1 / 20

Chuck Morganson HNTB Corporation, Sr. Project Manager San Francisco, CA

Transportation Management Center: Business Process Review and Playbook for Transition. Jim Kelly SFMTA, Deputy Director, Operations San Francisco, CA. Chuck Morganson HNTB Corporation, Sr. Project Manager San Francisco, CA. Presentation Outline. • Legacy Control Centers

garron
Télécharger la présentation

Chuck Morganson HNTB Corporation, Sr. Project Manager San Francisco, CA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Transportation Management Center: Business Process Review and Playbook for Transition Jim Kelly SFMTA, Deputy Director, Operations San Francisco, CA Chuck Morganson HNTB Corporation, Sr. Project Manager San Francisco, CA

  2. Presentation Outline • Legacy Control Centers New Integrated Transportation Management Center (TMC) Business Process Review Move-In Playbook

  3. New Transportation Management Center (TMC) SFMTA / MUNI Operations: Legacy Control Centers Transit Power Transit Operations Transit Lines Traffic Management Parking Control & Security

  4. New Transportation Management Center (TMC) Retrofit of existing decommissioned Bank of America control center to be LEED Certified TMC facility 4

  5. New Transportation Management Center (TMC)

  6. New Transportation Management Center (TMC) • Construction Progress 6

  7. Business Process Review Contract Implementation Design by HNTB-B&C JV, Central Subway Contract Included Business Process Review of SFMTA Operations Phase 1 Construction, Tenant Improvements (TI) Building owner is Hudson Pacific Property Work Performed by Hudson Pacific Property Phase 2 Construction, Work Outside Tenant Improvements (OTI) Work performed by Job Order contracts Procurement for Furnishings and City Agencies

  8. Business Process Review Achieve TMC Project Objectives Integrated Pro-Active Stakeholder Focused Start-Up Aspect of the TMC Project Creating a New Business process Creating a New Operational Organization Hiring New TMC staff Creating New / Revising SOP & training programs Budgeting TMC Operations Utilize Lessons Learned and Best Practices

  9. Business Process Review Major Areas for Change: Staffing – Organizational Structure Technology, Training, Support Internal Cultural Barriers / Silos • SFMTA Policies – SOPs Situational Awareness: Big Picture Small Picture

  10. Business Process Review Peer Review Session – August 2010 BART, San Francisco, CA MBTA, Boston, MA Montgomery County, Rockville, MD OC Transpo, Ottawa, Canada Tri-Met, Portland, OR 10

  11. Move-In Playbook Move-In Phases 2012 2013 2014 2015 2016 Pre-Phase 1: Nov. 2012- Feb. 2014 Phase 1: Feb. 2014 Pre-Phase 2: Feb. 2014-Oct. 2014 Phase 2: Oct. 2014-Sept. 2015 Post Phase 2: Sept. 2015-Sept. 2016

  12. Move-In Playbook Move-In “Playbook” and Time Frame Pre-Phase 1 Move-In Tasks ----- Create Labor Class Hire TMC Ops. Mgr. Conduct TMC Scanning Tour Create Trans. Operator Job Descriptions Develop New SOP Manual Develop Training Program Phase 1 Move-In ----- Pre-Phase 2 Move-In Tasks ----- Revise SOP Manual – Phase 1 transition to Phase 2 Revise Training Program – Phase 1 transition to Phase 2 Phase 2 Move-In ----- Post-Phase 2 Move-In Tasks ----- Revise SOP Manual – Post Phase 2 Enhancement Revise Training Program – Post Phase 2 12

  13. Move-In Playbook Staff Physical Move-In Phasing Phase 1 Move Phase 2 Move Line Management Center (Transit Pilot) SFGo CCTV Traffic Signals • Lenox Muni OCC • Transit Controller & Dispatchers • Power Control • Trouble Desks • Subject to Radio Replacement Schedule • CAD/AVL Cutover Parking Control & Towing Dispatch Security Monitoring

  14. Move-In Playbook TMC Start-Up Committee

  15. Move-In Playbook Transit Division TMC Organizational Structure TMC Deputy Director Senior Ops Manager Sustainable Streets Division Communications Facilities Manager/ Reception Finance & IT Division TMC Operations Manager/ Incident Manager/Transportation Floor Manager Third Party Security Monitoring PCO/ Towing Dispatching SFGo Operations Operations System Onsite Support Rail Trouble Desk Traffic Trouble Desk Transportation Management Control (Rail, Trolley, Bus) Rubber Tire Trouble Desk Public/ Passenger Information Officer Operations System IT Support Training Motive Power Control Trouble Desk Security TMC Operations Floor / Operations Theater

  16. Move-In Playbook New Attitude: Failure is Not an Option!

  17. Move-In Playbook SOP Master Checklist Each incident will follow these stages: Verification (Validation, Class 1-3) Notification Implement Response (Checklists) Event Management Service Modification Service Restoration

  18. Move-In Playbook Incident Classifications Class 1: Service Disruption Equipment Specific Line Specific / Mode Specific Systemwide Class 2: Accident Accident with No Injury Accident with Injury Accident with Fatality • Class 3: Serious Threat • Threat to Facility • Threat to Passengers / Personnel

  19. Move-In Playbook New Positions TMC Operations Manager TMC Transportation Shift Manager TMC Transportation Operator

  20. Summary 5 Legacy Control Centers combined into 1 new TMC Implement Business Process Review Develop Findings and Recommendations See for Yourself Wednesday Technical Tour - SFMTA Line Management Center & New TMC (under constr.)

More Related