1 / 18

Grid Interconnection and Power Quality Assessment of Distributed Resources

Grid Interconnection and Power Quality Assessment of Distributed Resources. Farid Katiraei Ph.D. Candidate Department of Electrical and Computer Engineering University of Toronto. Wind Power Generation Symposium Feb. 20, 2004. Outline. DR connection process Utility impact assessment

hyman
Télécharger la présentation

Grid Interconnection and Power Quality Assessment of Distributed Resources

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Grid Interconnection and Power Quality Assessment of Distributed Resources Farid Katiraei Ph.D. Candidate Department of Electrical and Computer Engineering University of Toronto • Wind Power Generation Symposium • Feb. 20, 2004

  2. Outline • DR connection process • Utility impact assessment • Interconnection requirements • Power quality issues • Case studies: A Hybrid system

  3. Decentralized Power System

  4. Standards and Regulations • “IEEE Std. 1547, for interconnecting Distributed Resources with Electric Power System”, IEEE Standards, July 2003 • CSA Standard CAN3-C235, C325, C107.1 • “MicroPower Connect Interconnection Guideline”, July 2003 • Ontario Electrical Safety Code (OESC) • Ontario Energy Board Act, 1998 ( sec. 27.1) • Electric Safety Authority (ESA)

  5. DR Connection Process • Step 1: Basic planning - Data collection and Plan development, - Environmental assessment • Step 2: Feasibility study -Utility impact assessment, - Electrical inspection requirements (ESA) • Step 3: Implementation - Detailed design and review, - Basic interfacing equipments, - ESA plan approval • Step 4: Commissioning & Authorization of the connection • Step 5: Operation & Maintenance

  6. Utility Impact Assessment • Power quality assessment • Interconnection requirements • line/equipment upgrades • Grounding • Power flow • System protection modification • Fault currents, re-coordination • Synchronization

  7. Power Quality Issues • Voltage regulation (Load dependent) • Voltage fluctuation (not greater than 5%) • Flicker (No objectionable flicker) • Voltage Unbalance • Harmonic injection (TDD,THD < 5%) • DC injection (< 0.5% of In) • Reactive power requirements (Preferred pf. : 0.9 lag  0.95 lead) • Surge withstand performance ( up to 220% of the rated voltage)

  8. Study system • Impact assessments of a Hybrid system: DG1: 2 MVA gas-fired diesel generator DG2: 2.5 MVA electronically-interfaced DG3: 1.5 MW wind turbine (Rotor diameter 76m, Wind speed: 5-25 m/s, Hub height: 64m) Load demand: Sensitive load, Industrial/Residential load • Case I: Wind turbine start up • Scenario 1: Grid interconnected system • Scenario 2: Stand-alone system • Case II: Short circuit analysis • Line-Ground fault on the Utility side, Fault clearing

  9. Wind turbine start up • Direct connected generators: • Speeding up with the wind, connection at 85% of synchronous speed • Soft starter, limit start up current • Second winding (two speed turbines) • Electronically interfaced: • Synchronization • Wind farm: • Sequential start up

  10. I-1: Grid Connected System • Bus voltages • - Startup @ t=2.0 s

  11. I-1: Grid Connected System • Power variation • - Startup @ t=2.0 s

  12. I-2: Stand-alone System • Bus voltages • - Startup @ t=2.0 s

  13. I-2: Stand- alone System • Power variation • - Startup @ t=2.0 s

  14. Case II: Fault Analysis • Voltage fluctuation • - Fault @ t=0.5 s • - Clear @ • t=0.58 s

  15. Case II: Fault Analysis • Freq. variation • -Fault @ t=0.5 s • -Clear @ • t=0.58 s • -Reconnect • @ t=1.08s

  16. Conclusion • Comprehensive study of the system • Steady-state analysis • Dynamic Analysis • Appling uniform interconnection Standards

  17. Thank YouQuestion(s) ?

More Related