1 / 35

WF Guidelines for implementation Financial management

WF Guidelines for implementation Financial management. 12 February 2010, Delft Kick-off meeting. Content. Partners’ budget (overview, approach , templates) Sub-division of budget per budget lines Eligibility (rules, period, requirements) First level control Reporting procedure

galeno
Télécharger la présentation

WF Guidelines for implementation Financial management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WFGuidelines for implementationFinancial management 12 February 2010, Delft Kick-off meeting

  2. Content • Partners’ budget (overview, approach, templates) • Sub-division of budget per budget lines • Eligibility (rules, period, requirements) • First level control • Reporting procedure • Payment procedure

  3. 1. Budget overview

  4. 1. Budget overview

  5. 1. Budget overview • Budget is a plan >< BUT! implementation is always changing slightly • Application phase: initial budget development • Start-up phase: conditions of approval set by the JTS >> modification of detailed budget as well > budgets per PP by CP, budget lines and reporting periods sent to PPs (and discussed individually if needed)

  6. 1. Budget overview • spending forecast - part of the Subsidy Contract (in a yearly breakdown) > has to be adhered to and taken seriously! • Taken very seriously by the JTS > this is what has to be fulfilled and will be checked strictly >> underspending is „the most serious crime” > decommitment rule >> may result in loss of funding

  7. 1. General characteristics of financial management • Time frame: 4-5 years from Application phase till project closure • Strict regulations on Programme level • Various country specific requirementsand their (frequent) changes • Prefinancing is needed from all PPs – can be as long as12 months! • Fluctuation of staff on PPs level • BIG CHALLENGE BUT GREAT EXPERIENCE • For future financial planning • For future project implementation

  8. 1. Financial planning - monitoring • In order to ensure a sound financial management for the project: • PPs are requested to provide (bi-)monthly internal reports to the LP (simple template provided by LP – checkinAnnex of theHandbook) onprecedingspendings and a forecast for the following month(s) • Based on this data > the LP is capable to follow & monitor the project’s actualfinancial status, to compare it with the AF & to propose measures in case of serious deviations

  9. 1. Budget flexibility Possible deviations & reallocations are laid down in the INTERREG IVC Programme Manual and the Subsidy Contract: Changes in budget lines, CP budgets and PP budgets are possible – as long as the maximum amount of funding (ERDF + Norwegian) awarded is not exceeded

  10. 1. Budget flexibility • 10% or 20,000 EUR flexibility: budget lines OR CP budgets OR PP budgets can be exceeded by • 10% • OR 20,000 EUR of the respective budget line OR CP budget OR PP budget – whichever is greater

  11. 1. Budget flexibility

  12. 1. Budget flexibility • The 20% budget modification: • Only once during the project and only in duly justified cases • Only upon prior approval from the JTS/MA • a reallocation can be made between budget lines, CPs and PPs up to 20% of the total budget = the increase to budget line / CP / PP’s budget can be maximum 20% of the total budget for each change

  13. 1. Budget flexibility

  14. 2. Budget by budget lines • Staff costs • Administration costs • Travel and accommodation • External expertise & services • Equipment

  15. 2. Staff costs • Definition: personnel costs of employed staff (including salary, tax, employer’s contribution for social secrurity, but not including voluntary contributions )- people beeing already on pay-roll or ad-hoc staff recruited and directly employed for the project by partner organisations • Calculation rules: on the basis of the actual salary rate stated in the regular employment contracts, pay-roll figures • Important administration rule: staff involved in and payed from the project needs to have job description including tasks related to WF project • Appears in all CPs – depending on the activities carried out and reported

  16. 2. Administration costs • Definition:all direct general costs (costs deriving exclusively from the project) and indirect general costs (overheads related to the project’s activities, based on real costs and calculated on a pro data basis) • Administration costs items: stationary, photocopying, mailing, office rent, telephone, internet, heating, electricity, bank charges etc.

  17. 2. Travel and accommodation • Definition: travel and accomodation costs and allowances of partners’ staff related to their participation in meetings, visits etc. • External experts’ travel costs are budgeted under „external expertise” budget line!

  18. 2. External expertise & services • Definition: Costs paid to external service providers on the basis of contracts and against invoices • Budget for external expertise: under the specific CPs in the budget line „External expertise” (see for details justification part in AF budget) • Only budgeted external expertise can be procured (public procurement applies!)

