1 / 5

nTof Civil engineering Status -4 February 2014

nTof Civil engineering Status -4 February 2014. Contractor’s main works started on 13/05/2013: Done from the last meeting : Completion of finishing works (doors, painting ) Landscaping Handover of the civil engineering package to CERN/ nTof Project on 27 th January 2014.

enrico
Télécharger la présentation

nTof Civil engineering Status -4 February 2014

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. nTof Civil engineering Status -4 February 2014 • Contractor’s main works started on 13/05/2013: Done from the last meeting: • Completion of finishing works (doors, painting) • Landscaping • Handover of the civil engineering package to CERN/nTof Project on 27th January 2014 L.A.Lopez

  2. Somepictures of the worksfrom the last meeting: Finishingworks: doors, painting

  3. Finishingworks : rails for the crane, «cloche» for the dump

  4. Landscaping

  5. Nextsteps • Start of installation works (by others) → fromJanuary 27th • Completion of snagging items GS-SE: • second layer of black top and finishing of façades → March 2014 • test of ventilation doors → date to bedeteminedwith CV Important reminder Handoveris the stage where responsibility for the building is passed from the Contractor back to the Client. Importantly, the risk in the building passes back to CERN. L.A.Lopez

More Related