10 m. 0. 5 m. OVERVIEW: UCN Facility in Meson Hall. 40 . deflection:. 145 mr. 18.5 . 12 mr. SHIELDING (Schematic Layout). SHIELDING. CFI cost estimate  schematic layout, based on A.Trudel’s calc. s  $1820 K  Include stacking details of blocks (20% contingency)

Télécharger la présentation

5 m

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 10 m 0 5 m OVERVIEW:UCN Facility in Meson Hall 40 deflection: 145 mr 18.5 12 mr

  2. SHIELDING (Schematic Layout)

  3. SHIELDING CFI cost estimate  schematic layout, based on A.Trudel’s calc.s  $1820 K  Include stacking details of blocks (20% contingency) Latest cost estimate Based on vendor quotes  $2111 K Possible Cost savings  Dose in Skyshine direction can be higher (-1m from top) Existing Concrete (10%, $125K), Special Shielding Blocks (detailed layout, graphite?,…) “New” Steel Blocks (plate thickness) Shielding Quotes: Concrete $1251 k Steel (radioactive) $ 360 k (66%) Steel (new) $ 480 k (33%) • calculations by Anne Trudel: 40 mA, 500 MeV protons stopping in tungsten tgt • assumes 0.5 m empty space around target (no moderator) • figure shows shielding needed to reduce dose to 3 mSv/hr outside shielding • integrating shielding gives 125 m3 steel and 375 m3 concrete not allowing for practicalities of stacking the blocks.

  4. UCN Status: Update • Main Focus of Recent Activities: •  UCN Beamline design & cost estimates • Layout Installation Schedule with Vijay Verma • UCN Beamline design & cost estimates (progress summary): • Shielding  working on 2nd Iteration design and cost • Spallation Target & Remote Handling • Beamline Magnets & Power Supplies • Beamline Infrastructure • Cryogenics • Schedule (progress summary): • Proposed Installation Schedule from Vijay Verma

  5. OVERVIEW:Superfluid He UCN Source and EDM Exp.

  6. OVERVIEW:UCN Facility in Meson Hall (Note: New/updated drawing in ~ 2 weeks) 10 m 0 5 m 40 deflection: 145 mr 18.5 12 mr

  7. SHIELDING 1st Iteration  “schematic” shielding layout; cost estimate  $1820 K 2nd Iteration  more refined; based on A.Trudel’s calculations  Include stacking details of blocks; other possible cost savings  New layout (~ 2 weeks) & recosting in progress (S.Austen/C.Davis) • calculations by Anne Trudel, assuming 40 mA, 500 MeV protons stopping in tungsten target • assumes 0.5 m empty space around target (no moderator) • figure shows shielding needed to reduce dose to 3 mSv/hr outside shielding • integrating shielding gives 125 m3 steel and 375 m3 concrete not allowing for practicalities of stacking the blocks.

  8. Spallation Target • Remote Handling & Transportation Issues of concern (P.Bricault) • New calculations from Safety (A.Trudel) indicates target activity level after 10 years of irradiation will still be a factor of ~5 below the A2 transport limit • Present Spallation Target conceptual design  Tungsten Cylinder, 30 mm (D) x 120 mm (L) Target Geom. Optimization (MCNPX code): Troy Dawson (U.W. grad student)  Cooling System: High Pressure He OR Water Discussions w/ P.Bricault, Y.Masuda, G.Clark & others  leaning towards Water • Discussion of conceptual design for Remote-Handling System (P.Bricault) • New Engineer being hired for Target/RH design (?)  Costing…(P.Bricault)  A stopping target of tungsten bombarded with 100 uA of 500 MeV protons.  Blue arrows correspond to 1, 5 & 10 years of irradiation.  Shown below the arrow is the total activity as a fraction of the A2 transport limit.  The inventory of activity in the target at ten years is at approximately one fifth of the A2 transport limit for Type A packages.

