1 / 22

Edmonton’s Anthony Henday Drive Unique Challenges

Edmonton’s Anthony Henday Drive Unique Challenges. Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014. Alberta’s Ring Roads. Planned in mid-1960’s around Alberta’s two major cities Began purchasing land in late 1960’s and early 1970’s Freeway standard roadway.

Télécharger la présentation

Edmonton’s Anthony Henday Drive Unique Challenges

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Edmonton’s Anthony Henday DriveUnique Challenges Saskatchewan P3 Summit 2014 Regina, Saskatchewan September 9, 2014

  2. Alberta’s Ring Roads • Planned in mid-1960’s around Alberta’s two major cities • Began purchasing land in late 1960’s and early 1970’s • Freeway standard roadway

  3. Project Delivery Mechanisms • Traditional Design-Bid-Build • Design-Build • Design-Build-Finance-Operate • also known as Public Private Partnerships (P3)

  4. Edmonton Ring RoadCurrent Status • 90% open to traffic • Design and construction started in 2000 • 80 km total length • Fully complete in fall 2016 • $4.3 billion invested to date

  5. Edmonton Ring Road

  6. Edmonton Ring RoadDelivery Time Frames • Anthony Henday Southwest – 12 years (Design-Bid-Build) • Anthony Henday Southeast – 3 years (P3) • Anthony Henday Northwest – 3.5 years (P3) • Anthony Henday Northeast – 4.5 years (P3)

  7. Calgary Ring RoadCurrent Status • 70% open to traffic • Design and construction started in 2003 • 100 km total length • $1.9 billion invested to date • Southwest segment remains to be completed

  8. Calgary Ring Road

  9. Calgary Ring RoadDelivery Time Frames • Stoney Trail Northwest – 12 years (Design-Bid-Build) • Stoney Trail Northeast – 3 years (P3) • Stoney Trail Southeast – 3.5 years (P3)

  10. Public Private Partnership Projects

  11. Alberta P3 Philosophy • P3 projects must demonstrate value for money • Risk transferred to the party best able to manage it • Agreement terms and technical requirements set before bids are submitted • No negotiation after submission of bids

  12. Risk Allocation - Construction

  13. Risk Allocation - Operations

  14. Challenges:Quality Management • Implementation of contractor’s quality plan • staff with appropriate experience and qualifications • clearly defined roles for quality control and quality assurance • authority for quality management team to affect construction operations • contractor’s ability to make adjustments as required • Design and construction issues • meeting technical requirements • addressing non-conformance • rejection versus modification • garnering support from consortium level

  15. Challenges:Fast-Track Design-Build • Ensure it is designed before it is built • Everything is on fast-track schedule • Designs are completed and submitted in sub-elements

  16. Challenges:Regulatory Approvals For River Crossing • Completed some preliminary engineering for river crossings during Functional Planning Study • Met with Department of Fisheries and Oceans and Transport Canada well in advance of issuing RFQ • Incorporated regulatory review and input during RFP process • Expedited contractor’s ability to obtain regulatory approval for construction

  17. Challenges:Utilities within Project Limits • Completed Hydrovac exposure of all underground utilities (approximately 500) and made information available to proponents during RFP phase • Existing utility agreements made available to proponents • Contractor required to coordinate relocations with their work • Getting utility crossing agreement with several different companies for construction phase • Shared risk for cost of utility relocations • up to $120 million borne by contractor • from $120 to $160 million shared 50/50 with department • beyond $160 million shared 25/75 with department

  18. Challenges:Agreements with Railway Companies • Initiated discussions with CP Rail and CN Rail well in advance of issuing RFQ • Agreement reached on cost apportionment • Objective to have railway agreements signed and available to proponents during RFP phase

  19. Challenges:Traffic Management During Construction • Projects include reconstruction of existing freeway and interchanges • Significant traffic disruptions occur over full duration of project • RFP included requirements to submit construction management plan along with staging analysis

  20. Challenges:Public Communications • Multiple stakeholders • Public expectations • open house/information sessions • traffic advisories • addressing complaints

  21. Thank you

More Related