This document analyzes the strategies involved in crashing a project timeline by 4 days, focusing on the actions and impacts for various tasks labeled A through G. The evaluation includes a cost analysis of different crashing techniques, providing insights into the optimal actions to accelerate project delivery. It identifies the implications of issues such as resource allocation and the potential for setting back other elements of the project. This analysis is essential for project managers aiming to effectively manage timelines while controlling costs.
E N D
C(4) Act. Imed. Pred. Time Crash the project by 4 days A None 7 B A 3 C A 4 D B,C 5 E D 2 F D 4 G E,F 5 B(3) F(4) G(5) D(5) A(7) E(2)