Capital Improvement Program (CIP) Overview
Capital Improvement Program (CIP) Overview. Nick Kanetis, P.E. June 14, 2013. OCSD Service Area 479 square miles 210 million gallons per day 2.5 million population 21 cities, 3 special districts 580 miles of sewers 15 pump stations 2 treatment plants. Los Angeles. Orange County.
Capital Improvement Program (CIP) Overview
E N D
Presentation Transcript
Capital ImprovementProgram (CIP) Overview Nick Kanetis, P.E. June 14, 2013
OCSD Service Area479 square miles210 million gallons per day 2.5 million population 21 cities, 3 special districts 580 miles of sewers 15 pump stations 2 treatment plants Los Angeles Orange County ServiceArea San Diego
Reclamation Plant No. 1Fountain Valley Treatment Plant No. 2Huntington Beach
Background • EPA Consent Decree Secondary Treatment 2002 - 2012 • Full Secondary December 2012 • Future Renewal, Replacement and Rehabilitation
Strong Financial Position • Revenues from user fees and connection fees • Proactive forecasting and planning • AAA Bond Rating
More than 70 Projects $1.8 Billion Dollars invested in our Infrastructure
Secondary Treatment ExpansionSix EPA Consent Decree Milestones
Trickling Filters at Plant No. 2 Designer: Brown & Caldwell Contractor: J.F. Shea Construction Construction Cost: $182M - Capacity: 60 MGD
New Secondary Treatment at Plant No.1 Designer: Black & Veatch Contractor: Kiewit Infrastructure West Construction Cost: $207M – Capacity 60 MGD
Headworks at Plant No. 2 Odor Control System Demolition of Existing Headworks Designer: Carollo Eng. Contractor: J.F. Shea Construction Construction Cost: $196M - Capacity 340 MGD
Outfall Land Section & OOBS Piping Rehabilitation Designer: Black & Veatch Contractor: J.F. Shea Construction Construction Cost: $11.8
Central Generation Automation Designer: Black & Veatch Contractor: Morrow Meadows/Sachs Electric Construction Cost: $14.6M
Magnolia Trunk Sewer Rehabilitation Design/Build: Kiewit Infrastructure West Design/Build Cost: $15.5M
Sludge Dewatering & Odor Control at Plant No. 1 Exterior finish Ground level Designer: HDR Eng. Contractor: W. M. Lyles Construction Cost: $127M
Pump Stations Rocky Point Pump Station Bitter Point Pump Station Designer: Malcolm Pirnie Contractor: Kiewit Inf. West Construction Cost: $9.2M Designer: Lee & Ro Contractor: Kiewit Inf. West Construction Cost: $20.2M
100% Secondary Standards 70 mgd Reclamation Increased System Reliability Lower engine emissions Less Odors Disinfection Treat Urban Runoff Fire & Safety Code Compliance IncreasingLevel of Service
CIP DriversEnhanced Planning Methodology Capacity Level of Service or Regulatory Change Plant or Collection System Condition Of Assets Business Efficiency & Research Outcome
CIP DriversEnhanced Planning Methodology Capacity Plant or Collection System Level of Service or Regulatory Change Condition OfAssets Business Efficiency & Research Outcome
CIP DriversTransition to Rehabilitation Before Cleaning Inspection After Cleaning Lining Failure
Future Focus • Project Scope Development • Resource Forecasting • Risk Management • Emphasis on Schedules • Change Order Controls • Outreach to Cities
FY 2013-14 CIP Expenditures $141 MillionMostly Rehabilitation
Upcoming Planned Projects • Headworks Rehabilitation - $50 Million • Outfall Pump Station Rehabilitation - $20 Million • Primary Clarifier Rehabilitation - $120 Million • Digesters Rehabilitation - $50 Million • Digester Gas Facilities Rehabilitation - $40 Million • Collections Rehabilitations - $100 Million • Odor Control Master Planning - $20 Million • Admin. Facilities Master Planning - $40 Million