Overview of Settlement Information: Operating Days 04/16/06 - 04/18/06 for Market Meeting

This document outlines the settlement information for operating days from April 16 to April 18, 2006, in preparation for the general market meeting on May 8, 2006. Key topics include a high-level review of all charges and payments for the three days, a review of OOM Capacity Settlement, Replacement Reserve Settlement, payments to providers (Section 6.8.1.10), and an exploration of under-schedule and uplift charges. It will also address questions regarding OOM Capacity and Replacement Reserves, ensuring clarity on complex settlement processes.

evadne
Télécharger la présentation

Overview of Settlement Information: Operating Days 04/16/06 - 04/18/06 for Market Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Settlement Information for Operating Days 04-16-06 thru 04-18-06 Prepared for the 05-08-06 General Market Meeting

  2. Outline of Presentation • High Level review of all charges and payments for the three days. (See “Rev E Q” spreadsheet.) • Review OOM Capacity Settlement • Review Replacement Reserve Settlement • Payments to providers (section 6.8.1.10) • Under-schedule Charge (section 6.9.2.1.1) • Uplift Charge (section 6.9.2.1.2) • Questions

  3. OOM Capacity

  4. Replacement Reserve

  5. Under Scheduled Charges and “USQTY” for 4-18-06

  6. OOM Capacity Payment (Section 6.8.2.2) If a bid exists: PCOOMRPqui = -1* MIN [(BPRPqui * COOMRPui), (PSui + POui)] Other wise: PCOOMRPqui = -1 * (PSui + POui) If the unit is deemed to be On-line as described in 6.8.2.2(4), Then: PSui = 0 POui = SUM [(RCGMECc – MCPEjz) * MIN (MINCAPu/4, MRuj)]j If the unit is deemed to be Off-line as described in 6.8.2.2(2), Then: PSui = [RCGSCc – (SUMs(MCPEwz * MRuw))] / (# of instructed hours) POui = SUM [(RCGMECc – MCPEjz) * MIN (MINCAPu/4, MRuj)]j

  7. Under Schedule Charge (Section 6.9.2.1.1)

  8. Uplift Charge (Section 6.9.2.1.2) UCRPiq = -1 * (Σ (PCRPiq + LPCRPiq)q + Σ (USRPiq) + TCRPAYRPi + Σ (CSCRPiq)q,CSC) * LRSqi TCRPAYRPi = -1 * (Σ(TCRcsci ) * SPCSCi )CSC

  9. Questions ?