  9. Beamline Magnets Magnets Design Power Supply Issues . Kicker (1AK1) M.Barnes M.Barnes/ABB Vector Fields calc. Switches  cost 1U Septum G.Clark G.ClarkRad-hardness Bender 1 (1UB1) G.Clark*M11 Bender (KR/DL/FM) Impact on BL1A D-Pace ? 1B Bender (overkill) Retrofit existing ? Quad 1 (1UQ1) From M20 From M20 Quad P.S. Refurbish Quad 2 (1UQ2) From M20 From M20 Quad P.S. Bender 2 (1UB2) From PIF From PIF Refurbish

  10. Preliminary Coil Design for UCN Kicker Kicker Specs: Kicker Power Supply • 500 MeV protons (p = 1090 MeV/c) • 15 mr maximum deflection (Bdl = 0.0545 Tm); normal deflection 12mr • effective length 1.5 m (physical available 2 m) • aperture 100 mm x 100 mm (possibly 130 mm horiz) • field uniform to 5% over central 80 mm diameter region • flat top 1 ms, flat to 5% over the 1 ms • fires every 3 ms (330 Hz rep. rate, able to run cont.) • can be re-configured (in <1 hr) to run as low as 100 Hz rep rate • power supply able to be located 10 m away

  11. Beamline Infrastructure Beampipe & Hardware, Vacuum, Diagnostics, Controls, Safety, Services Cost Estimate  Discussions with A.Hurst & others  Relevant documents forwarded to Andy for review  Identify missing components in existing Resource Chart  Provide updated cost estimate for BL infrastructure Power Budget/Capacity  Discussions with F.Mammarella  Capacity of substation transf  Does not look like it should be a problem ( M11+M13  UCN )  Revisit after magnet P.S. details clarified  “New” load from He Liquifier needs to be included Cryogenics TRIUMF LHe capacity in 5YP  Enough to meet UCN requirements? Discussions with I.Sekatchev  UCN requirements can be met (and then some)  Igor’s proposed liquifier has enough capacity to service UCN as well as other Meson Hall expts (UCN requires ~1000 L.L./day) (Linde L140 can provide ~ 3300 L.L./day) Cost Estimates  Liquifier costs  5YP  UCN-incurred costs - He Transfer Lines - dependent on Liquifier siting/location (Chuck, Igor, Stu)

  12. Installation Schedule Vijay’s Proposed Installation Schedule for UCN (refining timetable & manpower) 2011 2012 2013 2014 Shutdown Shutdown Shutdown Task 1 Task 1 Task 2,3,4 Task 5,6 Task 7 Task 7 Task • 1* Remove M11 “cold” end (3 wk) Jan 2011 shutdown or Sep 2011 • 2 Remove M11-Q1, Q2, B1, (3 wk) Jan 2012 shutdown • & blank off M11 septum • 3 Remove M13-Q1 to Q7 (6 wk) • 4* Remove PIENU (4 wk) • 5 Take out 1BVB2 (1 wk) Jan 2013 shutdown • Remove balance of 1B and PIF (3 wk) • Install Kicker, Septum, 1UB1, 1UQ1-Q2, (5 mo) • & restore shielding to allow 1A running • 6* Install PIF in new location (6 wk) • 7* Install 1UB2, Spallation Target, Shielding, (4 mo) Partially Jul-Dec 2012 (whenever possible) • & UCN equipment and finish between Jul 2013 – Apr 2014 • * No shutdown required

