1 / 15

Aceh Project, Indonesia ‘Biting the Bullet’ Shelter Meeting 09a 7-8 May 2009 Geneva, Switzerland

Aceh Project, Indonesia ‘Biting the Bullet’ Shelter Meeting 09a 7-8 May 2009 Geneva, Switzerland. Medair brings life-saving relief and rehabilitation in disasters, conflict areas and other crises by working alongside the most vulnerable

hollie
Télécharger la présentation

Aceh Project, Indonesia ‘Biting the Bullet’ Shelter Meeting 09a 7-8 May 2009 Geneva, Switzerland

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Aceh Project, Indonesia ‘Biting the Bullet’ Shelter Meeting 09a 7-8 May 2009 Geneva, Switzerland

  2. Medair brings life-saving relief and rehabilitation in disasters, conflict areas and other crises by working alongside the most vulnerable Created in 1989, a non-governmental organisation independent of any political, economic, social or religious authority More than 2 million beneficiaries served per year, 8 country programmes in 7 countries of operation: Afghanistan, Congo, Indonesia, Madagascar, Somalia, Sudan (N&S states), Uganda Head Office in Switzerland, 5 affiliate offices in France, Germany, The Netherlands, UK and the USA International Head Office in Switzerland with more over 70 staff; 120 internationally recruited staff in the field plus 980 nationally recruited staff ISO 9001:2001 certification worldwide, and Swiss ZEWO certification More than US$ 25 million total budget 85% of budget spent on humanitarian expenses Medair International Overview

  3. Our values Accountability, Compassion, Dignity, Hope, Integrity and Faith Our Core Competencies Emergency Relief Rehabilitation Our Sectors of Expertise Medair employs a multisectoral approach: Health Services Water & Sanitation Shelter & Infrastructure Additional Competencies Capacity building (‘Good Enough Guide’ contributor) Beneficiary accountability (HAP-I founder member) Medair International Overview

  4. Vulnerability Assessment Is the region isolated, remote or hard-to-access? Is the region impacted by a natural disaster, conflict or crisis? Is the region underdeveloped? Is the region experiencing life-threatening poverty? Is there a high percentage of refugees or internally displaced persons (IDPs)? Is there a high percentage of underweight children? Is there a high mortality rate for children under five? Is there limited or no access to humanitarian aid? Has the crisis been largely forgotten? Answers to the vulnerability assessment produce a measure of a population or region’s vulnerability, and help Medair determine whether it will launch an emergency relief and rehabilitation programme in the country Medair International Overview

  5. Kosovo, 2000-1:130 houses + 278 roofs built, 497 windows + 1453 windows distributed using voucher system in builders merchants; cash for shelter, camp management in Albania Mozambique, 2000:431 houses built with roads/ trees in new planned settlement, 52,000 hoes/ 6,500 household kits/ 9,600 mosquito nets distributed; 1 school, 1 clinic, 13 health posts India, 2001:1,087 families assisted with semi-permanent housing in Gujarat State through self-build programme Sri Lanka, 2004:3,000 transitional shelters constructed to ZOA design; latrines + access to clean water; boats + nets for 600 fishermen Iran, 2004-5:633 earthquake-resistant houses constructed/ completed to government approved design; 4km of irrigation channels repaired; 34 classrooms in ‘Connex’ buildings Pakistan, 2005-6:6,261 families received shelter kits, 1,273 tents distributed, 11,064 ppl trained in disaster mitigation; shelter kits for 14 rural health clinics; 11 schools TOTAL: 11,600+ shelter units completed/ rehabilitated Selected Shelter & Infrastructure Responses

  6. Indonesia Aceh Project Review Initial Context • Asian Tsunami struck on 26th December 2004 causing major damage. Decision made to go into Sri Lanka, rather than Indonesia. • Significant tsunami-restricted funds still available into 2006. • Needs assessment carried out April/ May 2006. • Main needs identifed as access to clean water and sanitation • First phase of project began in July 2006. • Developments • Earthquake struck Nias island March 2005 (3 months post-tsunami). • Nias – very poor, under-funded Christian island off Sumatra • Needs assessment carried out April & August 2006. • Main needs identifed as access to health facilities & clean water. • Project began in February 2007.

