An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AESA ConferenceMarch 26, 2019 Dust Permits – ‘Process and Common Issues’ Craig Grismore - PCAQCD

  2. Topics • Dust Control & Permits • Dust Generating Operations/Standards • When is a Permit Required • Permit Application Process • Approvals and Fees • Common Permitting Issues

  3. Dust Control & Permits • PM10 Non-Attainment Area Quality Standard • NAA classification means that air quality in a particular region does not meet federal health standards as defined by the Clean Air Act • PM10 is defined as a suspended particulate with an aerodynamic diameter of <10 microns • Control Goal – Limit the amount of particulate matter discharged to the atmosphere • Sources Include: Fires, Unpaved Roads, Road/Home Construction, Industry, Vehicle Emissions, Agricultural Activities, Demolition • Permitting ensures accountability and knowledgeof mitigating control methods • We Permit 3 different Areas (West Pinal, Apache Junction, Remainder of the County) • West Pinal (Rule 4-3-180) • Applicant Info: Owner, POC, Project Scope/Size, Work Practice Standards, Site Inspections, Control Measures, Work Practices, Trackout, Limit Trespass, Signage, Opacity Limits, Record Keeping, Signature • Apache Junction (Rule 4-7-230, 226, 238) • Applicant Info: Owner, POC, Project Scope/Size, Obligatory Work Practice Standards (Access control, Inactive/Post Operations Roadways, Bulk Material Op’s, Trackout, Signage, Training, Control Measures, Load Stabilization, Emission Mitigation, Sub-Contractor Registration, Opacity Limits, Active Area Stabilization, Record Keeping Requirements • General Area/Rest of County • We attain a signature after reasonable inquiry, that Project statements and information are true and accurate.

  4. Dust Generating Operations/Standards • Operations: • Earthmoving Activities, Land Clean-up, Leveling, Back Filling • Drilling, Construction, Demolition, Bulk material handling, storage and/or transporting operations • Operation of motorized machinery used in construction, Establishing/Using unpaved parking lots, haul access roads in work site • Installing initial landscapes using motorized equipment • Standards • Opacity Limitations • West Pinal/General - Cannot exceed > 20% on the property • Apache Junction – 0%/30 sec property line, >20% continuous/intermittent plume/time aggregate average • Maintain Site Stabilization • Ensure work site attains disturbed surface stabilization compliance at all times, including post-operation • Drop Ball Tests utilized to measure stabilization • Apache Junction Specifics – Maintenance of Threshold Friction Velocity, Vegetative cover standard, Erodible element coverage, Silt loading standards • Track Out • West Pinal/General - < 50 linear feet • Apache Junction Specifics – < 25 linear feet, Limited daily bulk material movement, measured rumble strips/gravel pads/internal paving guideline, Remove all at end of day

  5. When is a Permit Required • Any worksite that covers an area of 0.1 acres or larger • 0.1 acres = 4356 sqft • Calculation of land stripping/earthmoving surface areas: • Include surface are for all disturbance activities • Add 12.5’ to each side of structures, driveways, pads, etc. • Parcels must be contiguous if multiple parcels are on one permit • Calculation of disturbed area for trenching only projects: • 726’ for trenches < 4 feet deep • 363’ for trenches > 4 feet deep • Calculations in ‘linear feet’ • Land stripping and/or earthmoving permits cover trenching and stockpiling – (you do not need to permit them separately)

  6. Permit Application Process • Applicant Information: Applicant/Property Owner/Primary Project Contact • Project Information – Parcel #, GPS, Township/Range/Section • Project Scope – Type, Size, Road, Demo • ID Earthmoving Disturbance Activities • Work Practice Dust Control Measures – Dust Suppression • Limit Trespassing/High Risk Day Stabilization/Signage • Worksite Standards • Liability Signature – Obligations and Affirmation • Site Plot Map (Parcel/Work Location/Access/Neighbors)

  7. Approval and Fees • Approvals • Only trained Compliance Personnel can approve • ‘Real-Time’ approvals possible with front desk applicants • Target <24 Hour response to electronic submissions • Fees • Land Stripping - $75 (.1 to 5); $200 (5-10); add $200 for +10); $2000 (>100 acres) • Trenching – From $50 (500 lf) up to $2000 (> 4 miles) • Stockpiling – $50 for 10 cy; $100 for 100-500 cy; $150 for >501 cy • Annual Block Registration - $2000 (installing utility lines) • Late Fees - $25 for <5 acres; $100 > 5 acres

  8. Common Permitting Issues • ‘In-person’ applicant typically only represents Owner/Project Coordinator • Site Plot Maps Missing • Incomplete Submittals (Electronic) • ‘Wrong Area’ Applications • Name/Address/Phone/Email information missing or wrong • Project Scope lacks pertinent detail • Parcel/Township/Range/Section missing • Missing documents/signatures • Dust Control Measure boxes not checked • Permit Expiration - Large construction projects personnel allow permits to expire

  9. Questions?