43rd IG Meeting Draft Agenda - Enagás, GRTgaz, Reganosa, REN, TIGF

The draft agenda for the 43rd IG meeting on May 23rd, 2017. Topics include use of infrastructures, balancing regimes, market integration, infrastructures update, and pending issues.

evon
Télécharger la présentation

43rd IG Meeting Draft Agenda - Enagás, GRTgaz, Reganosa, REN, TIGF

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Enagás, GRTgaz, Reganosa, REN and TIGF 43rd IG meeting 23rd May 2017

  2. DRAFT AGENDA • Opening • Welcome • Minutes of the last meeting and agenda of this meeting (for approval) • WP First target. Use of infrastructures in the Region • Use of interconnections from 1st October 2014 to 30th September 2016 (deadline: June 2017): • Feedback fromACER-NRAs meeting (for information by NRAs) • Preliminary draft (for information by TSOs) • Preliminary conclusions: Dynamic capacity calculation, etc. (for information by TSOs) • WP Second target. Balancing regimes in the Region: follow-up of the balancing regimes from 1st October 2016 to 20th September 2017 (December 2017) • WP Third target. Market integration: • Iberia (for information by NRAs and TSOs) : • MIBGAS: implicit allocation mechanism (public consultation) and ongoing developments (information by ERSE) • The way forward • France: gas prices and internal congestions • WP Fourth target. Infrastructures • Update (for information by TSOs): • WP Fifth target. Pending issues: • Implementation of OSBB mechanism: current application of the mechanism and update on ongoing developments (for information by TSOs) • AOB • Stakeholder´s request: SG meeting (for information by NRAs) • Calendar for the next meeting.

  3. II.1 WP 1: Use of interconnections

  4. WP1: updated timeline Chapters 3 & 4 : Data underprocessing 31/May 7/June New version of the document with TSOs comments and first draft of chapters 3 & 4 to be circulated between TSOs Full draft of chapters 1, 2, 3 & 4 to be circulated to NRAs First draft of chapters 5 & 6 to be circulated between TSOs First draft of chapters 3 & 4 to be circulated internally within Enagás First draft of chapters 1 & 2 to be circulated internally within Enagás On going… Submission of the final report 26th May 2nd June 12th May 21st April 31st March 30th June 11th April 05th May 22nd May 14th March 24th May 2nd June 9th June First draft of chapters 1 & 2 to be circulated among TSOs Deadline for TSOs to submit comments /complete to chapters 1 &2 Deadline for TSOs to submit comments/ complete to chapters 1,2, 3 & 4 Deadline for NRAs to submit comments to chapters 1,2, 3 & 4 Deadline for TSOs to submit comments /complete to chapters 5 & 6 43rd IG meeting 42nd IG meeting From 8 to 30/June 7/June Chapters 1 & 2 : Data shared and compiled 26/May

  5. V. Infrastructures

  6. Infrastructures: new GRIP, TYNDP and PCIs • New South GRIP • TSOs are working in all the chapters of the South GRIP • Regular conference calls have taken place and also physical meetings • Itisexpected be sent to the editor in June • Itmight be publishedthisSummer

  7. Infrastructures: new GRIP, TYNDP and PCIs • TYNDP 2017 • Final TYNDP 2017 was published 28 April 2017, after public consultation • Main report • Executive Summary • Annex A: infrastructure projects • Annex B: Map • Annex C: Demand & Supply • Annex D: Capacities • Annex E: Modelling Results • Annex F: Methodology • Annex G: Gas quality outlook • Annex H: Feedback

  8. Infrastructures: new GRIP, TYNDP and PCIs • PCI 2017 • In the last NSI West Gas Regional meeting of 27/04/2017 some project promoters, after the questions from the EC, explained the cross-border impacts of their projects. Enagas, GRTgaz, Reganosa, REN and TIGF were not requested to provide information regarding the cross-border impact of their projects. • ENTSOG presented the templates that will be used to demonstrate the results of the PS-CBA of PCI candidates. • The EC explained the MS approval and MS opinion processes and the differences between them. • The methodology to elaborate the ranking of PCI projects will be presented in the next Cross-Regional meeting (30 May 2017).

  9. VI.1. OSBB

  10. OSBB at VIP PIRINEOS: Proposed timeline Update of the common methodology and submission to NRAs before summer 2) Internal deployment during summer with Data exchanges and coordination between TIGF and ENAGAS 3) Pre-launch meeting M-1 OSBB implementation. Before the meeting, TSOs will check the functionalities provided by PRISMA September 2017 22 May 2017 March 2017 19 April 2017 Semi-automatic Pre-launch meeting between TIGF and Enagas 1st Working meeting between TIGF and Enagas Automatic ok Preliminary implementation Final implementation ok 42nd IG 43rd IG October/November 2017 April 2018

  11. OSBB at VIP IBERICO: Timeline New version of the OSBB methodology to be sent to NRAs Preliminary implementation Final implementation April 2018 October 1st, 2017 April 2017 Before Summer • OS values will depend on: • Total booked capacity after the monthly auction >95% nominal capacity • monthly programation conditions • OS values will depend on: • Total booked capacity after the monthly auction >90% nominal capacity • monthly programation conditions

  12. OSBB at VIP IBERICO • Enagás and REN implemented OSBB on1st April 2017. • The offer of OS capacity depends on the following premises: • If after the monthly auction (for the following month) the capacity booked at VIP Ibérico is lower than 95%/90% (95% from April to September and 90% from October to March), then no OS capacity will be offered for the following month. • From 1st April 2017, OS capacity has been 0.