1 / 23

Bowie State University Fine and Performing Arts Center

Bowie State University Fine and Performing Arts Center. Zachary Lippert Faculty Advisor: Dr. Stephen Treado. Bowie State University Fine and Performing Arts Center. Project Team Owner: University of Maryland CM: Holder Construction Company

hali
Télécharger la présentation

Bowie State University Fine and Performing Arts Center

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bowie State University Fine and Performing Arts Center Zachary Lippert Faculty Advisor: Dr. Stephen Treado

  2. Bowie State University Fine and Performing Arts Center Project Team Owner: University of Maryland CM: Holder Construction Company Architect: EYP Architecture and Engineering Mechanical Contractor: W.E. Bowers Electrical Contractor: Mona Electric Controls Contractor: Seimens Commissioning Authority: EMC/Eaton MEP Engineer: EYP Architecture and Engineering • Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion Zachary Lippert Faculty Advisor: Dr. Stephen Treado

  3. Project Overview • Site • Bowie, Maryland • Southeast corner of campus • Project Information • 123,000 square feet • $79 million • Design-Bid-Build delivery method • Architecture • Large expanse of glass • Mixed use building • Multiple large performance spaces • Art gallery • Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion Courtesy of Google Maps

  4. Existing Mechanical System • 3 Mixed Air Units with enthalpy wheels • 16 Air Handling Units • 64 VAV boxes (40 to 1,200 CFM) • Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion

  5. Existing Mechanical System • Two 1712 MBH gas fired boilers • Four heating water pumps • 305 ton air cooled chiller • Four chilled water pumps • Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion

  6. Existing Mechanical System • Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion

  7. Proposed Redesign • Goals for the redesign • Improve the mechanical efficiency • Reduce utility bills • Redesign Components • Ground source heat pump • Underfloor air distribution • Energy efficient lighting system • Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion

  8. Ground Source Heat Pump • Soil type • Cretaceous • Diffusivity = .9 ft2 /day • Conductivity = 1.1 Btu/h*ft*°F • Calculations • Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion

  9. Ground Source Heat Pump • Equipment • 510 bores at 544 ft • 2 gpm/ton • System flow rate: 410 gpm • 5” headers and 1” U-tube piping • Total head loss: 54 ft of water • Two 10 HP 1750 RPM pumps • Energy Model • Heating: Saved 411,164 kBtu/year • Cooling: Saved 153,327 kBtu/year • Auxiliary: Used additional 237,532 kBtu/year • Net Savings: 326,959 kBtu/year • Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion

  10. Underfloor Air Distribution • Location of the systems • Large volume spaces • Encourage stratification • Duct layout • Less ductwork • Lower pressure drop • Less fan power • Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion

  11. Underfloor Air Distribution • Energy Usage • Minor reduction in cooling load • Significant increase in heating load • Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion • System Drawbacks • Raised floor system • Larger fan • More materials • Longer construction time • Uses more energy • This system was not further investigated • System Sizing • Increased duct length ~20% • Increased fan power and size

  12. Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion • Energy Efficient Lighting • Redesign Goal • Reduce the yearly kWh in the offices and classrooms • Provide adequate light for required tasks • Methods • Energy efficient luminaires • T5HO lamps • Occupancy sensors

  13. Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion • Energy Efficient Lighting • Existing Lighting Design • Offices • Recessed direct luminaires • Two foot luminaires with two 40 Watt TT5 lamps • 1.55 Watts/sq. ft. • Classrooms • Recessed direct luminaires • Four foot luminaires with two 32 Watt T8 lamps • 1.47 Watts/sq. ft. • Proposed Lighting Design • Offices and classrooms • Suspended direct/indirect luminaires • Four foot luminaires with one 54 Watt T5HO lamps

  14. Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion • Energy Efficient Lighting • Illuminance Values • Office: 30 foot-candles • Music Classrooms: 15 foot-candles • AGI Model • Less watts per luminaire • Half as many luminaires • Excellent energy savings

  15. Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion • Energy Efficient Lighting • Occupancy Sensors • Offices: Passive infrared • Classrooms: Ultrasonic • Equivalent Full Load Hours • Offices: 2870 • Classrooms: 2522 • Hours Saved • Offices: 1091 • Classrooms: 1463

  16. Classroom Energy Savings • Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion Office Energy Savings

  17. Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion • Ground Source Heat Pump Cost and Savings • Total System Cost: $2,938,000 • BG&E Incentive: $1,000,000 • Net Cost: $1,938,000 • Total Utility Savings: -$665.27

  18. Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion Lighting Redesign Cost and Savings

  19. Simple Payback • Occupancy Sensor Costs and Savings • Initial Cost of Sensors: $4,480 • BG&E 75% Incentive: $1,120 • Cost of Installation: $10,080 • Net Total Cost: $11,200 • Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion • Occupancy Sensor Cost and Savings • Initial cost of sensors: $4,480 • BG&E 75% Incentive: $1,120 • Cost of Installation: $10,080 • Net Total Cost: $11,200 • Simple Payback

  20. Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion • Recommendations • Ground Source Heat Pump • Reduced energy consumption • Expensive to install • Increased utility costs • Explore other options • Underfloor Air Distribution • Expensive to install • Increased energy consumption • Increased construction time • Explore other options • Lighting Redesign • Less expensive to install • Reduced energy consumption and costs • Implement this design • Occupancy Sensors • Reduced energy consumption and costs • More expensive to install • 8.8 year payback • Implement this design

  21. Presentation Outline • Project Overview • Existing Mechanical System • Proposed Redesign • Ground Source Heat Pump • Underfloor Air Distribution System • Lighting Breadth • Cost and Savings • Recommendations • Conclusion Acknowledgements Architectural Engineering Faculty and Staff Dr. Stephen Treado Adam Seigrist and Mike Luffred of EMC/Eaton Hayes Todd of Holder Construction My Friends and Family Questions?

More Related