The ECOSTILER project meeting on November 14, 2011, highlighted significant advancements across demo sites in Amsterdam, London, and Måbjerg. The key achievements include the completion of all refurbishment demonstrations, a functioning biogas plant, and ongoing testing of exhaust gases in a waste incinerator. Furthermore, a 12 km district heating backbone is now operational, serving roughly 4000 dwellings annually. Ongoing efforts include energy monitoring, optimization of CHP installations, and the finalization of research projects aimed at enhancing energy efficiency across all sites.
E N D
ECOSTILER, coordinators MEETING November 14, 2011
Demo sites • Amsterdam New West • London Lambeth • Måbjerg
Amsterdam 72 monthshighlights • All refurbishment demo’s complete • Biogas plant in waste to energy plant complete • Exhaustgases in waste incineratorbeingtested • District heatingbackbone of 12 km complete, currentconnectionrateabout 4000 dwellings/year • Renewables support program complete • Ongoing: monitoring of dwellings
London Lambeth 72 monthhighlights • All plannedrefurbishment buildings complete • (maybeonewillbeadded) • CHP installations complete, butbeingoptimized • R&D program complete • Somelooseendsbeingfinalized
Måbjerg 72 monthhighlights • Biogas plant constructionstarted August 2010 • All related research almostfinalized • To becompleted December 2011, Operation April 2012 • Auditing of Farms completed • Energy monitoring of farms ongoing • Energy efficiency measuresbeingexecuted.
Yet to do • Amsterdam • Finalizing of monitoring (buildings and biogas utilization) • London • Tentative: implementLoughboroughestaterefurbishment • Måbjerg • Make biogas plant operational • Executeenergy efficiency measures in stables • Monitoring