Tax Increment Financing Town Center Project Midwest City, OK. Pre Development. Public Participation. 1970 Comprehensive Plan. 1985 Comprehensive Plan. Midwest City Millennium Implementation Plan. Midwest City Downtown Redevelopment Plan. 2004 Report on Area Conditions.

Télécharger la présentation

Tax Increment Financing Town Center Project Midwest City, OK

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tax Increment FinancingTown Center ProjectMidwest City, OK

  2. Pre Development

  3. Public Participation 1970 Comprehensive Plan 1985 Comprehensive Plan Midwest City Millennium Implementation Plan Midwest City Downtown Redevelopment Plan 2004 Report on Area Conditions

  4. Major Project Aspects Local & Regional Void For Commercial & Retail I-40 Frontage with Multiple Access Points Limited Interstate Frontage Adjacent to Tinker Eastern Oklahoma County as Market Area 90 Acre Development 240 Lots to Assemble the Property Timing was Right

  5. 3 Main Project Goals Improve the Image of Midwest City Create a People Place -Downtown/Town Square Economic Development/New Retail Center

  6. Design Guidelines Process for Designers Philosophy Site Access and Traffic Flow Utilities Layout Site Lighting Architectural & Landscape Design Signage

  7. Site Plan Phase I - 329,400 sq ft Phase II - 96,150 sq ft Phase III - 203,104 sq ft Retail Total 629,000 sq ft Plus 11 Outparcels

  8. Town Center West Site Improvements Existing Site Conditions

  9. Funding 7 Million in Tax Increment Financing (TIF) 27 Million Midwest City Hospital Authority for Land Acquisition TCSP Highway Administration Funds Numerous Smaller Grants Partnership with Sooner Investment RFQ & RFP Process

  10. TIF – Project PlanAdopted August 2002 DESCRIPTION OF PROJECT • Redevelopment & revitalization of original downtown • 90 acres • Major commercial redevelopment • New private investment of $50,000,000 • 500 to 1000 jobs over 7 year implementation • Annual sales tax $1 to $2 million over 10 year period • Direct payroll $15,000,000

  11. TIF – Project PlanAdopted August 2002 ELIGIBILITY OF PROJECT • Project area is unproductive, underdeveloped and blighted • An area where investment, development and economic growth has not occurred • Area is and was blighted and detrimental to the public health, safety and welfare

  12. TIF – Project PlanAdopted August 2002 OBJECTIVE OF INCREMENT DISTRICT • Revitalize original downtown area • Promote economic development to increase sales tax revenues, raise property values, improve economic stability • Retain jobs and create new ones • Preserve and enhance tax base • Make possible development that otherwise would be difficult without apportionment of ad valorem taxes

  13. TIF – Project PlanAdopted August 2002 FINANCIAL IMPACTS • Proposed private redevelopment will generate tax increments necessary to pay authorized public costs of the project • Project does not create a measurable increase in demand for services or costs

  14. TIF – Project PlanAdopted August 2002 STATEMENT OF PRINCIPAL ACTIONS • Property acquisitions • Negotiation, preparation, execution and implementation of development and redevelopment agreements • Site preparation, planning and construction of public improvements • All other actions necessary and appropriate to carry out project

  15. TIF – Project PlanAdopted August 2002 ESTABLISHMENT OF DISTRICT #1 • Increment of ad valorem may be used to pay project costs for a period not to exceed 20 years • Increment is divided into 2 parts Part A: that portion of the increment generated by values up to the equalized assessed value of all real property and all personal property in the district for the year 1999 which is deemed to be $1,458,062 shall be allocated to affected taxing entities Part B: the balance of the increment generated within the increment district (the portion generated by values in excess of the 1999 value) shall be allocated to payment of project costs

  16. TIF – Project PlanAdopted August 2002 ESTIMATED PROJECT COSTS • Category A: • Demolition $ 1,500,000 • Street Improvements $ 1,900,000 • Park Improvements $ 200,000 • Utility Improvements $ 1,500,000 • Category B: • Organizational, administrative and professional services $ 300,000 • Contingencies $ 550,000 • Capitalized Interest $ 1,050,000 $ 7,000,000

  17. TIF – Project PlanAdopted August 2002 FINANCING REVENUE SOURCES • It is estimated that between $400,000 in the near and $900,000 over the longer term will be generated annually

  18. TIF – Project PlanAdopted August 2002 ACTUAL RESULTS • 1999 Assessed valuation $ 1,458,062 (generated $107,769 in property tax) • 2011 Assessed valuation $10,326,826 (excludes value of land - $107,769 + $997,735 = $1,105,504 in property tax) • TIF Note Payoff $7,000,000 - Borrowed from City Sewer Fund • 2007 $ 343,175 • 2008 $ 568,106 • 2009 $ 907,416 • 2010 $ 1,110,557 • 2011 $ 981,193 • 2012 $ 1,007,703 (est.)

  19. TIF – Project PlanAdopted August 2002 ACTUAL RESULTS – CONTINUED • Sales tax generated from site: Fiscal Year 2010-2011 $6,250,000 • Number of jobs created: Estimated:1000 Actual: 1150