1 / 45

ETI 4448 Applied Project Management

ETI 4448 Applied Project Management. Prof. Roy Levow Session 4. Building the Work Breakdown Structure (Ch. 4) -- Outline. The Work Breakdown Structure Uses for the WBS Generating the WBS Six Criteria to Test for Completeness in the WBS Approaches to Building the WBS Representing the WBS.

Télécharger la présentation

ETI 4448 Applied Project Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ETI 4448Applied Project Management Prof. Roy Levow Session 4

  2. Building the Work Breakdown Structure (Ch. 4) -- Outline • The Work Breakdown Structure • Uses for the WBS • Generating the WBS • Six Criteria to Test for Completeness in the WBS • Approaches to Building the WBS • Representing the WBS

  3. Work Breakdown Structure • “A hierarchical description of the work that must be done to complete the project as defined in the Project Overview Statement.” • Inputs • POS • Requirements Document • Terms • Activity: Chunk of work • Tasks: Smaller chunk of work. Activities are made up of tasks • Work Package: Complete description of how the tasks that make up the activity will actually be done

  4. Decomposition • The process of breaking down work into a hierarchy of activities, tasks, and work packages • Uses • Estimate Duration • Determine Resources • Schedule Work

  5. Uses for the WBS • Thought Process Tool • Architectural Design Tool • Planning Tool • Project Status Reporting Tool

  6. Generating the WBS • Top-Down Approach: Start with goal and continue to partition work until it has been sufficiently defined • Team Approach Variation • Subteam Approach Variation • Bottom-Up Approach: First-level tasks are identified. Then groups are formed around first-level tasks where these groups brainstorm the activities needed to complete the first-level task.

  7. WBS for Specific Projects • Small Projects – Consider mindmapping • Diagram relating components radiating out from central element (Ref: Wikipedia article) • Large Projects – Intermediate WBS • Adaptive and Extreme Projects – Iterative WBS

  8. Six Criteria to Test for WBS Completeness • Status/Completion is measurable • The activity is bounded • The activity has a deliverable • Time and cost are easily estimated • Activity duration is within acceptable limits • Work assignments are independent Seventh Criteria – Project manager’s judgment that the WBS is not complete

  9. Exceptions to the Completion Criteria Rule • Stopping Before Completion Criteria Are Met • Decomposing Beyond Completion of the Criteria

  10. Approaches to Building the WBS • Noun-type: In terms of the components of the deliverable • Physical Decomposition • Functional Decomposition • Verb-type: In terms of the actions that must be done to produce the deliverable • Design-build-test-implement • Objectives • Organizational: In terms of the units that will create the deliverable • Geographic • Departmental • Business Process

  11. Representing WBSTree Structure

  12. Representing WBSIndented Outline

  13. Representing WBSWaterfall Structure

  14. Estimating Duration, Resource Requirements, and Cost – Ch. 5 Outline • Estimating Duration • Estimating Resource Requirements • Estimating Duration as a Function of Resource Availability • Estimating Cost • Using a JPP Session to Estimate Duration, Resource Requirements, and Cost

  15. Estimating Duration • The difference between Duration and Work Effort

  16. Resource Loading Versus Task Duration • Crashing the task – adding more resources to preserve duration • Diminishing returns • Crashpoint: adding more resources INCREASES task duration • Considerations • Not always feasible (Can nine women have a baby in one month?) • Communication overhead increases • Risk increases

  17. Variation in Task Duration • Varying skill levels • Unexpected events • Efficiency of work time • Mistakes and misunderstandings • Common cause variation

  18. Six Methods for Estimating Task Duration • Similarity to other activities • Historical Data • Expert Advice • Delphi Technique • Group of experts individually estimate duration • Then, average of the estimates is calculated • Do it two more times • Three-Point Technique • most optimistic estimate, most pessimistic estimate, and most likely estimate, which are then averaged • Wide-band Delphi Technique • Combination of Delphi and Three-Point techniques

  19. Estimation Life Cycles “Early estimates will not be as good as later estimates.”

  20. Estimating Resource Requirements • Types of resources • People • Facilities • Equipment • Money • Materials

  21. People as Resources • Skills Matrices • Skills needed inventory • Skills currently on hand inventory • Skill Categories: uniform listing of skills • Skill Levels: level of expertise in a particular skill

  22. Resource Breakdown Structure Used to estimate resource and costs by showing the positions needed for a particular project

