1 / 28

IE 419 Work Design: Productivity and Safety Dr. Andris Freivalds Class #2

IE 419 Work Design: Productivity and Safety Dr. Andris Freivalds Class #2. NEED FOR SAFETY – 5. Myths, misconceptions Safety doesn’t sell Catastrophic failures main concern Safety slows operations Safety is human (operator, user) problem Cheaper to pay insurance (McWane??)

hewitt
Télécharger la présentation

IE 419 Work Design: Productivity and Safety Dr. Andris Freivalds Class #2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IE 419 Work Design:Productivity and Safety Dr. Andris Freivalds Class #2 IE 419

  2. NEED FOR SAFETY – 5 • Myths, misconceptions • Safety doesn’t sell • Catastrophic failures main concern • Safety slows operations • Safety is human (operator, user) problem • Cheaper to pay insurance (McWane??) • Making product safer increases costs IE 419

  3. NEED FOR SAFETY – 5 cont’ COSTS AMOUNT OF SAFETY IE 419

  4. IE 419 – Work Design • Productivity • Productivity tools: PERT, Worker-machine charts, line balancing, plant layout • Work measurement: MTM-2, MOST, Work sampling • Safety • General safety principles: how torecognize & analyze problem, select & apply remedy • Quantitative analyses: JSA, fault-tree, cost-benefit • Legal aspects: Workers Comp, OSHA • Hazards: recognize & control specific hazards IE 419

  5. PRODUCTIVITY TOOLS Methods Study = Systematic recording of existing and proposed ways of doing work in order to improve productivity (to improve the job for the operator) • Select project • Get and present data • Analyze data • Develop ideal method IE 419

  6. Fig. 2.1 – Steps in Methods Study IE 419

  7. #1 – Select Project Pareto analysis • aka: 80-20 rule • 80% of problems from 20% of jobs • Focus on the 20% • Plot in descen-ding order as cumulative proba-bility distribution • DesignTools IE 419

  8. #1 – Select Project Gantt Chart • Horizontal bar chart of activities, shaded if done • A snapshot of the status of all activities • Focus efforts on those that are behind schedule IE 419

  9. METHODS STUDY (Next?) • Get and present data • Analyze data • Develop ideal method • All of these overlap • Use special charts • Quicker, efficient, for IEs • Focus on productivity improvement IE 419

  10. PERT and CPM (pp. 27-30) • PERT = Program Evaluation and Review Technique (1950s) • Booz Allen for U.S. government & military • Time has uncertainty • Minimizing time is main goal • CPM = Critical Path Method (1950s) • DuPont for large scale projects • Time is specified • Trade-off between cost and completion date IE 419

  11. BASICS • Set of well defined jobs (activities) • Totality of which defines a project • Jobs start/stop independently of each other • Jobs are ordered in specific (technological) sequence • Forms a graphical network diagram • Allows computational estimates IE 419

  12. GOALS/QUESTIONS • How long if every job works out ideally? (optimistic estimate) • How long if everything goes wrong? (pessimistic estimate) • With average conditions → likely result • How can project be shortened at least cost? (trade-offs) IE 419

  13. RULES/PROCEDURES #1 • List jobs and estimated duration time • Draw network diagram • Arcs or vectors to depict jobs • Arrows to indicate direction (progress) • Numbered nodes to indicate events • Events = start and end of jobs IE 419

  14. Job A Job B Job A Job C Dummy Job Job B Job D RULES/PROCEDURES #2 • No two jobs can be identified by same nodes 3 • 1 2 1 2 • Dummy jobs take no time, no resources • Only to show dependency 1 3 2 Job A Use Dummy Job Job B IE 419

  15. 4 1 2 3 5 4 1 2 3 5 C A D D E E B B C A RULES/PROCEDURES #3 • Show precedence relationships (IP) clearly • Jobs B & C both required for Job D • Job C not required for Job D (but needed further on) IE 419

  16. RULES/PROCEDURES #4 • Time = estimated duration of each job • Earliest start time (ES) = such that IP hold • Latest start time (LS) = without delaying project completion • Earliest finish (EF) = ES + time to complete job • Latest finish (LF) = LS + time complete job • Critical jobs = jobs which delayed, delay project • Float (slack) = difference between ES and LS; time that noncritical jobs can be ↑, without delaying project • Critical path = longest path of critical jobs, determines duration of project; zero float IE 419

  17. Ex #1- CRITICAL PATH (Travel Times) • Two PSU profs (Allen, Booz) drive to Washington DC for a meeting with their contract sponsor (U.S. Army) • Prof. Allen leaves State College at 8 AM • drives to Philadelphia (KP, 3 hrs) • get materials from subcontractor Lockheed Martin (0.5 hr) • then onto Washington DC (2.5 hrs) • Prof. Booz leaves State College 8 AM • drives to Pittsburgh (3 hrs) • meets 3rd prof (collaborator) for lunch (2 hrs) • then onto Washington DC (4.5 hrs) • What is earliest they can meet for dinner? IE 419

  18. 2 3 3 Booz 0.5 Allen 4.5 2.5 Ex. CRITICAL PATH - 2 IE 419

  19. Ex. CRITICAL PATH – 3Network Table IE 419

  20. Ex. CRITICAL PATH – 4Network Diagram 0.5 LM Ph 2.5 3 SC DC 3 4.5 Pi Lu 2 Critical Path = 3 + 2 + 4.5 = 9.5 Earliest dinner: 8 + 9.5 = 5:30 PM IE 419

  21. Ex. CRITICAL PATH - 5 • Critical path = 9.5 hours • Earliest dinner is 5:30 PM • Allen can leave 3.5 hrs later (11:30 AM) • Or drive more slowly, sightsee • Flexibility or slack in time = float • Practically: If Booz shortens lunch to 1 hr, then could meet a 4:30 PM IE 419

  22. Ex #2 – CPM and FLOAT (Building a House) 7 major steps in building a house (months): • A - Design & obtain financing (3) • B - Lay foundation (2) • C - Order materials (1) • D – Build house (3) • E – Select paint (1) • F – Select carpet (1) • G – Finish work (1) IE 419

  23. Ex #2 – CPM and FLOAT - 2 3 B 2 A 3 D 3 G 1 6 4 7 2 1 C 1 F 1 E 1 5 IE 419

  24. 3 B 2 A 3 D 3 G 1 6 4 7 2 1 C 1 F 1 E 1 5 Critical Path = IE 419

  25. 3 B 2 A 3 D 3 G 1 6 4 7 2 1 C 1 F 1 E 1 5 Forward Pass ES = max (EFi) EF = ES + t IE 419

  26. 3 B 2 A 3 D 3 G 1 6 4 7 2 1 C 1 F 1 E 1 5 Backward Pass LF = min (LSi) LS = LF - t IE 419

  27. 3,53,5 3 5,55,5 B 2 8,9 8,9 5,85,8 A 3 D 3 G 1 6 4 7 2 1 C 1 0,30,3 3,44,5 F 1 6,77,8 E 1 5 5,66,7 Float = LS – ES = LF – EF IE 419 Critical path = all with 0 float =

  28. 3 B 2 A 3 D 3 G 1 6 4 7 2 1 C 1 F 1 E 1 5 Crashing – Expediting job, reallocation of resources to shorten project duration IE 419

More Related