  7. Initial Strategy SO1 Support tsunami survivors to return to their permanent homes as quickly as possible by enabling safe water and effective sanitation in Aceh SO2 Support earthquake survivors in Nias to not only recover to pre-disaster conditions but reduce future vulnerability with rehabilitation of water & sanitation and health facilities as well as sustainably improve the quality of health care SO3 A flexible emergency response capacity to respond to disasters and still unmet recovery needs in Indonesia SO4 Disaster mitigation and preparedness activities within each intervention SO5 Seek out other people in need of disaster recovery assistance who have so far received little help Funding Chaîne du Bonheur (Swiss Solidarity), Tearfund UK, Cedar Fund Indonesia Aceh Project Review

  8. Indonesia Aceh Project Review Proposed household septic tank and treatment garden

  9. Indonesia Aceh Project Review Initial Project • Aceh project was set up in two phases: • Phase 1 from July 2006 to August 2007 • Phase 2 from December 2006 to November 2007 • Total Expenditure: $2.7m • Main objectives for Phases 1 & 2 combined: inc. 1000 watsan units, 4 rainwater fed systems, 3 gravity-fed systems, 60 shallow well rehabilitations • Both 1 & 2 phases were run from two project bases (2 hours apart), by two Project Managers, who both reported to the Deputy Country Director.

  10. Evaluation of initial project At the close of project, Medair’s survey indicated high beneficiary satisfaction However, an independent evaluation on behalf of one of the main donors, Tearfund UK, indicated serious water quality issues with a significant number of the 644 completed water treatment units A comprehensive study of all units was carried out by a Medair team and a repair programme developed using a new country team and a revised implementation approach Tearfund UK & Chaîne du Bonheur approved the new approach and agreed to fund these remedial works, due for completion in July 2009 Indonesia Aceh Project Review

  11. New household water treatment unit nearing completion Indonesia Aceh Project Review

  12. Approach 1 Two bases, both reporting to Deputy Country Director Many contractors in many villages Sign off by IRS/ NRS, not specified Trained some villagers for them to train their neighbours Monitoring by IRS and NRS was not structured MoUs/ regular authority contact not followed up Approach 2 One base, run by Country Director One contractor, in one place at one time Sign off by Construction managers Individual Training Daily Supervision, especially at key phases MoUs with local authorities in place and followed up Indonesia Aceh Lessons Learned

  13. Important to use a good local lawyer from the start in setting up contracts Important to ensure HR records are kept in order Important that good office set up, filing of beneficiary distribution lists, sign off sheets etc. kept in order from the beginning. Important to maintain relations with local authorities, not only at the start and when there are problems. Indonesia Aceh Lessons Learned Setting up with exit in mind

  14. Indonesia Aceh Lessons Learned Learnings • Desk Officer (DO) continuity: the DO changed 4 times during the first year of the project. No HQ Operations field trip was made for over a year. • Programme Selection and Mission Alignment: Was our intervention really responding to the most vulnerable or because Donor funding was available? • Inadequate management: At several levels there were failures in proper management. From NRS to contractors, IRS to NRS and CD to PMs & HQ follow up. • Contract Management: There was a lack of both construction and contractor management expertise; ensure the right staff are in place for the size/ complexity of project • Pilot innovative technical ideas yourself without relying on the opinion of others: “Don’t experiment with the lives of the poor”

  15. Indonesia Programme ultimate aim… “I really appreciate the time Medair takes on community relations. It is something they do really well.” Gregoire Labhardt, Funding Partner, Chaîne du Bonheur, during visit to Nias project Children enjoying clean water source in Hilizaria