120 likes | 247 Vues
The 2035 Regional Transportation Plan (RTP) Update is essential due to findings by FHWA that our state did not meet "Fiscal Constraint." This update addresses the need for revised STIP/RTPs, reflecting current cost estimates and ensuring available revenues for implementation. The work scope includes demographic considerations, new financial constraints, and conformity determinations. Input from the public and agencies is crucial for outlining project priorities, costs, and enhanced revenue strategies. Participation in the survey at www.2035Plan.org is encouraged.
E N D
2035 RTP UPDATE August 2010
Why Update the RTP? • 2007 - FHWA found State did not meet “Fiscal Constraint” • 2008 - Required revised STIP/RTPs based on YOE Costs • “Froze” 2008-11 STIP • Precipitated new short & long term TxDOT financial forecast • New forecasts significantly lower
What is “Fiscal Constraint” ? Plan considered fiscally constrained if: • Can be implemented with “reasonably available” revenues • Reflects current/updated cost estimatesfor capital projects • Indicates sufficient funding to operate and maintainthe Federal-aid system and Public Transportation
How TxDOT $$ Impact RTP • New 2011-14 TIP, 2015-2020 TxDOT project lists already approved by TPC • Must determine “reasonably available” revenue, project priorities • Projects removed from RTP cannot: • Receive federal environmental clearance • Permit State right of way acquisition • Be part of Air Quality Conformity finding
Work Scope for RTP Update • Same horizon year • Same demographics • New financial constraint • New conformity determination • Revised list of proposed added capacity highway projects
Funding Scenarios ($B) TxDOT Maintenance $2.3 2011-2014 TIP Locally-Sponsored RTP Projects (including toll roads) Transit RTP Projects US 290/IH 610 IC Phase 2 “Baseline” TxDOT Maint. $9.2 Critical Regional Corridors $5.2 “Enhanced” $98.7 Remaining RTP Projects $56.0 TxDOT $6.5 Transit $38.5 Cities & Counties $23.2 Toll Roads $17.4 Baseline $85.7 Additional Funds $69.0 Baseline $85.7 Additional Funds $13.0 Expenditures • Baseline • $85.7 • Enhanced • $98.7 • Full • $154.7 Revenues Total $85.7 Total $98.7 Total $154.7
Development Schedule • AUG – Solicit comments on Baseline, Enhanced & Full RTP scenarios • SEP – Public comment on draft plan • OCT – Approval of final plan & air quality conformity determination
What We Need Public & Agency input on: • Program of projects for each scenario • Project scope & cost information • Priorities • Enhanced revenue strategies • What is acceptable/unacceptable • Other ideas Take the Survey: www.2035Plan.org
Questions? • Becky Blatnica • Becky.Blatnica@h-gac.com • 832-681-2591 • Pat Waskowiak • Patricia.Waskowiak@h-gac.com • 713-993-2478 • www.2035Plan.org