1 / 12

Implementation Update of Fuels Reduction and Vegetation Management on National Forests (2010-2014)

This report provides a comprehensive summary of the fuels reduction and vegetation management treatments conducted on the Arapaho and Roosevelt National Forests and Pawnee National Grassland from 2010 to 2014. The document outlines accomplishments from 2002-2013, detailing the area treated in both Wildland-Urban Interface (WUI) and non-WUI zones. It highlights past treatments, planned future treatments for 2013 and 2014, and offers insights into ongoing forest management strategies aimed at reducing wildfire risks and enhancing ecosystem health.

ganit
Télécharger la présentation

Implementation Update of Fuels Reduction and Vegetation Management on National Forests (2010-2014)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FRONT RANGE ROUNDTABLE Q2-13 QUARTERLY MEETING IMPLEMENTATION UPDATE 2010 - 2014 • Arapaho and Roosevelt National Forests and Pawnee National Grassland May 31, 2013

  2. Fuels Reduction and Vegetation Management TreatmentsAccomplishment Summary • 2002 – 2009 • WUI Acres Treated: 26,695 acres • Non-WUI Acres Treated: 9,836 acres • 2010 – 2012 • WUI Acres Treated: 17,412 acres • Non-WUI Acres Treated: 6,919 acres

  3. Fuels Reduction and Vegetation Management TreatmentsPlanned Accomplishment Summary • 2013 • WUI Acres Planned: 2,470 acres • Non-WUI Acres Planned: 725 acres • 2014 • WUI Acres Planned: 3,307 acres • Non-WUI Acres Planned: 1,923acres

  4. 2013 Planned Treatments: Boulder/Clear Creek RDs 6

  5. 2013 Planned Treatments: Boulder/Clear Creek 7

  6. 2013 Planned Treatments: Sulphur RD 9

  7. 2013 Planned Treatments: Canyon Lakes RD 11

  8. 2013 Planned Treatments: Canyon Lakes RD 12