1 / 10

CURRENT ENVIRONMENT: BANK DEBT CONDITIONS REMAIN RESTRICTIVE

FINANCING OF PPP’S: LESSONS LEARNT IN THE LAST 18 MONTHS… AND BEFORE Enrique Fuentes, Development Director Ferrovial Chairman PPP Workgroup European International Contractors PPP Days Asian Development Bank Manila, March 2010. CURRENT ENVIRONMENT: BANK DEBT CONDITIONS REMAIN RESTRICTIVE.

faris
Télécharger la présentation

CURRENT ENVIRONMENT: BANK DEBT CONDITIONS REMAIN RESTRICTIVE

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FINANCING OF PPP’S: LESSONS LEARNT IN THE LAST 18 MONTHS… AND BEFOREEnrique Fuentes, Development Director FerrovialChairman PPP Workgroup European International ContractorsPPP DaysAsian Development BankManila, March 2010

  2. CURRENT ENVIRONMENT: BANK DEBT CONDITIONS REMAIN RESTRICTIVE Loan Market • Market strongly focused in refinancing / re-structuring • Bond markets have become an alternative for loan financing • Around 55% of loans refinanced in 2009 done through bonds Pricing &Structures • Conditions in the loan markets have shown first signs of easing • Market still focused in short term, but 5 year tenor is back for some good rating corporates • Pricing is tightening but still well above pre-crisis maximums, and increases considerably with maturity • Typical structures: short term with specific take-outs and step-up pricing Banks – Current Situation • Liquidity has increased but Banks’ balance sheets are still highly leveraged • Uncertainty about removal of support measures press liquidity prices up and maintain risk aversion • Underwriting appetite in the loan market is still low but improving ACCESS TO BANK LENDING RESTRICTED FOR PPP’S (specially riskier ones: i.e. greenfields)

  3. CURRENT ENVIRONMENT: BOND MARKET IMPROVING, BUTNOT APPLICABLE TO MANY PPP’S • Bond margins have decreased, but are still above pre crisis highs • Low interest rates compensate margins (for now) • but less so in longer tenors, which are the ones needed for PPP’s • Yield differentials between 10 and 30 yrs 407ETR bonds well above average • Reduction in long term interest rates much smaller than in short term • Bonds are a difficult instrument to fund PPP’s (particularly riskier ones) • No certainty of funding at time of committed offer • Disappearance of monoline insurers • Requires combination with bank bridge financing Δ risk & cost of financing Source: Merril Lynch: European bond market report, March 2010

  4. CURRENT ENVIRONMENT: EQUITY LOOKS ABUNDANT BUT WITH CONDITIONS • Limitations of traditional developers to maintain the rythm of investment • Access to debt • Equity markets still difficult for raising capital • Increasing importance of pure financial investors • Infrastructure funds: “dry powder” in existing funds: US$ 71,5 Bn • … of which US$ 21,4 Bn are allocated to European assets • Increasing interest from final investors (Pension Funds, Sovereign Funds, Family Offices) in investing directly in assets • Financial investors have specific issues regarding risks and return • Averse to construction and significant operating risk • Brownfields preferred to greenfields • Association with traditional developers to mitigate those risks • Significant equity IRR requirements (above 12% for mature projects) • Require not only IRR but also cash yield • Limitations on debt capacity • Higher project IRR’s • In many cases, limitation on maturity • Most infrastructure funds have tenors of no more than 15 yrs • Require absolute transparency and predictable regulatory frameworks • … and are in a position to compare internationally • Potential development of a secondary market in which projects promoted by traditional developers are sold, when mature, to financial investors

  5. RECENT EXPERIENCE: NORTH TARRANT EXPWY (NTE), TEXAS, 2010 • Reconstruction of 21 Km. of highway, adding 4 tolled express lanes • 52 yr concession • Total construction Capex above US$ 1.8 Bn • Paid by tolls • Fully electronic • Escalation linked to capacity utilization and avoidance of congestion • Concession conditional to financial close • Substantial support for the financing • TIFIA loans (soft loans provided by US DoT) • 35 yr tenor • 10 yr interest capitalization • “soft” interest: 40yr UST Bond + 0.01% • Tax exempt Bonds: interest is tax deductible for holder • Cuts interest rates by 100 – 140 bp • Subsidies Total = $2.1 billion

  6. RECENT EXPERIENCE: A1, POLAND, 2010 • Construction of 96 Km of new highway and refurbishment of 84 Km of existing highway (total: 180Km) in main North – South corridor • 35 year concession (conditional to financial close) • Toll Road, but with traffic risk mitigation (availability payments) • Total Construction investment: €1.4 Bn • Innovative financing support by EIB: Loan Guarantee for Trans European Networks, subordinated credit facility to cover revenue shortfall • Availability: 5–7 years after completion • Can repay senior debt to improve Cover Ratios and allow refinancing • Despite support, no financial close: project & risk too big for markets • Availability of Commercial debt and EIB & EBRD project facilities insufficient to cover required debt • EIB could only provide shortfall through Government facilities • FX risk was key: financing in € vs revenues in PZL

  7. STRUCTURAL ISSUES: PPP’s IN EMERGING COUNTRIES GROW RELATIVELY SLOWLY Investment commitments to infrastructure projects with private participation in developing countries, by country Source: World Bank and PPIAF, PPI Project Database. • Unadequate regulation • Unadequate risk / return: both political, commercial & financial • Succesful PPP’s in ECA area: average of 4.5 yrs to financial close!

  8. …PARTICULARLY IN TRANSPORT & WATER Investment commitments to infrastructure projects with private participation in developing countries, by sector 2008 US$ billions • … which have specifities which affect risk • Regulated tariffs • Very often, full transfer of demand risk Source: World Bank and PPIAF, PPI Project Database.

  9. ADAPTING PPP’S TO NEW REALITY • Reduce risk: PPP’s do not finance the projects Governments want, but those acceptable to private sector & financial markets • Focus of Government should be to mitigate risks that the market cannot assume at reasonable costs • Role of multilaterals should be to advice on risk/return acceptable to markets and to provide financing and risk coverage • Co-operative approach with multilaterals to design risk coverage tools • FX risk!!! • Maximize competition and focus it in project IRR and in quality and efficiency • “Evolutionary” approach: risk coverages decrease as experience and development of the country increase • Focus on efficiency • Private Party should be given flexibility, under clear legal framework based on performance indicators, to run the project efficiently • Management of initial investment and of ongoing Opex & Capex • Easier to fund smaller projects: reduce investment & funding • Combination of public & private funding • Imaginative use of Govt guarantees or funding allow to maximise “leverage” of public resources

  10. ADAPTING PPP’S TO NEW REALITY • Bidding process: certainty of financing no longer exists • Avoid long post preferred bidder phases (obtain approvals before) • If not possible, introduce flexibility to re-adjust conditions • Adapt projects to international financial investors standards • Transparent regulation and consistent behavior of granting authority • Change orders • Delays in payments • Tariff escalation • Resolution of conflicts • Regulation should facilitate financing: creation of guarantees, step in rights, change in ownership • Combine user paid schemes with risk mitigation • May allow for efficient pricing of the public service • Create alternative to traditional taxation • Where tax revenues can be unreliable, user paid schemes may end up being more attractive financially • Risk can be mitigated through minimum revenue & other clauses

More Related