1 / 15

HSE’s Ageing and Life Extension Key Programme (KP4) and Human Factors

HSE’s Ageing and Life Extension Key Programme (KP4) and Human Factors. Peter Fearnley, Energy Division - Offshore. KP4 website: www.hse.gov.uk/offshore/ageing.htm. ……..Covering……. Why? Ageing and Life Extension Equipment, Systems and People What can I do, what can I ask. Why?.

haines
Télécharger la présentation

HSE’s Ageing and Life Extension Key Programme (KP4) and Human Factors

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HSE’s Ageing and Life Extension Key Programme (KP4) and Human Factors Peter Fearnley, Energy Division - Offshore KP4 website: www.hse.gov.uk/offshore/ageing.htm

  2. ……..Covering……. • Why? • Ageing and Life Extension • Equipment, Systems and People • What can I do, what can I ask

  3. Why? • UKCS operates a Safety Case Regime • The Safety Case describes measures in place reducing major accident risks to people to the lowest reasonable level • *There are proper arrangements in place for an independent audit of the systems (?)* • The systems are complex and need all our attention to remain effective

  4. Why? People Fitness Competence Morale/Trust Perception Behaviour Facilities & Equipment Design Work Environment Maintenance Reliability Demand To be safe all 3 have to work well, together Systems Hazard identification Risk assessment Management Commitment Procedures, Training Incident investigation Monitoring Change Learning

  5. Why? Facilities & Equipment • Design • Work Environment • Maintenance • Reliability • Demand Ageing and Life Extension Systems Hazard identification Risk assessment Management Commitment Procedures, Training Incident investigation Monitoring Change Learning People Fitness Competence Morale/Trust Perception Behaviour History of Development

  6. WHAT ARE AGEING & LIFE EXTENSION? Across the European Union’s hazardous industries ageing is implicated in: 30% of incidents 28% of loss of containment AGEING “Ageing is not about how old your equipment is; it’s about what you know about its condition, and how that’s changing over time” Condition Management is the key LIFE EXTENSION • When assets exceed design life = Life Extension phase • Half UKCS production platforms in LE phase • Some platforms anticipate 50-70 years production • Plus 5-10 years to removal from sea bed

  7. What Is ALE?It’s All About Managing AgeingForth Rail Bridge • Opened 4th March 1890 (~123 years old) • Robust structure • 200 trains per day • Continuous painting programme

  8. What Is ALE?It’s All About Managing AgeingForth Road Bridge • Opened 4th September 1964 (~48 years old) • Highly engineered structure • 32 000 vehicles per day • IM programme didn’t identify cable corrosion risk • 2003: numerous wire strands in suspension cables found to be corroded and failed • Weight restrictions applied • Needs replacing ~£1.4 Billion

  9. WHAT IS KP4? • Raising awareness of consequences of ALE • Understanding & forecasting degradation mechanisms & rates of Safety Critical Elements • Obsolescence management • Sharing ALE knowledge for the benefit of all • Working with industry for a common goal • Reducing Hydrocarbon Releases *MAINTAINING AND IMPROVING SAFETY*

  10. WHAT HAS KP4 COVERED? • Process Safety, Fire and Explosion • Structures • Marine • Mechanical and Corrosion • Electrical, Control and Instrumentation • Pipelines • Human and Organisational Factors

  11. HYDROCARBON LEAKS:EQUIPMENT, SYSTEMS, PEOPLE Norwegian study found: • 60% of leaks due to human interventions; • key issues: • failure to check pre and post-work isolations and integrity; • Technical degradation caused ~21% of HC leaks • No relationship between age and leak frequency – condition management! • 100% management system failure? Equipment, Systems, People

  12. EQUIPMENT, PEOPLE AND SYSTEM ISSUES When equipment doesn’t work as designed (ALE), carry out risk assessment Risk Perception & Assessment HSE still finding problems with Operational Risk Assessments (ORA) – risk assessment can be too difficult Failures identifying and addressing MAH risks, see ORA guidance rolled out by OGUK Clear procedures guiding correct thought process, e.g. ORA default should be shut-down unless there are good reasons to continue operations

  13. WORKFORCE INVOLVEMENT IN ALE Need to equip people at all levels of the organisation with the right skills to recognise and respond to risk Hazard awareness, assessment & anticipation Need to understand and actively manage the factors that influence human performance, e.g. operating wrong valve, not following a procedure Distractions, badly written procedures, poor communication, lack of feedback Need to develop a culture where ‘speaking up about concerns’ is managed appropriately acceptable for ‘bad news’ to travel up the line

  14. What Can I Do, What Can I Ask? • Getting ALE and People (HF) issues right requires a focus – where is it in your organisation? • Does your organisation have an ALE policy? • How well are they doing? • What are they planning to improve? • Are you clear what your part is in this?

  15. What Can I Do, What Can I Ask? • Does your organisation have a clear approach to dealing with people issues/human factors? • Do you see it worked out in incident and near-miss investigations? • Are the reasons for mistakes understood and does this make a difference to the way jobs/tasks are planned and carried out? • Are audits, monitoring and other learning seen as vital to stopping incidents before they happen?

More Related