  13. Installation Schedule & Manpower Requirements UCN INSTALLATION TASKS (Based on Vijay's and Des Ramsay’s notes of the 20 Nov 2009 meeting) TASK Remove M11 cold end. No shutdown required. 3 weeks. 3 Techs + crane and riggers + some support from other groups Remove M11 (Q1,Q2,B1,blank off Septum) Meson Hall shutdown only. 3 weeks. 3 Techs + remote handling + crane and riggers + support from other groups Remove M13 (Q1 to Q7) Meson Hall shutdown only. 6 weeks. 3 Techs + crane and riggers + some support from other groups Remove PIENU No shutdown required. Can be done anytime once PIENU finished. 4 weeks. 3 Techs + crane and riggers + some support from other groups Take out 1BVB2. Kicker will go here. 1BVB2 will also be used on UCN.  Requires Cyclotron shutdown (vault access) 1 week. 3 Techs + crane and riggers + some support from other groups Remove balance of beamline 1B and PIF  Requires Cyclotron shutdown (at least for upstream 1B). 3 weeks. 3 Techs + crane and riggers + some support from other groups Install Kicker, Septum, 1UB1, 1UQ1, 1UQ2, and restore enough shielding to run Meson Hall. To make room for the shielding, may be necessary to leave 1UQ1 and/or 1UQ2 out temporarily  Requires vault and meson hall access. 5 months. 4 Techs, crane and riggers, support from other groups Install 1UQ1 and 1UQ2 if not installed during the long shutdown.  Requires meson hall shutdown only. 4 weeks. 3 Techs + crane and riggers + some support from other groups Install PIF in new location. No shutdown required. 6 weeks. 3 Techs + crane and riggers + some support from other groups Install 1UB2, spallation target, shielding, UCN equipment.  No shutdown required. 4 months. 3 Techs + crane and riggers + some support from other groups In addition, 6 months or so of prep work will have to be done refurbishing magnets, installing water headers on magnets, preparing vacuum boxes and stands,etc. I guess this would tie up mostly beamlines techs. Total “Shutdown” Time(s): Cyclotron shutdown 5.5 months At least meson hall shutdown 3 months No shutdown required 6.5 months

  14. UCN Important Dates Dec 5-15 UCN Experiment Run at RCNP-Osaka Jan 20-22 UCN Collaboration Meeting at TRIUMF ??? Gate 2 Review at TRIUMF Late March CFI Re-submission Apr 8-9 UCN Workshop at RCNP-Osaka

  15. SHIELDING (1st Iteration): How much room does it need? 1st Iteration costing  Jeff Martin

  16. Example of Proton Beam Sharing 120 mA 120 mA 80 mA meson hall 0 40 mA UCN source 0 mA 0 mA 0 1 min. 4 min.

  17. 10 ms to40 ms Proposed time division of beam normal TRIUMF beam, 4 min. 1 ms 120 mA 0 2 ms 2 ms 120 mA 0 2/3 beam to mSR 0 1 ms 1 ms 1 min. 120 mA 1/3 beam to UCN 0

  18. A stopping target of tungsten bombarded with 100 uA of 500 MeV protons. • Blue arrows correspond to 1, 5 and 10 years of irradiation. • Shown below the arrow is the total activity as a fraction of the A2 transport limit. • The inventory of activity in the target at ten years is at approximately one fifth of the A2 transport limit for Type A packages. Anne Trudel

  19. Preliminary Coil Design for UCN Kicker Mike Barnes

  20. UCN Kicker Mike Barnes

  21. Kicker Specs: • 500 MeV protons (p = 1090 MeV/c) • 15 mr maximum deflection (Bdl = 0.0545 Tm); normal deflection 12mr • effective length 1.5 m (physical available 2 m) • aperture 100 mm x 100 mm (possibly 130 mm horizontal) • field uniform to 5% over central 80 mm diameter region • flat top 1 ms, flat to 5% over the 1 ms • fires every 3 ms (330 Hz rep. rate, able to run continuously) • can be re-configured (in <1 hr) to run as low as 100 Hz rep rate • power supply able to be located 10 m away Examples:

  22. Kicker Power Supply

  23. Kicker Power Supply Ramp-Up: + - SW1 and SW2 are closed, magnet ramps up from the high voltage

  24. Kicker Power Supply End of Ramp-Up: + - SW1 is opened. Current circulates through D3, D1, and SW2

  25. Kicker Power Supply Flat Top: + - + - SW3 closes as required to maintain the flattop with the low voltage supply

  26. Kicker Power Supply Ramp-Down: + - All switches open. Current is against the HV for fast ramp down. Stops at I=0 when diodes become back biased.