This report discusses the financial and implementation challenges faced during the various phases of the Jawaharlal Nehru National Solar Mission (JNNSM). Phase I (1000 MW), Phase II (9000 MW), and Phase III (10000 MW) provided critical lessons, including the need for risk-sharing by the government, issues with unreliable DNI data, and the importance of affordability, bankability, and market accessibility. The report outlines a five-point action plan for the 12th Plan, including a two-bid system, case bidding templates, and measures to enhance REC bankability.
E N D
Financial and Implementation Challenges Lessons for 12th Plan
JNNSM • Phase I 1000 MW • Phase II 9000 MW • Phase III 10000 MW
Phase I A success … with enormous lessons
Three major lessons: • No risk sharing by Government • Compromises by MNRE • Unreliable DNI data
Five point action plan for 12th Plan • Follow two bid system • Case 2 bidding template • Allow portfolio approach • Standardize the plant size • Make RECs bankable