1 / 22

TBWG Plenary STATUS OF GSA NORTHERN BORDER PROJECTS

TBWG Plenary STATUS OF GSA NORTHERN BORDER PROJECTS. Bill Wells Land Ports of Entry SME October 27, 2010. Discussion Overview. Projects Recently Complete Jackman, ME Warroad, MN Blaine, WA (Peace Arch) Investment Since 2006 Project Under Construction – Portal, ND

eyal
Télécharger la présentation

TBWG Plenary STATUS OF GSA NORTHERN BORDER PROJECTS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TBWG PlenarySTATUS OF GSA NORTHERN BORDER PROJECTS Bill Wells Land Ports of Entry SME October 27, 2010

  2. Discussion Overview • Projects Recently Complete • Jackman, ME • Warroad, MN • Blaine, WA (Peace Arch) • Investment Since 2006 • Project Under Construction – Portal, ND • Construction starts planned in 2011/2012 • Derby Line, VT • Madawaska, ME • Van Buren, ME • Alexandria Bay, NY • Program-Project Investment Outlook

  3. Recently Completed Projects Jackman, Maine • Estimated Total Project Cost $30.5 M • Construction Award 1/2008 • Construction Completed 09/2010 • Gold LEED Certification

  4. Recently Completed Projects cont. • Warroad, Minnesota • Estimated Total Project Cost $45. 4 M • Construction Start 06/2008 • Construction Completed 2/2010 • LEED Gold Certification

  5. Recently Completed Projects Cont. Peace Arch, (Blaine) Washington • Estimated Total Project Cost $100.5 M • Construction Start 08/2007 • Estimated Construction Completion 12/2010 • LEED Gold Certification

  6. Projects Completed Since 2006 • Calais, ME • Jackman, ME • Champlain, NY • Massena, NY • Sault Saint Marie, MI • Detroit, MI • Warroad MN • Peace Arch, WA • Capital Investment: $438M

  7. Ongoing Construction Projects Portal, North Dakota • Estimated Total Project Cost $39.7 M • Disconnect in design, which delayed original construction completion • Construction Start 06/2008 • Re-rewarded construction contract after redesign • Estimated Construction Completion 6/2012

  8. 2011/2012 Construction Starts Derby Line, Vermont • Estimated Total Project Cost $43.5 M • Construction Start 02/2011 • Estimated Construction Completion 08/2013

  9. Derby Line Notes: • PROJECT ON HOLD. • The design awarded to Orcutt Associates 1/15/09. • The project on hold at CBP request • CBP is opting for a de-scoped project • GSA moving forward to study optimizing existing site • Goal to maximize throughput at this port • Construction award is planned for 9/2011

  10. 2011/2012 Construction Starts Cont. Madawaska, Maine • Estimated Total Project Cost $69.7 M • Construction Start TBD • Estimated Construction Completion TBD

  11. Madawaska Notes: • GSA is looking into the viability of the elevated roadway connecting the existing bridge to the planned new LPOE. GSA with MDOT have had very preliminary talks of a new bridge at the existing port location as an alternative to the current elevated roadway proposal. Pending.

  12. 2011/2012 Construction Starts Cont. Van Buren, Maine • Estimated Total Project Cost $42.0 M • Construction Start 06/2011 • Estimated Construction Completion 11/2013

  13. Van Buren Notes: • Concepts approved by Commissioner on March 18, 2010. • The design/build construction contract was awarded on June 29, 2010 to J&J contractors • Robert Siegel Architects

  14. 2011/2012 Construction Starts Cont. Alexandria Bay, New York • Estimated Total Project Cost $175 M • Possible Construction Start 2012 • Estimated Construction Completion 6/2014

  15. Near Future Program • Richford, VT • Ferry Point, ME • Milltown, ME • Coburn Gore, ME • International Falls, MN • Dunseith, ND

  16. Future Program Considerations: • $6 Billion program need • Future projects could be re-scoped, and/or re-prioritized. • Much leaner program than envisioned • Tough decisions on priorities • Scaled down projects • Decades to modernize

  17. Thank You U.S. General Services Administration 1800 F Street Washington, DC 20405 202-501-1858 (Ph. WDC) 202-281-8373 (mobile) bill.wells@gsa.gov

More Related