1 / 13

Project Management Lecture 16

Project Management Lecture 16. Project management involves estimating the length of time to complete a project Once a project has been undertaken then a project manager is responsible for carrying out the project on the assigned time table How do the managers establish a time schedule

freira
Télécharger la présentation

Project Management Lecture 16

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management Lecture 16 • Project management involves estimating the length of time to complete a project • Once a project has been undertaken then a project manager is responsible for carrying out the project on the assigned time table • How do the managers establish a time schedule • Generally based on average length of time for each component • Average length of time based on past experience • Length of time to complete each step is a random variable

  2. Materials for Lecture 16 • Readings Chapter 14 • Lecture 16 Short Project Management.XLSX • Lecture 16 Project Management.XLSX • Lecture 16 Event Management.XLSX • Lecture 16 Have Some Fun.XLSX

  3. Project Management • Who does project management? • Engineers, managers, accountants • They calculate number of days to completion • Generallydo not incorporate risk • Benefits of incorporating risk into project management analysis • Assign a probability to number of days until project completion • Assign a probability to getting a project done in a fixed timeframe

  4. Project Management • KOV for a project management problem is: How long will it take? • There is no final answer until project is completed • Answer is an unknown PDF of days, weeks, or months to completion • Simulation provides a methodology for estimating unknown PDFs • Formulate the problem as a Monte Carlo simulation problem

  5. Project Management • Model formulation • KOV is “Number of Days” to completion • Identify each task (step) for project • Specify order of each task for the project • Identify bottlenecks where tasks will wait on precious stages • Determine the PDFs for number of days (or weeks, months, etc.) to complete each task • Rely on experience from past jobs • Depend on experts for time to complete each task • PDF may be dependent on resources available

  6. Project Management • Critical to identify the order of the tasks and their linkages (dependencies), for example: • Task 10 starts after Tasks 5 and 8 are completed • Task 11 starts after Task 10 is completed • Thus, Task 5 or 8 could hold up the whole project • If analysis shows 5 is the bottleneck is it worth investing more resources in Task 5 to get the project completed earlier?

  7. Project Management • Create a simple Project Network Diagram to summarize the order of tasks • Drawn it in Excel with simple arrows and boxes • Network diagram shows potential bottlenecks

  8. Project Management • Tasks 1-6, 2 and 3 wait on 1, 4 waits on 2, 5 waits on 3 and 4, last task (6) waits on 5 • Assumes next task starts day after it predecessor ends • Days in column C are GRKS() stochastic

  9. Project Management • Finite limit to complete the project is 45 days • P(Days>45)=?

  10. Spreadsheet of a Project Management Analysis

  11. Project Management Expanded • I like to add a second KOV – Cost • We know cost of a project is stochastic • So project management model can simulate PDFs for days and cost • In the example $/day costs for each task are multiplied by stochastic days

  12. Event Planner • Event planner KOVs • Number of days ahead to start planning an event • Cost of the event • Research application KOVs • Time to complete a research project • Cost of project • Wedding planner • Probability of being ready on time • Cost of the event • Banquet planner

  13. Event Planner

More Related