1 / 23

Entergy Mississippi, Inc. Proposed Transmission Reliability Projects

Entergy Mississippi, Inc. Proposed Transmission Reliability Projects. Transmission Planning Summit. 2008 - 2012 EMI Transmission Reliability Projects. Horn Lake – TH Allen 161kV Line Upgrade 2009. Grenada/Winona/Greenwood Area Improvement 2011. Hollandale/Belzoni Breakers 2011.

jalene
Télécharger la présentation

Entergy Mississippi, Inc. Proposed Transmission Reliability Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Entergy Mississippi, Inc.Proposed Transmission Reliability Projects Transmission Planning Summit

  2. 2008 - 2012 EMI Transmission Reliability Projects Horn Lake – TH Allen 161kV Line Upgrade 2009 Grenada/Winona/Greenwood Area Improvement 2011 Hollandale/Belzoni Breakers 2011 Indianola-Greenwood 115 kV 2009 Ray Braswell –Byram 115kV Line 2011 Ridgeland - Madison Reliability Improvement 2012 Natchez D-Var and Capacitor Banks 2008 Rankin-Ind. – Airport 115 kV 2009 Liberty – Gloster 115 kV 2009 Liberty – Gillsburg 115 kV 2009

  3. 2008 Natchez SES:Install D-Var and Capacitor Bank Scenario: • The Natchez area is served by five 115 kV lines out of Franklin, Baxter Wilson, Liberty, Swartz, and Standard. The load in the area in 2009 will be 482 MW. • The single contingency loss of any one of the five lines feeding into the area will cause low voltages at various substations. Recommended Solution: • Install two 30 MVAr capacitor banks at Natchez SES and refurbish and relocate two +/- 8MVAr D-VAR systems from Texas to Natchez SES. • Estimated Cost: $8 MM

  4. Natchez SVC and Capacitor Bank

  5. 2009 Liberty - Gillsburg 115 kV: Upgrade Capacity of Line Scenario: • The Liberty - Gillsburg 115kV line, located in southern Mississippi, is approximately 15 miles long and is limited to a rating of 69 MVA. • The loss of the Franklin – Bogalusa EHV line will cause the line to overload. Recommended Solution: • Re-conductor the Liberty – Gillsburg line and increase the rating of the line to 103 MVA. • Estimated Cost: $7 MM

  6. Liberty - Gillsburg 115 kV: Upgrade capacity of line

  7. 2009 Liberty - Gloster 115 kV: Upgrade Capacity of Line Scenario: • The Liberty - Gloster 115kV line, located in southern Mississippi, is 20 miles long and is limited to a rating of 108 MVA. • The loss of the Franklin – Meadville 115 kV line or the S. Vicksburg – Port Gibson 115 kV line will cause the line to overload. Recommended Solution: • Re-conductor the Liberty – Gloster line and increase the rating of the line to 190 MVA. • Estimated Cost: $4.4 MM

  8. Liberty - Gloster 115 kV: Upgrade capacity of line

  9. 2009 Indianola - Greenwood Line Upgrade Scenario: • The Indianola - Greenwood 115kV line, located in central Mississippi, is 28 miles long and is limited to a rating of 120 MVA by equipment in the Moorhead, Itta Bena, and Greenwood substations. • The loss of the several lines in the area including Pickens - Durant 115kV and Delta - Ruleville 115kV will cause the line to overload. Recommended Solution: • Replace the affected substation equipment and increase the rating of the line to 161 MVA. • Estimated Cost: $250 K

  10. Indianola - Greenwood Line Upgrade

  11. 2009 Horn Lake:Energize 230/161kV Autotransformer & Upgrade Horn Lake – Allen (TVA) 161kV Line Scenario: • The load in the Southaven and Senatobia areas, served by one 230 kV line and two 115 kV lines, will total approximately 406 MW in 2009. • The single contingency loss of the Freeport – Horn Lake 230kV line will cause low voltages at 9 substations. Recommended Solution: • Reconductor the Horn Lake – TH Allen (TVA) 161kV line to a rating of at least 390 MVA and energize the idle 230/161kV autotransformer at Horn Lake. • Estimated Cost: $3.5 MM

