Managing Decommissioning Risks for Government

Managing Decommissioning Risks for Government. Keith Mayo Head of Offshore Decommissioning Unit, Department of Energy and Climate Change . Key Event - Energy Act 2008. Brings legislation on oil and gas decommissioning up to date Uses lessons learned

jacoba
Télécharger la présentation

Managing Decommissioning Risks for Government

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Managing Decommissioning Risks for Government Keith Mayo Head of Offshore Decommissioning Unit, Department of Energy and Climate Change

  2. Key Event - Energy Act 2008 • Brings legislation on oil and gas decommissioning up to date • Uses lessons learned • All licensees become liable at same time • Pipeline owners made liable when construction not production starts • Widens powers to require financial information and guarantees

  3. DECC Concerns • Failure of banking sector to provide credit and guarantees • Brought forward date for implementation of Act • Decommissioning provisions in force from 26 January • Issued new version (3) of Guidance Notes • https://www.og.berr.gov.uk/regulation/guidance/decommission.htm

  4. Industry Concerns Addressed • Licensees not liable if they have never been entitled to benefit from the field • Act and guidance notes explain “benefit” • A share of the oil or gas production • Owners of host platform not liable for other owners’ tieback • “Manager” is the operator

  5. Financial guarantees • Can now be required at any time • New fields, licence transfers or other changes • Reviews of financial positions, especially during credit shortage • Will compare decom costs to net worth • If over 50% - discuss security with company • Legal notice requiring guarantee

  6. Decommissioning Estimates • £15 billions for UKCS at 2006 figures • 20% inflation in 2007 and 2008 • £22 billions at 2008 peak • Costs falling back now? • >5000 wells for £5 bn to £15 bn • New study by consultants • £20 billion? at current prices

  7. No Activity Chart • Operator predictions on 2P basis – pessimistic? • In 2008, predictions for 39 fields changed by 5 or more years • 25 fields extended,14 fields shortened • Predictions cluster around licence expiry • Also around 2015, 2020, 2025 • Actuals don’t support predictions • More uncertainties with smaller fields

  8. Operators CoP Predictions 2006,7,8

  9. What is DECC? • Set up by the Prime Minister on 3 October • Greater focus on solving twin challenges of climate change and energy supply • Lead on UK responsibility for meeting climate change targets • Develop policies on affordable, secure and sustainable energy supplies

  10. DECC activity • Setting up resources, systems and plans for a completely new organisation Three groups 1. Mobilise the transition to low carbon UK 2. Pursue international co-operation 3. Nuclear/Renewables/Clean fossil fuels

  11. Impact on oil and gas - longer term • UK to achieve 80% cut in emissions by 2050 ═ zero carbon electricity generation • EU ETS covers operations on UKCS platforms • Will CCS be essential to enable us to keep producing from UKCS? • Will drive for low carbon bring forward decommissioning of older facilities? • But still need to make the most of UK resources

  12. What we are doing • Encouraging projects tackling emissions and strengthening security of supply • Energy Bill sets frameworks • CCS projects regulated like oil and gas • Unloading and storage of hydrocarbon gas • Gives clarity for developers • Supports re-use of oil and gas infrastructure

  13. Impact on decommissioning - longer term • Decommissioning activity will have to become low carbon • Not an excuse to dump on the seabed • Low carbon options preferred if key impacts are similar • e.g. concrete structures and cuttings piles • More attention to emissions data in EIAs

  14. Low carbon decommissioning? • Heavy lift • Single lift • Piece small • Buoyancy float back • Rig or vessel well abandonment • DP or anchors • Which options will cut emissions?

  15. Tough Times Ahead? Short term • Banks failing to provide credit and guarantees • Company failures • Oil prices and costs rising again, or falling? Longer term • Drive for low carbon re-use of infrastructure • Low carbon options for decommissioning