1 / 13

FDOT District 6 ITS Project Update

FDOT District 6 ITS Project Update. Manuel Fontan, E.I. ITS Project Manager. Outline. ITS Program Updates Other Deployment Updates ITS Operations Contract Updates Operational Updates. ITS Program Updates. US 1/SR 5 Estimated Completion Date: April 25, 2008 4 DMS 17 CCTV 6 Detectors.

flann
Télécharger la présentation

FDOT District 6 ITS Project Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FDOT District 6ITS Project Update Manuel Fontan, E.I. ITS Project Manager

  2. Outline • ITS Program Updates • Other Deployment Updates • ITS Operations Contract Updates • Operational Updates

  3. ITS Program Updates • US 1/SR 5 • Estimated Completion Date: April 25, 2008 • 4 DMS • 17 CCTV • 6 Detectors

  4. ITS Program Updates • I-395/SR A1A & Port of Miami • Letting Date: October 9, 2007 • 1 DMS (Port of Miami) • 8 CCTV (Mainline); 2 CCTV (Port of Miami) • 10 Detectors (Mainline)

  5. ITS Program Updates • SR 826 • Letting Date: October 9, 2007 • 3 DMS • 6 New CCTV (4 on Interchanges and 2 for DMS Verification); 4 Existing • 37 Detectors

  6. ITS Program Updates • ITS Technical Consultant Services • Letting Date: Approximately May 2008 • Executed: Approximately July 2008 • Budget Amount: $ 1.5 Million/5 Years

  7. ITS Program Updates • 95 Express (Miami-Dade County) – Phase 1A (SR 112 to GGI) • Design Build Initiated • Equipment/Devices: • Tow • CCTV • Toll Rate Signs • Lane Status Signs (1 Line DMS) • Estimated Completion Date: Summer 2008 • Estimated Completion Date - All phases: Summer 2010 • Ramp Metering • Initial metering will be for the 8 NB ramps on the 95 Express Lanes limits • Turned on simultaneously with 95 Express Lanes

  8. Other Deployment Updates • June 2008 • FDOT District 6 SunGuide™ TMC Intranet Release 2.0 • RRDIS Release 2.0

  9. ITS Operations Contract Update Notice to Proceed: December 17, 2007 Staff Transitioned: January 14, 2008 24 positions • IT: 5 Positions • 1 IT/ITS Maintenance Manager • 1 Network Administrator • 2 IT Administrators • 1 Software Systems • TMC Operations: 16 Positions • 1 TMC Manager • 1 Assistant TMC Manager • 1 Road Ranger Contract Manager • 2 Shift Supervisor • 2 TMC Lead Operators • 9 TMC Operators • Contract Support: 3 Positions • 1 Contract Project Manager • 1 Office Manager • 1 Receptionist (Front Desk)

  10. Operational Updates February 2008

  11. Operational Updates February 2008

  12. Operational Updates February 2008

  13. Questions? Manuel Fontan, E.I. FDOT District 6 (305) 499 - 2493 Manuel.Fontan@dot.state.fl.us

More Related