An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. REACH Solar Project2006 East Blair Housing Co-op Eugene, OR

  2. East Blair Housing Co-op • Established June 30, 1981 • Located in the historic Whiteaker neighborhood • 22 households (only 5 in solar project) • Townhouse apartments, SF and large conversions • Garden space and safe play areas

  3. Project Partners • OHCS • Lane County HSC • EWEB • HACSA • EBHC

  4. Time lines • July 2006 Request for proposal • August Submittal deadline • September 2nd solicitation • October Review committee selection • November Award of Contract and roof replacement • December Installation, inspections, progress payments. • Dec. 29th Solar Heated water “on-line”

  5. Selection Criteria • Cost • Design • Effectiveness • Completion time line • Maintenance • Reliability • EWEB approved “Brightway specs”

  6. Proposal Cost Range • Solar Assist $23, 332 to $25,832 • Mr. Sun $35,750 to $38,230 • Cascade ~ no quote ~

  7. Budget • DOE $5,082 • LIEAP $9,605 • REACH $7,500 • EWEB $1,145

  8. Solar System Components • Drain-back Solar Water Heater • (3) 4’ X 10’ SunEarth “black chrome” collectors • (2) 120 gallon Rheem/Ruud Solar storage tanks • (1) SunEarth “Steca) Differential Temperature Control • (1) Grundfos Pump • (1) 10 gallon drain back tank • (1) 1 ¼ Tempering valve

  9. Scope of Work • Build storage shed for solar tanks and equipment • Replace roofing on south slope (by EBHC) • Install collectors, tanks, valves, differential temperature control, and pump • Connect all components and plumbing to serve 5 townhouse units. • Instruct Co-op residents regarding recommended system maintenance and operation