AE Title III Status

Jacobs' full-time on-site representative at LCLS, responsible for Title III services during construction, including RFI responses, subcontractor submittal reviews, and site visits.

guillermom
Télécharger la présentation

AE Title III Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AE Title III Status Introduction Jacobs’ full time, on-site Representative (since 26 July’06), Co-located with CF Group. Function is to represent the Designer and work as part of the LCLS Conventional Facilities Team. Recent DOE project experience was as one of two full-time on-site design team representatives on SNS project.

  2. AE Title III Status • Background • Jacobs was responsible for the Title I and II design of the Conventional Facilities including the CLOC. • Jacobs is currently performing Title III Services during construction as described in AIA Document B141 and as amended by letter of agreement between SLAC & Jacobs

  3. AE Title III Status Title III services include the following: Response to design related requests for information (RFIs) during the Bidding process. Response to CM/GC and subcontractor generated RFIs. Review of subcontractor Submittals and Requests for Substitution.

  4. AE Title III Status • Site Visits by the design leads at appropriate times during construction • All Scope Changes are handled through the previously established DCN process • Completed VE redesign on 16 October 2006 • SLAC/Jacobs currently evaluating impact of CLOC deletion on remaining scope. .

  5. LCLS Jim Cranston Jacobs On-site CA Manager Cypress Project Management Dave McDonough Jacobs MOP Boston Portland TurnerConstruction Walnut Creek AE Title III Status

  6. AE Title III Status RFI’s Reviewed Bid RFI’s -180 (15days) Contractor RFI’s - 58 (9days) • Projected turn- around time = 5 Days

  7. AE Title III Status Submittals Status: Projected turn-around time = 10 days Current Average Turn-around time = 12 days* * After removal of several anomalies.

  8. AE Title III Status Management Goals • Reduce turn-around time for review of RFI’s and Submittals • Improve response time to Design Modification requests • Continue improvement of communications between SLAC, Turner and Jacobs

  9. AE Title III Status Questions?