  12. HornLake 230/161kV Auto & Allen Line Upgrade

  13. 2011 Rankin Ind. - Airport Reconductor Scenario: • The Rankin Ind. - Airport 115kV line, located in near Jackson Mississippi, is 5.5 miles long and is limited to a rating of 161 MVA. • The loss of the 230/115kV autotransformer at Rankin will cause the line to overload. Recommended Solution: • Re-conductor the Rankin Ind. - Airport 115kV line and increase the rating of the line to 231 MVA. • Estimated Cost: $3 MM

  14. Rankin Ind. - Airport Reconductor

  15. 2012 Ridgeland-Madison Reliability Improvement Scenario: • The Lakeover -NE Jackson - Rex Brown 115 kV line is 25 miles long and will serve 6 substations totaling 194 MW in 2009. • The loss of the Rex Brown - Hico, Hico - N. Jackson or N. Jackson - Canton Rd 115 kV lines in 2008 causes overloads on the Lakeover - Livingston Rd 115 kV line. The loss of the Lakeover - Livingston Rd or Livingston Rd - Ridgeland 115kV lines causes the Rex Brown - Hico - N. Jackson 115kV lines to overload. Recommended Solution: • Build a 115kV substation in the existing Northpark 230kV substation and cut in the Lakeover-NE Jackson line at Northpark (between Ridgeland and Country Club). Double-Circuit the existing Lakeover–Livingston–Ridgeland 115 kV line, upgrading the existing line to at least 231 MVA, and connect the new circuit to the new 115kV bus at the Northpark substation. This new circuit will be used for the feed to the new Sunnybrook substation. • Estimated Cost: $13 MM

  16. Sunnybrook Northpark 115 Ridgeland-Madison Reliability Improvement

  17. 2011 Ray Braswell – Byram 115 kV LineConstruction Scenario: • The SW Jackson to Byram to Brookhaven line is 53 miles long and serves 162 MW of load. • The loss of the SW Jackson to Elton or Elton to Byram 115 kV lines will cause overloads on three line sections from Brookhaven to Hazlehurst 115 kV and undervoltages on various buses in 2008. • In addition, the loss of Brookhaven - Wesson or Wesson - James Rd. will cause overloads on two line sections from SW Jackson to Byram. Recommended Solution: • Build a new 115 kV line from Ray Braswell to Byram 115 kV substation with a rating of at least 261 MVA. • Estimated Cost: $23 MM

  18. Ray Braswell – Byram115 kV Line Construction

  19. 2011 Hollandale - Belzoni Breakers Scenario: • The N.Vicksburg - Rolling Fork - Greenville line is 81 miles long and will serve 109 MW of load in 2009. The Indianola - Yazoo City line is 51 miles long and will serve 35 MW. When either end of the N.Vicksburg - Rolling Fork - Greenville line is open, the buses along the line have low voltages, and when the North end of the Indianola - Yazoo City line is open, Inverness, Isola, and Belzoni substation have low voltages. Recommended Solution: • Install breakers at Hollandale and near the Belzoni SS / Midnight substation to close the normally open section between Belzoni SS and Murphy. Install a 21.4 MVAR capacitor bank at the Rolling Fork Substation. • Estimated Cost: $4 MM

  20. Hollandale - Belzoni Breakers

  21. 2011 Tillatoba - South Grenada:Build New 230 kV Line and Install 230/115 Auto at S. Grenada Scenario: • The Greenwood, Winona, and Grenada area is supplied by five 115kV lines and will serve 390 MW in 2009. • The loss of one of these five 115 kV lines or the loss of the Tillatoba 230/115kV auto will cause various bus undervoltages and overloads on 2 115kV lines. Recommended Solution: • Build a 230kV line from Tillatoba to S. Grenada and install a 230/115kV autotransformer at S. Grenada. Install a capacitor bank at Schlater (21 MVAR), an additional bank at Winona (21 MVAR) and upgrade the bank at Greenwood (32 MVAR) Estimated Cost: $45 MM

  22. Tillatoba - S. Grenada: Build New 230 kV Line & South Grenada Auto

  23. EMI Transmission System Target Areas 2013 and Beyond • Southhaven Area • Build 2 New 230 kV lines • Madison/N. Jackson Area • Lakeover-Pickens 230 kV line • Northpark 230/115kV Auto • Franklin Area • New 230kV Substation • Build 2 New 230kV Lines

More Related