1 / 16

USDA RURAL DEVELOPMENT RURAL UTILITIES PROGRAM

USDA RURAL DEVELOPMENT RURAL UTILITIES PROGRAM. Technical Support Staff - State Engineers Marcy Newman, P.E. & John Helgren, P.E. . Construction Documents. RURAL DEVELOPMENT DOCUMENTS. http :// www.rurdev.usda.gov/home.html http:// www.rurdev.usda.gov/NY_WEP_Home.html.

hope
Télécharger la présentation

USDA RURAL DEVELOPMENT RURAL UTILITIES PROGRAM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. USDA RURAL DEVELOPMENT RURAL UTILITIES PROGRAM Technical Support Staff - State Engineers Marcy Newman, P.E. & John Helgren, P.E. Construction Documents

  2. RURAL DEVELOPMENT DOCUMENTS http://www.rurdev.usda.gov/home.html http://www.rurdev.usda.gov/NY_WEP_Home.html

  3. Construction Documents • Consulting Engineer prepares • Regulatory Agency reviews (NYSDEC, NYSDOH, County/Local DOH, NYSDOT, County/Local DOT, ARC, SRBC, USACOE) • RD State Engineer review and approve prior to bid • Owner’s Attorney review

  4. Construction Documents Engineers Joint Contract Document Committee (EJCDC)(2007/2010) with RUS Bulletin 1780-26 (10/09) for some forms and guidance No longer a separate Funding Agency edition

  5. RUS Bulletin 1780-26 • Information about engineering and contractor agreements • Advertisement for Bids (Attachment E) • Instruction to Bidders (Attachment F) • Bid Form (Attachment G) • Supplementary Conditions (Attach. H)

  6. Other Documents • Other USDA Forms: 400-6, 1940Q, 1048, Guide A • RUS Supplementary Conditions • Only change bracketed/italizied • Use Engineers Special Conditions for other items • Project Sign

  7. Wage Rates • NYS only required • Federal wage rates and Davis-Bacon required only if other Federal Agency is involved: HUD (GOSC), ARC, EDA or EFC is co-funding • Additional language for Fed. Rates • W/MBE not required by RD

  8. Seismic Requirements • All new above-ground structures must comply with the National Earthquake Hazards Reduction Program (NEHRP). • RD has a pre-printed form for the PE to fill out and sign

  9. RD Review of Documents • Project as identified in PER • Contract Provisions • Free and open competition • Make sense, modest in design? • Environmental mitigation measures from ER • Not re-engineer or regulatory compliance

  10. Open and Free • 1 Manufacturer and “or equal” – Change from 2 mfrs. • Pipe Materials: DI vs PVC vs HDPE • Tank type: LCA in PER or after Bid

  11. Other Items • Bid Schedule • No mfrs • Alternates: add alternates, full project from PER • Contract Price clear • Contract Times • Liquidated Damages • Permits

  12. Other Items, cont. • Soil boring/test pits • Property Ownership/Easements: permanent & temporary • Resident Inspection • ADA - buildings

  13. Procurement methods • Competitive sealed bids • Pre-Selection • Small purchases procedures • follow New York State Municipal Law • quotes from three qualified sources • Short form contract • Owner Construction/Self Help/Force Account-separate documentation required

  14. Pre-Selection • Equipment that impacts design • To obtain best price for equipment • Locked in Price for Bid of Project

  15. Submittal of Contract Documents • Submit one set of documents to State Engineer and Area Specialist; pre-bid • Letter of Conditions MUST have been issued and all conditions fulfilled • Letter of Review sent to PE • Call if significant issues • Acceptable for Bid Contingent on Changes

More Related