1 / 28

Greg Blatt Penn State Architectural Engineering Construction Management April 12, 2004

Greg Blatt Penn State Architectural Engineering Construction Management April 12, 2004. 901 New York Avenue Washington, D.C. Greg Blatt Construction Management. 901 New York Avenue Washington, D.C. Greg Blatt Construction Management.

hhodges
Télécharger la présentation

Greg Blatt Penn State Architectural Engineering Construction Management April 12, 2004

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Greg Blatt Penn State Architectural Engineering Construction Management April 12, 2004

  2. 901 New York AvenueWashington, D.C. Greg Blatt Construction Management

  3. 901 New York AvenueWashington, D.C. Greg Blatt Construction Management

  4. 901 New York AvenueWashington, D.C. Project Information • Class A Office Building • Cost: $54,000,000 • Size: 580,00 Square Feet • Construction Dates: August 2002 – October 2004 • Uses: Office space, street-level retail, underground parking garage, & a health club Greg Blatt Construction Management

  5. 901 New York AvenueWashington, D.C. Pour Sequencing Foundation Redesign LEED Certification Greg Blatt Construction Management

  6. 901 New York AvenueWashington, D.C. Original Parameters POUR SEQUENCING FOUNDATION REDESIGN LEED • 9 pours per floor • Columns poured the day after the slab for each section • Pour #1 for each floor was started after Pour #4 for the previous floor • Originally scheduled from May 20, 2003 to November 6, 2003 • 124 days on the schedule Greg Blatt Construction Management

  7. 901 New York AvenueWashington, D.C. Pour Breaks POUR SEQUENCING FOUNDATION REDESIGN LEED 7 1 5 4 3 2 8 6 9 Greg Blatt Construction Management

  8. 901 New York AvenueWashington, D.C. Proposed Parameters POUR SEQUENCING FOUNDATION REDESIGN LEED • 9 pours per floor • Columns poured the day after the slab for each section • Pour #1 for each floor was started after Pour #4 for the previous floor • Originally scheduled from May 20, 2003 to October 31, 2003 • 119 days on the schedule • Durations changed on the lower floors to accelerate the schedule Greg Blatt Construction Management

  9. 901 New York AvenueWashington, D.C. Comparison POUR SEQUENCING FOUNDATION REDESIGN LEED Greg Blatt Construction Management

  10. 901 New York AvenueWashington, D.C. Sequencing Conclusion POUR SEQUENCING FOUNDATION REDESIGN LEED • One week was saved due to the schedule acceleration. • Other trades can begin their work earlier. • This allows the occupants to move into their spaces earlier. • The owner will be able to start to make money on building at an earlier date. Greg Blatt Construction Management

  11. 901 New York AvenueWashington, D.C. Pour Sequencing Foundation Redesign LEED Certification Greg Blatt Construction Management

  12. 901 New York AvenueWashington, D.C. Foundation Redesign POUR SEQUENCING FOUNDATION REDESIGN LEED • Change from column footings to a mat foundation • Potential savings in the schedule • Mat foundation will be more expensive (extra materials & labor) • Economical comparison Greg Blatt Construction Management

  13. 901 New York AvenueWashington, D.C. Original Design POUR SEQUENCING FOUNDATION REDESIGN LEED • 146 Column Footings • 39 are combined footings • Smallest Footing – 4’-6” x 4’-6” x 21” • Largest Footing – 17’-0” x 17’-6” x 64” • 15,000 psi soil bearing capacity • Scheduled for 35 days • Estimated Cost of $645,966 Greg Blatt Construction Management

  14. 901 New York AvenueWashington, D.C. Mat Foundation Design POUR SEQUENCING FOUNDATION REDESIGN LEED • Check for punching shear • Determine thickness for different strengths of concrete • Estimate costs for each strength of concrete • Estimate time duration • Compare to column footing design Greg Blatt Construction Management

  15. 901 New York AvenueWashington, D.C. Mat Foundation Design POUR SEQUENCING FOUNDATION REDESIGN LEED Greg Blatt Construction Management

