Chapter 5. Cost Estimation. Prepared by Diane Tanner University of North Florida. Used by managers to Enable the creation of a cost function so that Costs can be predicted at various activity levels Useful when fixed and variable costs are grouped together Four common methods

eros
Télécharger la présentation

Prepared by Diane Tanner University of North Florida

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 5 Cost Estimation Prepared by Diane Tanner University of North Florida

  2. Used by managers to Enable the creation of a cost function so that Costs can be predicted at various activity levels Useful when fixed and variable costs are grouped together Four common methods Account analysis Scattergraph High-Low Linear regression Cost Estimation Methods 2

  3. The Goal of Cost Estimation 3 Goal is to create a total cost equation TC = VCx + FC Y = mx + b Where: TC = Y = total costs FC = b = fixed costs = y-intercept VC = m = variable cost per unit = slope of function x = units produced/sold Both equations serve the same purpose

  4. Used to estimate fixed and variable costs Step 1: Classify costs as variable or fixed Requires professional judgment Go through the list of costs and separate into two piles—fixed costs versus variable costs Step 2: Determine variable costs per unit Account Analysis Method 4 Total Costs Activity Level • Step 3: Determine fixed costs • Add the costs in the fixed cost group from step 1 Cost function (equation) = TC = VCx + FC

  5. Used to estimate fixed and variable costs to determine how costs and activity levels change Step 1: Acquire cost information over activity levels Step 2: Graph the data points Step 3 : Eyeball a linear relationship and draw a line through the data points Step 4: Determine where the line crosses the x-axis i.e., y-intercept (Fixed costs) Step 5: Determine the slope (rise over run), i.e., variable cost per unit Step 6: Write the cost equation Scattergraph Approach 5 If you have forgotten how to graph data points, this will help. .http://www.studyzone.org/testprep/math4/d/linegraph4l.cfm Source www.studyzone.org  Grade 4 Math Lessons

  6. Results: Variable cost = Line slope Fixed costs = Y-intercept High-Low Method 6 • Used to estimate fixed and variable costs at various levels of activity • Uses two data points, the high and low levels of activity and their related total costs

  7. High-Low Method 7 First pick the high and low amounts from the activity column. Then pick the costs related to those activity points. Key Point: Step 1: Select the high and low data activity points Step 2: Subtract the smallest from the largest cost and the smallest from the largest activity and use the changes in the following formula Change in Cost Change in Activity = Variable cost per unit

  8. High-Low Method Continued 8 Step 3: Pick one point—either the high or low: Substitute the total cost of the point you selected for “TC” in the equation: TC = VCx+ FC Step 4: Substitute the variable cost from step 2 into the formula for “VC” Slope Step 5: Substitute the number of activity units for the data point chosen in step 3 for “x”

  9. High-Low Method Continued 9 Step 6: Solve for fixed costs “FC” Step 7: Replace the VC with the variable cost per unit you calculated and the FC with the fixed costs you calculated, into the following formula: TC= VC x + FC Only two variables will be displayed in the formula–X and TC. The other letters—VC and FC should be replaced by the respective amounts.