1 / 16

PM report International & UK programmes

PM report International & UK programmes. Overview Reconstructing the schedule The UK Project Management team Progress with major subsystems Substation upgrade Space, staffing and skills. Andy Nichols, STFC, UKNF/MICE PSAG, 14-6-11. Overview.

finley
Télécharger la présentation

PM report International & UK programmes

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PM reportInternational & UK programmes • Overview • Reconstructing the schedule • The UK Project Management team • Progress with major subsystems • Substation upgrade • Space, staffing and skills Andy Nichols, STFC, UKNF/MICE PSAG, 14-6-11

  2. Overview • Muonbeamline reliable, decay solenoid now being cooled in readiness for July user run • Target development is going very well, re-engineered target has been formally accepted by ISIS as technical baseline • FC #1 manufacture is progressing, coil winding is complete, but cold mass supports critical path now, but overall very good progress • RF cavity production well on schedule, but LBNL effort rightly transferred to spectrometer solenoids • Spectrometer solenoids – approval of repair plan late – expert controversy over quench protection, but resolved now • 2MVA substation upgrade – installed and working ahead of schedule • Diffuser – steady progress, but limited by available effort • PPS - DSA system now formally handed over to ISIS • First (ten) EMR planes delivered by June 13th, installation planned for July user run – it’s here, assembly started • LH2 R&D system, ready for cooldown with He next week • LH2 absorber #1, delivered last week

  3. Reconstructing the schedule • The MICE Project Board (MPB) requested that MICE presents a credible top-level project schedule by 28th June • MICE had a two-day internal schedule review to prepare for this: • List of major sub-systems • Schedules presented • Resource limitations • Risks and difficulties • Went very well, almost 100% engagement from the project • New plan is under construction, aim to: • Assimilate all the information by 10th June • Approval by MICE Executive Board by 17th June • Deliver to MPB 18th June

  4. Reconstructing the schedule • We will be able to present a detailed schedule for Step IV • Steps V & VI will be as accurate as possible, but qualified with statement that they are subject to the Coupling Magnet uncertainties – still a major project risk • A hard cut-off point for MICE will be the long ISIS shutdown for moderator change in August 2014 • We will aim to achieve a major constructional and/or scientific goal by then • Right now, I don’t know what it is... • We hope it can be Step V • The top-level schedule will contain a more detailed breakdown of each step configuration

  5. STEP IV Step IV ready...Q3, 2012

  6. Organisation and Project Management • Thanks to the cooperation of several people, we can now put names to our UK Project Management model – see last OsC: • UK Project Manager – Alan Grant • System Engineer – Tim Hayler • Project Associate – Andy Lintern • Very unfortunately, we’ve lost Willie Spensley (Hall Manager and Principal Contractor) • This is a major blow – provision of a PC is a legal responsibility for STFC within the CDM framework and Willie has made a huge contribution to MICE • Andy N, aided by Vishal Francis, will deputise until we have a replacement (not ideal) • I believe we must have an STFC employee in the post; this is already in progress

  7. Progress with the Major subsystemsSpectrometer solenoid • US magnet programme is now led by Steve Gourlay at LBNL • He is able to re-direct resources and set local priorities - crucial • UK is providing the magnet co-ordination partnership • Roy Preece (engineering) has been on LTA in US since April • Mike Courthold (magnetic systems) travelling and reviewing extensively • Magnet workshop at LBNL mid-May, very useful • Aimed to collect all available information on spectrometer solenoid recovery • Clear up active/passive quench protection (QP) discussion • Clarify route to MAP approval • Mostly done; QP was cleared up yesterday – it can be passive – easier construction, minimal cost, easier for MAP to approve • It’s now a question of putting it into practice at Wang – Roy is already making a big difference there

  8. Definitive 5+1 CCR layout

  9. Progress with the Major subsystemsCoupling Magnets • First Coil is complete at Qi-Hian – major milestone • Fabrication of cold mass jacket and helium tubes has started • Cryostat design is complete – another major milestone • 261 manufacturing drawings of high standard have been issued for review • Formal review probably at SINAP during August • AN has been invited – Jason Tarrant (MICE integration Engineer will also be involved • Testing of coil likely in US now – Florida State University has big enough cryostat • Unfortunately cannot predict final RFCC module delivery due to US/China uncertainties, but we’re slowly getting under the skin • Have started the complex integration of CC in MICE Hall discussion – the CC has put on weight since the last effort!

  10. Coil #1 before and after Al banding Cold-mass Cryostat RFCC module

  11. Progress with the Major subsystemsFC module #1 • Recent progress at Tesla has been good: • Coil is wound and of good quality • Manufacture of vessel and turret going well in parallel • Cryo-cooler performance being qualified by physical tests • Installing quench heaters • Potting and welding cover plates • Things still worry about: • Testing the FC and field mapping at RAL – likely in R9, but need experts to work out how to do it (proximity of ferromagnetic infrastructure) Magnet also needs independent support structure • Accurate co-axial setting of cold mass in vessel • Cold mass support design needs to be finalised • But it’s encouraging news – looks like September delivery

  12. Progress with the Major subsystemsLiquid hydrogen system • Going well both inside and outside MICE Hall • R&D system almost ready to test with LHe • Have slipped a month or so due to hole in pre-cool circuit • Now need final leak-test of transfer line • Work on roof in final stages • Control system (and UPS) and extract fans has been exercised • No real problems with ISIS/SHE negotiations • Taking opportunity to design/install extensive pipework for systems two and three

  13. Progress with the Major subsystemsSubstation Upgrade • Was finished two days ahead of schedule • Formally handed over to MICE on 27th May • All circuits back on 11KV supply now • Went exceptionally well – minimal disruption to project and to ISIS • Most of the bill got paid in last FY • All credit must go to BPG and JW Morris Ltd • MICE now has a secure power supply for Step VI

  14. Space, Staffing and Skills • Permission given by the RALEC in March for MICE to use all of R9 – very good news • NMR magnet is on its way out soon • MICE needs to adapt the place a bit – design work started at IC • Vital that we use this space for parallel assembly of RF and magnets while Step IV is data-taking (one year) and before that • Availability of staff in DL electrical group is becoming a major worry • 100% application of some posts (design and installation) will be required very soon if we are to deliver: • RF systems • Solenoid controls

More Related