  23. Estimating Duration as a Function of Resource Availability • Three variables influence Duration Estimate • Duration • Total amount of work (hours/days) • Percent per day that person can devote to task • Methods for Estimating Duration • Assign as a Total Work and a Constant Percent/Day • 40 hours / 0.50 = 80 hours • Assign as a Duration and Total Work Effort • 5 person days / 10 days = 0.5 • Assign as a Duration and Percent/Day • 10 days X 0.50 = 5 person days • Assign as a Profile (when using multiple resources)

  24. Estimating Cost • Resource Planning • Trading money for time (depends on skill level) • Part-time workers (think of ramp-up time) • Don’t overschedule resources • Cost Estimating • Order of magnitude estimate • Estimate is 25% above and 75% below final number • Budget estimate • Estimate is 10% above and 25% below final number • Definitive estimate • Estimate is 5% above and 10% below final number

  25. Cost Budgeting and Cost Control • Cost Budgeting – Assign costs to tasks on the WBS • Cost Control – Two major issues • How often report of costs is needed • Depends on risk and need to spot developing problems • Use of a cost baseline to spot cost variances when you receive actual figures

  26. Using Joint Project Planning Session to Estimate Duration, Resource Requirements, and Cost Advice from the author: • Get it roughly right • Spend more effort on front-end activities than on back-end activities • Consensus is all that is needed

  27. Constructing and Analyzing the Project Network Diagram – Ch. 6 Outline • The Project Network Diagram • Building the Network Diagram Using the Precedence Diagramming Method • Analyzing the Initial Project Network Diagram • Using the JPP Session to Construct and Analyze the Network

  28. The Project Network Diagram • Definition: “A pictorial representation of the sequence in which the project work can be done.” • What is needed to construct diagram • Tasks • Task Duration • Earliest time to start task • Earliest expected completion date for the project

  29. Gantt Chart • Older than the project network diagram • Rectangular bars that show the duration by length • Placed along a timeline in sequence • Does not indicate what task needs to be done before and after a task • Does not indicate if the project planning is most effective or efficient

  30. Advantages of the Project Network Diagram • Planning – Visual overview of the project that is easy to use for scheduling • Implementation – Software exists that automatically updates task dates and duration • Control – Project manager can better schedule tasks and spot variances

  31. Building a Network Diagram Early Method – Task-On-the-Arrow (TOA)

  32. Building a Network Diagram Precedence Diagramming Method (PDM)

  33. Using PDM • First, every task in the WBS has a task node

  34. Using PDM (Cont.) • Second, determine the sequence of tasks • Every task has at least one predecessor and at least one successor • EXCEPT • Start Task has no predecessor • End Task has no successor • Diagram the connections

  35. Using PDM (Cont.) Diagramming connections between tasks

  36. Using PDM (Cont.) Four Kinds of Task Dependencies

  37. Constraints Determine Task Dependencies • Technical Constraints • Discretionary • Best-Practices • Logical • Unique • Management Constraints • Interproject Constraints • Date Constraints

  38. Lag Variables • Pauses or delays between tasks • Can be intentional • Also created by constraints

  39. Creating the Initial Project Schedule • Compute two schedules • Early schedule – use Forward Pass • Late schedule – use Backward Pass Forward Pass Backward Pass What’s different?

  40. Critical Path • “The longest duration path in the network diagram” • “The sequence of tasks whose early schedule and late schedule are the same” • “The sequence of tasks with zero slack or float” The Critical Path Determines the Completion Date of the Project

  41. Calculating Critical Path • First method – add up all of the path’s durations. The longest one is the critical path.

  42. Calculating Critical Path (Cont.) • Second method – Compute the slack time • The amount of delay (in time units) in starting a task that will not affect the project completion date • Difference between late finish and early finish of a slack time • Do not include holidays, weekends, and similar such time • Two types of slack • Free slack – amount of delay for a task without causing a delay in the early start of immediate successor task(s) • Total slack – amount of delay for a task without delaying the project completion date

  43. Analyzing the Initial Project Network Diagram • Crashing the schedule: necessary when the initial project network diagram shows a projected completion date that is later than the requested completion date. • Strategies • Examine the Critical Path to see if you can move tasks off the Critical Path • Partition tasks into parallel subtasks • Concerns • Increase in risk • More communication and coordination needed

  44. Example of Schedule Compression

  45. Management Reserve • Padding task duration • Individual task level • Project level • Bad at the task level • BUT, good at the project level • Accounts for risk • Incentive (management reserve time not used can be the basis for bonus)

More Related