  16. 901 New York AvenueWashington, D.C. Mat Foundation Design POUR SEQUENCING FOUNDATION REDESIGN LEED • 6,000 psi concrete foundation was the least expensive of the 4 options analyzed • Estimated to take 45 days to complete Greg Blatt Construction Management

  17. 901 New York AvenueWashington, D.C. Foundation Comparison POUR SEQUENCING FOUNDATION REDESIGN LEED Greg Blatt Construction Management

  18. 901 New York AvenueWashington, D.C. Foundation Conclusion POUR SEQUENCING FOUNDATION REDESIGN LEED • Mat foundation costs approximately $810,000 more than the column footings. • Mat foundation is estimated to take 10 more days to complete than the column footings. • Overall, the column footings were a better choice as a foundation system for this project. Greg Blatt Construction Management

  19. 901 New York AvenueWashington, D.C. Pour Sequencing Foundation Redesign LEED Certification Greg Blatt Construction Management

  20. 901 New York AvenueWashington, D.C. LEED Certification POUR SEQUENCING FOUNDATION REDESIGN LEED • Analyze the project to check if it meets the minimum LEED Certification requirements. • If it does not meet those requirements, suggest ways to get the project to an acceptable certification level. Greg Blatt Construction Management

  21. 901 New York AvenueWashington, D.C. LEED Certification POUR SEQUENCING FOUNDATION REDESIGN LEED • LEED Rating Version 2.1 • Rated: 26 – 32 points • Silver: 33 – 38 points • Gold: 39 – 51 points • Platinum: 52 + points • Total of 69 points that can be earned Greg Blatt Construction Management

  22. 901 New York AvenueWashington, D.C. Initial LEED Analysis POUR SEQUENCING FOUNDATION REDESIGN LEED LEED SECTION points earned / points possible Sustainable Site 6 / 14 Water Efficiency 1 / 5 Energy & Atmosphere 3 / 17 Materials & Resources 0 / 13 Indoor Environmental Quality 0 / 15 Innovation & Design Process 1 / 5 Total 11 / 69 Greg Blatt Construction Management

  23. 901 New York AvenueWashington, D.C. Suggestions POUR SEQUENCING FOUNDATION REDESIGN LEED • Dedicated Outdoor Air System (DOAS) • Construction Waste Management System • Use of Local/Regional Materials • Additional Daylighting • Designated spots for carpooling Greg Blatt Construction Management

  24. 901 New York AvenueWashington, D.C. LEED Analysis w/ Suggestions POUR SEQUENCING FOUNDATION REDESIGN LEED LEED SECTION points earned / points possible Sustainable Site 7 / 14 Water Efficiency 4 / 5 Energy & Atmosphere 4 / 17 Materials & Resources 6 / 13 Indoor Environmental Quality 9 / 15 Innovation & Design Process 4 / 5 Total 33 / 69 Greg Blatt Construction Management

  25. 901 New York AvenueWashington, D.C. LEED Conclusion POUR SEQUENCING FOUNDATION REDESIGN LEED • The original design would not meet LEED Certification requirements. • By implementing the suggested items, 33 credits were obtained for the certification process. • The suggested items led to a rating of Silver for the project. Greg Blatt Construction Management

  26. 901 New York AvenueWashington, D.C. Conclusions Pour Sequencing – Accelerated the schedule by 1 week Foundation Redesign – Column footings are a better choice than a mat foundation LEED Certification – Changes could be implemented to reach a minimum certification level. Greg Blatt Construction Management

  27. 901 New York AvenueWashington, D.C. THANK YOU Alison Starner – Clark Construction Marshall Singh – Clark Construction Cathy Barus – Clark Construction Jon Kolbe – Clark Concrete Frank Schultz – Hensel Phelps Walt Schneider – AE Faculty AE Faculty & Staff Family & Friends Greg Blatt Construction Management

  28. 901 New York AvenueWashington, D.C. QUESTIONS Greg Blatt Construction Management

More Related