550 likes | 969 Vues
Construction Estimating Using Excel Professor Locurcio CON4003, CVE4073, CVE5073. Fundamentals of Quantity Takeoff Chapter 4. Outline. Performing Quantity Take Offs Work Packages Communication in the Field Counted Items Linear Components Sheet and Roll Items Volumetric Goods
E N D
Construction Estimating Using Excel Professor Locurcio CON4003, CVE4073, CVE5073 Fundamentals of Quantity TakeoffChapter 4
Outline • Performing Quantity Take Offs • Work Packages • Communication in the Field • Counted Items • Linear Components • Sheet and Roll Items • Volumetric Goods • Quantity-From-Quantity Goods • Waste
Quantity Take Off • The process of preparing a complete list of all components needed to complete the project • Includes all components including site and direct overhead • Units include all common units (feet, sq. feet, yards, etc.), months, each, and lump sum
Performing Takeoffs • Determine all materials, equipment, and labor • Building the project from the bottom up in the mind • Example: Prehung Door
Work Packages • Related labor tasks are divided into work packages • Job cost codes may be broken into multiple work packages • Example: The same lumber used in different floors of a building • Should match project sequence and scheduling
Footing and Wall Packages • Foundation wall package (top) • Foundation footing package (bottom) • Anchor bolts are placed in concrete first, so they are part of the wall package
Field Communication • Estimators and workers need to communicate to prevent delays in the project • Methods and procedures can differ, creating problems
Materials Categories • Counted Items • Linear Components • Sheet and Roll Items • Volumetric Goods • Quantity-From-Quantity Goods
Counted Items • Simplest way to determine quantity • Important to check off items already counted • Count repetitive items using equations (????)
Counted Items Cont'd • Members at both ends, Eqn. 4-1 Number = (Distance / Spacing)+1 • Member at one end, Eqn. 4-2 Number = (Distance / Spacing) • No end members, Eqn. 4-3 Number = (Distance / Spacing)-1
Examples + 1 16 120 ft.
Linear Components • Components measured by length • Can be connected with lap or butt joints
Effective Length • Distance between the start of two linear components • Number = (Length / Effective Length)
Area Measurements(Sheet and Roll Goods) • Components measured by area • Can be butt, lap, or spaced jointed • Two methods: Area and Row/Column
Examples 50ft 8ft 15 5/8” 3/8” Effective Area 8 x 18 = 128 in3 8” 16”
Row and Column Method Cont'd Number = (NumberRows)(NumberColumns) Eqn. 4-18 Example:
Volumetric Goods (Concrete, Sand, Rock) Volume = (Length)(Width)(Height) Eqn. 4-19 • Additional volume formulas in Appendix A • Example
Quantity-From-Quantity • Quantity estimated from another quantity Examples: • 1 gal paint covers 250sf of wall • 1 lb of nails covers 100sf of roofing
Waste • Unavoidable waste should be included • Expressed as a percentage of calculated quantity
Solution Distance = 120 ft = 120 ft (12 in/1 ft) = 1,440 inches Spacing = 16 inches on center Number = (1,440 inches / 16 inches) + 1 = 91 studs
Homework • Book problems only ask for quantity • I require…. • Quantity… plus • Material Cost • Equipment Cost • Labor Cost • Total Cost per unit • Excel Format
Using RSMeans • Identify items to be counted • Determine quantities needed for each item • Select “correct” RSMeans item – CSI format • Cite RSMeans line item selected • Use Excel columns for Material & Labor Costs • Note… cite units for all items • Differs from item to item • Differs from text questions • Determine total cost for each item • Sum all line item costs for materials & labor • Add OH & Profit at end
Questions? • Homework due for Thursday…. • Shed Estimate… 3 documents • Cover sheet • Transmittal letter w/total cost • Excel sheet with itemized costs