An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RENAISSANCE LYONWP Progress and PlansWP 0.2: National Management Béatrice Couturier & Malorie CLERMONT Local coordination - Grand Lyon & Hespul

  2. WP 0.2: National Management WP 1: Research, Technological and Innovation Development WP 1,1: finished WP 1,3: technical and juridical assistance on heating systems WP 1,4: study on the impacts of the Concerto programme in social housing WP 1,5: Local action plan: questionnaires and booklet WP 2: Monitoring and Analysis WP 2,1: impact of the PV systems on the electrical distribution networks WP 2,2: detailed monitoring and lab monitoring WP 2,3: exchange with Spanish partners WP 3: Demonstration WP 4: Dissemination and Promotion WP 5: Training WP 5,1 & 5,2: organisation of the 1st training sessions for workers

  3. WP 0.2: National Management State of progress year 3: 6 last months Thematic/transversal meetings : - WP 1.5: work on the 1st questionnaires for inhabitants (step 2) : work on the “Welcome and orientation booklet”: advices for a “green behaviour” • - WP 4 : dissemination protocol: updating and follow-up • : “Welcome and orientation booklet”: addition of Concerto information (2 pages) - WP 5: preparation of the training sessions for on-site workers (May/June 2009) 2

  4. WP 0.2: National Management State of progress year 3: 6 last months - CSG 11/12/2008 • WP 1.5: conclusions step 1 • WP 5: training sessions - Delays in demonstration site / Concerto contract - WP 4: dissemination protocol - CSG 27/03/2008 - WP 5: training sessions • WP 1.5: step 2 - Inspection visits of the construction site: blocks A, B, C • 3rd Progress Report finished • Redaction of the document to ask for a prolongation of the Renaissance contract: drafted in Lyon

  5. WP 0.2: National Management Analysis of progress • 2 CSG meetings since the last PSG (Oct. 2008): with the objective of 4/year • In time • 3rd annual progress report: some difficulties to be in time • For the 4th and successive reporting process, it is necessary to work on improving this process to finalise it in time • Delays of construction • impact on others WP such as WP2 and WP1.5 (WP1.4), WP4, WP5

  6. WP 0.2: National Management Plans for the next 6 months - Organisation of 2 local meetings (CSG) at a minimum (ie: in June and September) • Regional Site Visit of ConcertoPlus in Ajaccio (June 2009) with French and Swiss Concerto partners • Next PSG in Zaragoza (to be determined) • 4th Annual Progress Report …

  7. WP 0.2: National Management Overview : Plans for the next 6 months WP 1: Research, Technological and Innovation Development WP 1,3: ESCo WP 1,4: study on the impacts of the Concerto programme in social housing WP 1,5: to finish step 2, to begin step 3 WP 2: Monitoring and Analysis WP 2,1: monitoring of PV systems WP 2,2: detailed monitoring and lab monitoring WP 2,3: exchange with Spanish partners and ConcertoPlus team WP 3: Demonstration Block A:Arrival of the 1st inhabitants (60 dwellings) –September 2009 WP 4: Dissemination and Promotion Follow up and up dating the Dissemination strategy WP 5: Training WP 5,2: training sessions on outside insulation and ventilation (air tightness)