  19. 2. Equipment • Definition: purchase of equipment necessary for the project • Public procurement rules have to be respected • Has not been planned for WF! (details should have been given in AF)

  20. 2. Supporting documentation • Staff costs: timesheets, internal monthly salary statements, work contracts, position descriptions, statement on calculation method, bank transfer of payment of salary and related social charges • Administration costs: utilities, renting invoice/contract, possible calculation methods: staff number / sq meter / working hours, statement on calculation method • Travel & Accommodation: tickets, boarding cards, travel diary, internal documentation linked to travel (e.g. travel permit, other official statements) • External expertise: procurement documentation, contract/order form, delivery statements, invoice, bank transfer certificate, tangible output of delivery of the service (study, brochure, etc.)

  21. 3. Eligibilityrules • Only eligible expenditures meeting the following criteria can be funded under the INTERREG IVC Programme: • Expenditure must be linked & related to the respective partner budget and project activity (AF, progress report) • Only paid invoices can be claimed • All expenditure must be supported by evidence (invoices to the partner’s name, accounting documents, etc) • Expenditures incurred and paid within the project’s implementation period (from start to end date fixed in Subsidy Contract)

  22. 3. Eligibility period • Preparation phase: until 31.01.2009Costs must relate exclusively to preparation activities and must be claimed in first progress report(staff, travel, external) • eligibility period start: 05.11.2009 (decision of MC) • Project implementation phase: 01.01.2010- 31.12.2012

  23. 3. General eligibility requirements • Double funding is not allowed • VAT is not eligible unless it is definitely borne by the partner and it is not recoverable by the partner >> if eligible cost for the PP >> the PP’s budget is gross! • Charges for international transactions (bank costs) are eligible (mostly affects LP) • Interest on debt, fines, financial penalties, foreign exchange losses etc. are not eligible

  24. 3. Specific country relatedEligibilityRequirements • PPs must be familiar with national rules relevant to their project • If national standards are more demanding than EU rules, the stronger must be applied • PPs are advised to consult their first level controller to get familiar with specific requirements to be met as soon as possible • Public procurement rules must be respected

  25. 3. Public procurement • National regulations apply (may be stronger than programme requirements!) • Fundamental principles to keep in mind: • Be familiar with national public procurement regulations and/or involve a public procurement expert if needed • Be aware of the length of time needed for public procurement procedures (plan it when preparing your own implementation plans) • Ensure transparency of the whole public procurement process – full documentation (has to be available for financial control & audit purposes) • Content of procured activity (TOR) must be fully in line with activities in the AF.

  26. 3. Expenditurereporting ispossibleif: • Calculations are based on actual costs • Costs are borne by the PP organisation • Expenditure has been paid out ( debited from the partner’s bank account – date of payment) • Expenditure is directly linked to the project partner’s budget

  27. 4. First Level Control (FLC) • Each partner’s partner level reports have to be verified by the respective FLC body (centralized or decentralized) • Aim: to control that costs co-financed under the INTERREG IVC Programme are in line with legal and financial provisions of the Subsidy Contract and with the relevant national laws • The role of FLC: administrative, financial and eligibility check of the project’s implementation on partner level

  28. 4. First Level Control Centralized systems • Hungary • Latvia • Poland • Sweden • Northern Ireland Decentralized systems • The Netherlands • UK • Finland • France • Italy • Spain • Norway

  29. 4. First Level Control – basic tasks for PPs • Identify, contact ASAP and keep in continuous contact with yourFLC – in case of decentralized systems: start the approbation procedure ASAP • Read and follow the regulations released (and modified) by your FLC • Have personal consultations before the submission of each Partner Report (but definitely before the 1st one!) • Fulfil the reporting and clarification requirements of your FLC always without delay

  30. 5. ProgressReporting: procedure (1) • Reporting periods: calendar half-years (1 January- 30June AND 1 July – 31December)

  31. 5. ProgressReporting: procedure (2) STEP 1: Partner level reports • submitted by all PPs to their first level controllers • Validation process • Output: 16 control confirmations in each reporting period

  32. 5. Progress Reporting: procedure (2) STEP 2: Progress report • PPs send an internal PP ProgressReport (=simplifiedtemplate) tothe LP toprovidethemdataforpreparingthejointProgressReport • PPs send their controlconfirmationsinoriginal to LP within max 15 days before deadline of the Progress Report submission • LP submitsthejointProgressReporttoits FLC forcounterchecking • LP submitstheProgressReporttothe JTS • LP – ifneeded, withtheinvolvement of PPs – fulfilsclarificationsrequirementsofthe JTS

  33. 5. Reporting: documents to be submitted (3) Documents to be submitted together with the Progress Report by the LP: • Original copies of all PPs’ control confirmations (released by FLC) • Bank statements confirming the transfer of the reimbursed ERDF funds transferred from LP to PPs (from the 2nd report onwards) • 3 copies of each project communication material (brochure, newsletters etc.)

  34. 6. Payment procedure

  35. Thankyouforyourattention!

More Related