HCAL Commissioning Status Overview

HCAL Commissioning Status Overview. Preparing for HCAL commissioning Remaining cables preparation for installation Stand-alone test hardware preparation Software development and test Commissioning procedure tentative schedule Remaining problems to be solved.

evonne
Télécharger la présentation

HCAL Commissioning Status Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HCAL Commissioning Status Overview • Preparing for HCAL commissioning • Remaining cables preparation for installation • Stand-alone test hardware preparation • Software development and test • Commissioning procedure tentative schedule • Remaining problems to be solved 30.03.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino)

  2. HCAL Commissioning Status HCAL cabling Cables for LED control are ready ½ HCAL (PZ) to be installed during coming week-end Signal cables for pinD: 10 mini-conn. x 8 cables available 2 mini-conn. x 8 cables recuperate 4 mini-conn. x 2 cables required 104 in total 4 FE boards for pinD readout: Even 1 board/side serves ½ HCAL 30.03.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino)

  3. HCAL Commissioning Status Preparing for stand-alone commissioning • The mini-rack installed on to platform: • PC with GPIB interface to CAMAC • CAMAC crate (ADC’s, TDC’s, control ) • NIM crate (discriminators, delays) Ethernet link is urgently needed on HCAL electronics platform 30.03.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino)

  4. HCAL Commissioning Status Software development and test • Most of Software has been developed and tested: • On-line data readout • User friendly interface • On-line visualization • Automated scan procedure • Processing of measured data • Store results in data base Software test has been done with real and simulated data 30.03.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino)

  5. HCAL Commissioning Status Stand-alone commissioning procedure • Tentative procedure plan: • Connect signal cables to ADC’s 2 hours • Trace LED signal in one module (16-40+pinD) 12-24 hours • Set LED pulse-height to ~3000 ph.e.(±25%) 1 hour • Scan PMT with HV variation 1 hour • Scan LED with PMT gain ~104-5 1 hour • Reconnect signal cables to TDC’s 2 hours • Scan PMT’s delay on HV, adjust LED to about same signal 1 hour • Gather data and analysis 4 hours • Re-measure some data if required 8 hours • Total estimate 24-44 hours Schedule for 5-8 weeks per ½ HCAL (26 modules) 30.03.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino)

  6. HCAL Commissioning Status Remaining problems • Few cables for pinD signal readout promised end of March • HV/LED control boards not yet delivered promised March, 15 • (4 needed urgently + rest within 1 month) test will take 2 weeks • Mains ~240 AC on the HCAL platform needed now • Ethernet link on the HCAL electronics platform needed within 2 weeks • High pressured air (5ati) would be needed in June • Radioactive source delivery promisein June • Access to cable tray HCAL (cryo-side) no solution so far • Access to PMT’s, LED’s, pinD no solution so far 30.03.2006 Rustem DZHELYADIN (CERN&IHEP, Protvino)