T34753EWR DTAP FDIO/PCRCU Echo Port Connection NAS CCB Approved – 5/2/2013JW925-ATCT-1002 / T34759EWR DTAP Equipment Space ESA Approved – 3/4/2013